Professional Documents
Culture Documents
Mangga Concreting - 3
Mangga Concreting - 3
At Intlet Transition
Class "A"Concrete
Ihead wall = 10.20 x 3.00 x 0.30 = 9.18 cu.m.
Lean Concrete
V = 8.08 x 10.20 x 0.05 = 23.02 cu.m.
+ 2x 8.68 + 17.40 x 3.60 x 0.05
2.00
Total = 23.10 cu.m.
Side Borrow
V = 3.60 x 16.80 x 2.38 x 2.00 = 74.71 cu.m.
- 2x 8.08 + 16.80 x 3.60 x 2.38
2.00 Total = 74.80 cu.m.
S U M M A R Y
pc
PVC 87.5 deg Sanitary Tap Tee with Seal Ring (50mm x 38mm) 90.00
Shower Head with Valve set 1,940.00
Soap Holder set 350.00
Cylindrical Water Tank set 16,500.00
Stainless Ladder Rung kg 167.00
Kitchen Sink set 5,000.00
Floor Drain pc 282.00
Paper Holder set 263.00
Mirror sqft 60.00
Gate Valve 25mm Dia pc 390.00
Union Patentee 13mm Dia pc 36.00
Water Meter pc 1,600.00
Solvent can 120.00
Tefflon Tape roll 10.00
GI Nipple 13mm Dia pc 283.00
Hardware
Anchor Bolts with Nuts and Washer Kg 36.00
Machine Bolts with Nuts and Washer Kg 105.00
Tension Rod (38mm D) LnFt 57.00
Tension Rod (16mm D) LnFt 26.00
Tension Rod (19mm D) LnFt 33.00
Tension Buckles (12.7mm D) pc 162.00
Tension Buckles (16mm D) pc 186.00
Tension Buckles (19mm D) pc 233.00
WI Strap kg 61.00
Hinge (50mm x 101mm) pr 70.00
Sand Paper set 1,600.00
Door Locks set 1,550.00
Automatic Door Closer set 1,800.00
Tar Paint gal 455.00
Steel Cable kg 125.00
Steel Grating Frame kg 90.00
Wooden Doors and Windows
Flush Hollow Core Door sqm 900.00
Flush Type Solid Core Door sqm 1,700.00
Narra Paneled Door sqm 5,200.00
Tanguile Paneled Door sqm 4,500.00
Aluminum Glass Door sqm 6,500.00
Glass Transom On Wood sqm 1,900.00
Accordion Type Door sqm 2,100.00
Varifold Type Door sqm 3,000.00
Awning Type Steel Casement Windows sqm 1,800.00
Swing Type Steel Casement Windows sqm 1,900.00
Glass Jalousie Window sqm 680.00
Fixed Glass Window on Metal Frame sqm 450.00
Fixed Louvered Steel Window sqm 577.00
Aluminum Cement Window sqm 4,800.00
Sliding Aluminum window sqm 5,500.00
Metal Roofing
Corrugated Roofing Gauge 26 sqm 260.00
Pre Painted Metal Roofing Sheet Ga 26 Long Span sqm 425.00
Pre Painted Metal Roofing Sheet Ga 26x 2.44m sqm 420.00
Pre Painted gutter Ga 24 lnm 160.00
Ordinary Gutter lnm 105.00
Pre Painted Flashing lnm 160.00
Ordinary Flashing lnm 105.00
Pre Painted Ridge Roll GA 24 lnm 160.00
Ordinary Ridge Roll GA 24 lnm 105.00
Roof Ventilators set 1,300.00
Ceramic Tiles
Ceramic Glazed tiles sqm 760.00
Ceramic Unglazed Tiles sqm 750.00
Wood Tiles
Narra Wood Tile sqm 1,500.00
Tanguile Wood Tile sqm 780.00
Vinyl Floor Tile
Vinyl Tiles, 1/16'' Thickness sqm 300.00
Vinyl Tiles, 1/14'' Thickness sqm 360.00
Vinyl Tiles, 1/12'' Thickness sqm 375.00
Conduits, Boxes, and Fittings
Electrical Rigid Steel Conduit (12.7mm D) lght 365.00
