Professional Documents
Culture Documents
Institutional Assessment Tools
Institutional Assessment Tools
Portfolio
Written
The evidence must show that the trainee…
*Interpret correct drawing based on job
/ / /
requirements
Determine correct quantities of conduit, fittings
/ /
and materials as per job requirements
Select tools, and equipments as per job
/ /
requirements
*Installed and assemble conduit ensuring that
fittings are fully inserted ,tightened and / /
threaded as per job requirements
Conduit is bent with bends not exceeding 90˚
/ /
as per standard and job requirements
*Installed wire ways and cable tray / /
*Prepare cable pulling, wiring installation and
/ /
lay-out
Follow safety procedures in line with standard
/ /
operating procedures (SOPs)
*Installed auxiliary terminal cabinet and
/ /
distribution panel
*Notified completion of work / /
NOTE: *Critical aspects of competency
Objectives/Content # of items/
Knowledge Comprehension Application
area/Topics % of test
1. Install electrical
metallic/non- 1 ITEM 1 ITEM 2 ITEM
20%
metallic (PVC 5% 5% 10%
conduit)
2. The conduit is allowed to bend, but should not exceed the maximum
tolerance of.
c. Pipe bender
requirements.
7. These are made from metals with insulators in the handle and are used
for cutting, twisting, bending, holding, gripping wires and cables.
a. Pliers b. mallet
a. 30 amp b. 20 amp
c. 15 amp d. 60 amp
_________12. Cable pulling is the moving of length of cable from one place to
another to install a connection of some type between designated areas.
_________15. There are three ways to show electrical circuits. They are
wiring diagram, schematic diagram and pictorial diagram. The two most
commonly used are wiring diagram and schematic diagram.
___________18. Sometimes called thin wall, it is less costly and lighter than
GRC.
___________19. A pocket size tools use to test the line wire or circuit if there
is flow of current in it.
___________20. These are tools used in driving or pounding and pulling out
nails, they are made of hard steel, wood, plastic or rubber.
1. C
2. D
3. D
4. B
5. B
6. C
7. A
8. B
9. A
10. B
1. T
2. T
3. F
4. F
5. T
2. Utility box
General Instruction:
Given the following tools, materials and equipments you should be able
to perform roughing-in activities, wiring and cabling works for single-phase
distribution, power, lighting and auxiliary systems as per job requirements.
Specific Instruction:
1. Ensure that the fittings are fully inserted and tightened as per job
requirements.
job requirements.
4. Install wire ways and cable trays are properly installed as per job
requirements.
all times.
specification.
11. Final checking are made to ensure that work conforms with