You are on page 1of 12

Evidence Plan

Competency ELECTRICAL INSTALLATION AND MAINTENANCE NC II


standard:
Unit of PERFORM ROUGHING-IN ACTIVITIES, WIRING AND
competency: CABLING WORKS FOR SINGLE PHASE DISTRIBUTION,
POWER, LIGHTING AND AUXILIARY SYSTEM.
Ways in which evidence will be collected:
[tick the column]

Third party Report


Demonstration &
Observation &

Portfolio

Written
The evidence must show that the trainee…
 *Interpret correct drawing based on job
/ / /
requirements
 Determine correct quantities of conduit, fittings
/ /
and materials as per job requirements
 Select tools, and equipments as per job
/ /
requirements
*Installed and assemble conduit ensuring that
fittings are fully inserted ,tightened and / /
threaded as per job requirements
 Conduit is bent with bends not exceeding 90˚
/ /
as per standard and job requirements
*Installed wire ways and cable tray / /
 *Prepare cable pulling, wiring installation and
/ /
lay-out
 Follow safety procedures in line with standard
/ /
operating procedures (SOPs)
*Installed auxiliary terminal cabinet and
/ /
distribution panel
*Notified completion of work / /
NOTE: *Critical aspects of competency

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
TABLE OF SPECIFICATION

  Objectives/Content # of items/
Knowledge Comprehension Application
area/Topics % of test

1. Install electrical
metallic/non- 1 ITEM 1 ITEM 2 ITEM
20%
metallic (PVC 5% 5% 10%
conduit)

2. Install wire ways 1 ITEM 1 ITEM 1 ITEM


and cable trays 15%
5% 5% 5%

3. Install auxiliary 1 ITEM 1 ITEM 2 ITEM


terminal cabinet and 20%
distribution panel 5% 5% 2%

4. Prepare for cable 1 ITEM 1 ITEM 1 ITEM


pulling and 15%
installation 5% 5% 5%

5. Perform wiring 1 ITEM 1 ITEM 2 ITEM


and cabling lay out 20%
5% 5% 10%

6. Notify completion 1 ITEM 1 ITEM


of work 0 10%
5% 5%

5 ITEMS 6 ITEMS 9 ITEMS 20 ITEMS


TOTAL
25% 30% 45% 100%

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
Written Test

TEST I -MULTIPLE CHOICES: Choose the correct answer and


encircle its letter.
1. A conduit informally called Greenfield or flex. Is made by the helical
coiling of a self-interlocked ribbed strip of aluminum or steel, forming a
hallow tube through which wires can be pulled. It is used primarily in dry
areas where it would be impractical to use EMT.

a. EMT (Electrical Metallic tubing) b. RMC (Rigid Metal Conduit)

c. FMC (Flexible Metallic Conduit) d. ENT (Electrical nonmetallic conduit)

2. The conduit is allowed to bend, but should not exceed the maximum
tolerance of.

a. 30˚ b. 45˚ c. 180˚ d. 90˚

3. The equipment needed to install metallic and non-metallic conduits are:

a. Electric power drill, Portable Grinder

b. Heat gun, Pipe Thread maker

c. Pipe bender

d. All of the above

4. What specific Instructions must be followed in installation of conduit


fittings, couplings and elbows?

a. Inserted as per job requirements.

b. Fully inserted, tightened and properly installed as per job

requirements.

c. Installed and constraint as per job requirements.

d. None of the above.

5. The blade tip of this kind is wedge-shaped and resembles a negative


sign.

a. Philips screw b. Flat screw driver

c. Insulators d. Stubby screw

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
6. Used for cutting and holding fine wires. Can reach tight space or small
opening where others cannot.

a. Wire stripper b. Diagonal pliers

c. Long nose pliers d. Electrician knife

7. These are made from metals with insulators in the handle and are used
for cutting, twisting, bending, holding, gripping wires and cables.

a. Pliers b. mallet

c. Claw hammer d. Side cutter

8. Is a component of an electricity supply system that divides an electrical


power feed in to subsidiary circuits, while providing a protective fuse or
circuit breaker for each circuit in a common enclosure.

a. Multi tester b. Distribution board or Panel board

c. Mother board d. PCB

9. What specification (ampere) of circuit breaker is needed after installing a


special purpose outlet (SPO)?

a. 30 amp b. 20 amp

c. 15 amp d. 60 amp

10. A class type of hardhat that tested at 2200 volts.

a. Type I hard hat b. General class

c. Electrical class d. Conductive class

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
TEST II – TRUE OR FALSE

Direction: Write T if the statement is TRUE and Write F if it is FALSE.

_________11. A protective device used to automatically blow or cut off the


flow of electrical current when trouble in the circuit such as short circuit or
overload occurs is called circuit breaker.

_________12. Cable pulling is the moving of length of cable from one place to
another to install a connection of some type between designated areas.

_________13. A cable tray is a tube used to protect and route electrical


wiring in building or structure.

_________14. Reading and interpreting electrical drawing, familiarize all


electrical symbols will not help you to complete wiring installation as per job
requirements.

_________15. There are three ways to show electrical circuits. They are
wiring diagram, schematic diagram and pictorial diagram. The two most
commonly used are wiring diagram and schematic diagram.

Test III – IDENTIFICATION

Direction: Identify the following question.

___________16. It is galvanized steel tubing with a tubing wall that is thick


enough to allow threading.

___________17. A rectangular shaped metallic or non-metallic material in


which flush type convenience outlet and switch are mounted or attached.