Electrical Rigid Steel Conduit (19mm D) lght 520.00
Electrical Rigid Steel Conduit (25.4mm D) lght 730.00
Bushing and Locknut (12.7mm D) pr 6.00
Bushing and Locknut (19mm D) pr 9.00
Bushing and Locknut (25.4mm D) pr 13.00
Elbow 90 deg Rigid Steel pc 195.00
PVC Conduit Pipe (3m x 12.7mm D) pc 70.00
PVC Conduit Pipe (3m x 19mm D) pc 94.00
PVC Conduit Pipe (3m x 25.4mm D) pc 120.00
PVC Conduit Elbow 90 Deg pc 19.00
PVC Adapter with Locknut (12.7mm D) pc 8.00
PVC Adapter with Locknut (19mm D) pc 14.00
PVC Adapter with Locknut (25.4mm D) pc 16.00
RS Conduit Coupling (12.7mm D) pc 21.00
RS Conduit Coupling (25.4mm D) pc 30.00
PVC Conduit Coupling (12.7mm D) pc 4.00
PVC Conduit Coupling (19mm D) pc 5.00
PVC Conduit Coupling (25.4mm D) pc 8.00
Octagonal Junction Box pc 32.00
Utility Box Gauge pc 31.00
Square Box (101mm x 53mm) pc 40.00
Square Box (101mm x 63mm) pc 38.00
Metal Pull Box (152mm x 152mm x 101mm) pc 350.00
Metal Pull Box (304mm x 304mm x 101mm) pc 750.00
Telephone Cabinet (304mm x 457mm x 127mm) set 1,650.00
Telephone Cabinet (304mm x 610mm x 152mm) set 1,850.00
Condulet Type F 12.7mm pc 66.00
Condulet Type F 19mm pc 101.00
Service Entrance Cap (12.7mm D) pc 62.00
Service Entrance Cap (19mm D) pc 95.00
Service Entrance Cap (25.4mm D) pc 192.00
Mica Tubing pc 25.00
Electric Wires THWN/THHN 2 sq mm m 16.00
Electric Wires THWN/THHN 3.5 sq mm m 24.00
Electric Wires THWN/THHN 5.5 sq mm m 38.00
Telephone Jacketed wire Cat set 29.00
Single Gang Switch set 65.00
Two Gang Switch set 105.00
Three Gang Switch set 135.00
Two Way Switch set 152.00
Duplex Convenience Outlet set 128.00
Heavy Duty Outlet set 365.00
Polarized 3-Prongs (ACU Outlet) set 455.00
set
Enclosed Air Circuit Breaker 100Af, 3P, 220V, 70AT NEMA1 1,350.00
set
Enclosed Air Circuit Breaker 50Af, 3P, 220V, 40AT NEMA 1 1,250.00
set
Enclosed Air Circuit Breaker 50Af, 2P, 220V, 70AT NEMA1 550.00
Electrical Tape 3/4'' 20 Yards pc 35.00
Panel Boards and Cabinets (30 AMP, 2PST) set 1,220.00
Panel Boards and Cabinets (60 AMP, 2PST) set 1,500.00
1 x 20 W Box Type FLF set 300.00
1 x 40 W Box Type FLF set 380.00
2 x 40 W Box Type FLF set 580.00
1 x 20 Industrial Type FLF set 680.00
2 x 40 Industrial Type FLF set 830.00
1 x 40 W Troffer Type Aluminum Louver Recess set 1,000.00
2 x 40 W Troffer Type Aluminum Louver Recess set 1,250.00
1 x 40 W Troffer Type Aluminum Louver Surface set 1,000.00
2 x 40 W Troffer Type Aluminum Louver Surface set 1,250.00
6 '' D Pinlight with 18 W 220 V CFL set 300.00
Equipment for Fire Alarm Station - Manual set 1,250.00
Equipment for Fire Alarm Bell set 1,500.00
Equipment for Fire Alarm, Annunciator set 4,500.00
Equipment for Fire Alarm, Control Panel set 3,200.00
Equipment for Fire Alarm, Smoke Detector set 1,300.00
Floor Outlet Pop Up set 3,600.00
Telephone Outlet set 200.00
Other Construction Materials
NIPA Single Class I sqm 22.00
NIPA Single Calss II sqm 35.00
Sawali 2m x 2m With Skin sqm 52.00
Sawali 2m x 2m Skinless sqm 58.00
Mechanical Equipments
Generator 220v 100kw Capacity unit 400,000.00
Air Conditioner Window Type, 1 HP 220V unit 18,500.00
Air Conditioner Window Type, 1,5 HP 220V unit 23,000.00
Air Conditioner Window Type, 2 HP 220V unit 26,000.00
Reinforcing Steel Bar (Grade 60)
Reinforcing Steel Bar (Grade 40)
Tie wire
Curing Compound
Asphalt Sealant
Forms (Rental)-200mm
Ready Mix Concrete
Polyethylene sheet
RMX
Fine aggregates
Fine aggregates (sand bedding)
Coarse aggregates
Gravel fill
Selected borrow matls
Agg. Subbase course matls
Garden soil
Portland cement
Concrete Saw (Diamond Blade -14"Ø)
Pipe sleeve
Protection Matls (double lane) or boulders
Grease tar
Concrete Admix
Good lumber
Good lumber (coco)
Plywood (1/2' x 4' x 8')
Project Sign (Tarpaulin)
Plywood 4.5mm
Assorted CWN
RC Pipe 24 Ø
RC Pipe 30 Ø
RC Pipe 36 Ø
Weephole PVC
Filter cloth
Boulders
Rope, 1"Ø
Readymix concrete class A w/ pumpcrete 7 days
Readymix concrete class A w/ pumpcrete 14 days
Readymix concrete class A w/ pumpcrete 28 days
Readymix concrete class A 7 days
Readymix concrete class A 14 days
Readymix concrete class A 28 days
Soil poisoning
50mmØ PVC Pipe Series 600
50mmØ PVC Pipe Series 1000
150mmØ PVC Pipe Series 600
150mmØ PVC Pipe Series 1000
Gypsum board
Metal furring
Carrying channel
Hanger bars/rod
Channel clip
Wall angle
Rivets
Metal screw
Hollow core flush door
Wooden panel door
Corrugated roofing sheet
Tekscrew w/ j bolt with washers
Ridge roll 0.60mm
Hip roll 0.60mm
Valley roll 0.60mm
Counter flashing 0.60mm
Blind rivets
Gutter 0.60mm
12" x 1" Plain GI strap
Prepainted metal sheets (Corr.)
Cement based waterproofing
Primer coat
Liquid waterproofing
Asphalt primer
Preformed membrane
50mm -100mmØ Roof drain, canopy drain/ gutter drain
with strainer
Glazed tiles
Tile grout
Tile adhesive (25kg)
Unglazed tiles/granite/synthetic granite tiles
1/2" TO 2" x 3M PVC PIPE BLUE
PVC ORANGE S1000 2"-4" Ø
PVC ORANGE S1000 4"-8" Ø
Fixtures
STAINLESS WATERTANK(8000 LIT) WITH STEEL
FRAMING
2 HOLES PANEL BOARD WITH BREAKER
6 HOLES PANEL BOARD WITH BREAKER
12 HOLES PANEL BOARD WITH BREAKER
1.6mm² - 5.5mm WIRES THW/THHN/THWN
8.0mm² - 22mm WIRES THW/THHN/THWN
PVC ORANGE 15mmØ-32mmØ
UTILITY & JUNCTION BOX(PVC)
SWITCH PLATES WITH ELEMENTS
CONV. OUTLET PLATES W/ ELEMENT
LIGHTING -18WATTS LED BULBS INCLUDING
RECEPTACLES
LAMP POST WITH LED BULB
STREETLIGHTS WITH LED BULBS
ELECTRICAL TRASNFORMER 37.5KVA
Double-Throw Switch
KHW METER
Mega-Spotlight (4-branches)
1.0mm THK. X 0.465m Steel Deck
0.8mm THK. X 0.465m Steel Deck