___________18. Sometimes called thin wall, it is less costly and lighter than
GRC.

___________19. A pocket size tools use to test the line wire or circuit if there
is flow of current in it.

___________20. These are tools used in driving or pounding and pulling out
nails, they are made of hard steel, wood, plastic or rubber.

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
Answer Key

Test I. Multiple Choice

1. C

2. D

3. D

4. B

5. B

6. C

7. A

8. B

9. A

10. B

Test II. True or False

1. T

2. T

3. F

4. F

5. T

Test III – IDENTIFICATION

1. Galvanized Rigid Conduit

2. Utility box

3. Electrical Metallic Tubing

4. Screw tester/ Circuit tester

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
5. Hammer

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
Performance Test

Specific Instruction for the Candidate

Qualification ELECTRICAL INSTALLATION AND


MAINTENANCE NC II

Unit of Competency PERFORM ROUGHING-IN ACTIVITIES,


WIRING AND CABLING WORKS FOR
SINGLE-PHASE DISTRIBUTION,
POWER, LIGHTING AND AUXILIARY
SYSTEMS

General Instruction:

Given the following tools, materials and equipments you should be able
to perform roughing-in activities, wiring and cabling works for single-phase
distribution, power, lighting and auxiliary systems as per job requirements.

Specific Instruction:

1. Ensure that the fittings are fully inserted and tightened as per job

requirements.

2. Install Conduit coupling and elbows are properly installed as per

job requirements.

3. Interpret correct drawing as per job requirements.

4. Install wire ways and cable trays are properly installed as per job

requirements.

5. Select correct quantities of materials as per job requirements.

6. Install auxiliary terminal cabinet as per job requirements.

7. Set up cable lay out and installation equipment in accordance with

manufacturers and job requirements.

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
8. Identify cable pulling and installation requirements and constraints

from plan and site inspection as per job requirements.

9. Observe bending radius and loops tolerance for cable materials at

all times.

10. Proper pulling materials are installed and tensioned to required

specification.

11. Final checking are made to ensure that work conforms with

instruction and job requirements.

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
QUESTIONING TOOL

Questions to probe the candidate’s underpinning Satisfactory


knowledge response
Extension/Reflection Questions Yes No
1. Why do you need to familiarize the different tools,
materials and equipments?
Answer; To easily locate and prepare the materials, tools  
and equipments needed as per job requirements.
2. What are the requirements needed before starting the
installation process?
Answer; Observe OHS; Verify the availability of materials,  
tools and equipments.
3. Why do we have to familiarize in all electrical symbols
and interpret the correct drawing?
Answer; To easily follow the correct cable lay out, wiring,
conduit, cable tray, wire ways and distribution panel and  
auxiliary terminal cabinet installation as per job
requirements.
4. Why do we have to read and understand the manual or
guide?
Answer; To easily follow and perform the correct  
procedures.
Safety Questions
5. Why do we have to strictly follow the OHS?  
Answer; To avoid incidents in the work place
6. Is it necessary to verify the sizes of conductor to be  
use? And Why?
Answer; Yes, following the correct use of conductor as per
standard will avoid overloaded of electrical current.
7. Why do we need to replace substandard materials?  
Answer; To avoid short circuit.
8. Is it necessary to double check GFCI before use? And  
Why?
Answer; Yes, To avoid sudden electrical shock, and
equipment damage.

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
Contingency Questions
9. What will you do, if you see or encounter fire in the  
workplace?
Answer; Sound the alarm and use the correct type of fire
extinguisher to extinguish the fire.
10. How can we be sure that the tools are in good and safe  
condition and materials are the correct as per job
requirements?
Answer; Insulation of tools must be thoroughly checked to
ensure it is safe for electrical use and double check
materials labelling and specification.
11. Why do we need to check wiring of electrical  
equipment regularly?
Answer; To prevent fire.
12. What will you do if you encounter someone is  
electrocuted?
Answer; Switch off the source of electricity and immediately
call emergency.
Job Role/Environment Questions  
13. Why do we need to keep working area clean?  
Answer; To prevent/avoid Hazard and Risk
14. Why is it so important segregate materials/things in  
work area?
Answer; To easily locate materials needed and avoid delay
in actual performance
15. Why do we need to dispose unnecessary items?  
Answer; Maintaining cleanliness of the work area can avoid
exposure to hazard and risk
Rules and Regulations  
16. Why do we need to get involved in OHS management?  
Answer; To foster a safe working environment
17. Why is it so important to follow the standard  
procedure of training?
Answer; In order for us to easily achieve the goals of the
training
18. Why is it so important to follow the standard  
procedures of job requirements?
Answer; Compliance to standard procedures ensured the
quality and safety of work.
ELECTRICAL Date Developed: Document No.
Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01
19. Why do we need to follow the rules and regulations of  
training Industry or Institution?
Answer; Compliance with rules and regulations showed
respect and attitude of candidate who can easily achieve
the objectives of training.
20. Give at least two (2) precautionary measures while on  
the training?
Answer; 1. Observe OHS and use of PPE
2. Remove any metal accessories from your body
to avoid statics or electrical shock.
The candidate’s underpinning  Satisfactory  Not
knowledge was: Satisfactor
y

ELECTRICAL Date Developed: Document No.


Oct. 2019 to Feb. 2020 Issued by:
INSTALLATION
Date Revised:
AND
MAINTENANCE Developed by:
NC II ARTHURO G. RAMOS
Revision # 01

You might also like