Concrete neutralizer
Concrete sealer/primer
Patching compound
Semi gloss latex
Glazing putty
Flat wall enamel
Enamel quick dry
Paint thinner
Tinting color
Red oxide primer
Enamel paint
Panel Door Set
Ployethylene sheets 6 mils
Reflective insulation
Stainless door and frames
PVC door and frames
100mm CHB
Structural steel roof framing matls
Acetylene
Oxygen
Welding rod
Structural steel purlins
Anchor bolt
Sagrods with nuts and bolts
Turnbuckle
Cross bracing
Steel plates
15mm - 32mmØ PVC (electl pipe)
Conduit fittings
Junction/utility/pull square box
1.6mm² - 5.5mm² Electric Wire (TW/THHN/TWHN)
8mm² - 22mm² Electric Wire (TW/THHN/TWHN)
30mm² - 38mm² Electric Wire (TW/THHN/TWHN)
50mm² - 60mm² Electric Wire (TW/THHN/TWHN)
Switches
Single convenience outlet
Duplex convenience outlet
Rope, 1" 0- 5 uses
Developing
Safety Helmet
Safety Shoes
Safety Vest
Working Gloves
Rain Coats (30% of the Duration)
Rubber Boots
Eye Goggles
Face Mask (Surgical/Cloth)
Pop up convenience outlet
EQUIPMENT RENTAL
simplicity RATES
in computation, the operated rental rates are preferred over the bare rental rates as the former includes ope
maintenance.
DESCRIPTION MODEL
Bulldozer D6H SERIESS II PSDS/DD
Bulldozer w/ Ripper D6H SERIESS II PSDS/DD
Payloader LX80-2C
Motorized Road Grader G710A
Motorized Road Grader w/ Scarifier G710A
Compaction Equipment
Pneumatic Tire Roller 9-SWHL, 9.00X20,4PR
Vibratory Roller SD100DC
Tandem Steel Roller CC421
Plate Compactor 400-500 Gasoline Engine
Lifting Equipment
Crawler Crane All models
Truck Mounted Crane (31-35mt) All models
Truck Mounted Crane (41-45mt) All models
Low bed trailer
Excavating Equipment
Backhoe SE 130 LC-2
Backhoe w/ Breaker SE 130 LC-3
Backhoe w/ Chipping Hammer added by HTD
Backhoe, Wheel Mounted PW60N-1
Foundation Equipment
Vibro Hammer DPD600T Hydraulic Pile Driver
Asphalting Equipment
Asphalt Distributor ROSCO/5 ton
Asphalt Paver NF220BIIVDM
Concreting Equipment
Concrete Screeder Wacker Truss Screed
Concrete Paver COMMANDER III, FOUR TRACK
One Bagger Mixer
Transit Mixer All models
Hauling Equipment
Dump Truck All models
Cargo/Service Truck (160HP) All models
Boom Truck All models
Cargo/Service Truck (270HP) All models
Water Truck/Pump All models
Water Truck/Pump (2) All models
Air Equipment
Air Compressor (356-450cfm) All models
Air Compressor (161-185cfm) All models
Air Compressor (15-35 cfm) All models
Diamond Drill CP-8
Jackhammer
Pneumatic Drilling Machine
Pumping Equipment
Water Pump 100mmØ suction 2667 liters/min
Shop Equipment
Welding Machine (Electric Driven)
Welding Machine (Gas/Diesel Driven)
Special Support Equipment
Chainsaw
ental rates as the former includes operator's wages, fringe benefits, fuel, oil, lubricants and equipment
maintenance.
FLYWHEEL ADJUSTED
CAPACITY HORSEPOWER 2014 Rental Rate RENTAL RATE Rental Rate per day
165 3,379.00 3,492.53 27,940.24
165 3,885.85 31,086.80
1.5 cu.m/1.95 cu. Yd 110 1,733.00 1,810.96 14,487.68
140 2,173.00 2,260.48 18,083.84
140 2,824.00 22,592.00
-
10 mt 107 561.00 4,488.00
10 mt 125 1,846.00 1,916.40 15,331.20
10.10 mt 123.4 1,652.00 13,216.00
5 123.00 123.00 984.00
-
36-40mt 190 1,522.00 1,902.00 15,216.00
31-35 mt 238 1,861.00 1,861.00 14,888.00
41-45 mt 246 2,151.00 2,606.00 20,848.00
3,750.00 30,000.00
-
0.80 cu.m/1.04 cu yd 99 1,537.00 1,537.00 12,296.00
0.80 cu.m/1.04 cu yd 99 2,074.95 1,998.00 15,984.00
99 1,998.00 15,984.00
0.28 cu m/0.37 cu yd 50 922.00 922.00 7,376.00
-
60 ton 201 2,123.00 16,984.00
-
3000 USG 100 936.00 7,488.00
80 1,833.00 14,664.00
-
5.5 545.00 545.00 4,360.00
6,765.00 6,765.00 54,120.00
4-6 cu ft/min 172.00 172.00 1,376.00
5-6 cu yd 1,318.00 1,386.99 11,095.92
-
12 cu yd 290 1,420.00 1,420.00 11,360.00
2-5 mt 160 783.00 783.00 6,264.00
2-5 mt 160 1,017.90 1,017.00 8,136.00
9-10 mt 270 1,212.00 1,212.00 9,696.00
16000 L 360 2,450.00 2,543.42 20,347.36
1000L 360 1,420.00 2,543.42
-
356-450 cfm 130 965.00 965.00 7,720.00
161-185 cfm 69 502.00 502.00 4,016.00
15-35 cfm 20 205.00 205.00 1,640.00
201.25 201.00 1,608.00
150.00 150.00 1,200.00
170.00 170.00 1,360.00
-
50 16 266.25 266.25 2,130.00
-
500Ampere 391.00 391.00 3,128.00
300Ampere 371.00 371.00 2,968.00
-
75.36 75.36 602.88
-
1,386.00 1,386.00 11,088.00
-
with 5Amperes Gasoline Driven Unit 91.25 91.25 730.00
32.63 32.63 261.04
219.75 219.75 1,758.00
um Rebar, Three Phase 351.50 351.50 2,812.00
4,286.63 4,286.63 34,293.04
1,759.50 1,759.50 14,076.00
6,900.00
130.54 130.54 1,044.32
952.00 952.00 7,616.00
93.75 93.75 750.00
187.50 187.50 1,500.00
200.00 200.00 1,600.00
45.45 45.45 363.60
300.00 300.00 2,400.00
200.00 200.00 1,600.00
ls 9.79 1.06 9.79
4583.3333333
G40 10 0.616 6
G60 12 0.888
G60 16 1.578 6
G60 20 2.466 7.5
G60 20 2.466 9
G60 25 3.853 9
list all diameter of this series specify length
list all diameter of this series specify length
philhealth pag-ibig wage monthly wage daily wage hourly
260.57 100.00 21,360.79 819.05 102.38
188.19 100.00 15,431.54 591.70 73.96
144.76 100.00 11,885.99 455.75 56.97
144.76 100.00 18,519.77 710.11 88.76
3.696 176.5 47.754329004
Embankment from roadway excavation (Common Soil) cu.m 79.00 254.72 20,123.12
Subgrade Preparation (Common Material) sq.m. 3,934.00 20.75 81,625.27
III. SUBBASE COURSE
Aggregate Subbase Course cum 591.00 981.20 579,887.94
IV. BASE COURSE
Aggregate Base Course `cu.m. 394.00 818.77 322,596.12
V. SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced) - 0.23
sq.m. 2,810.00 1,515.77 4,259,307.20
m thick, 14 days
VI. CONCRETE DEMOLITION
Removal of Structure and Obstruction cu.m. 3.00 439.83 1,319.50
VII. CONCRETE STRUCTURES (ROAD CROSSING DRAINAGE)
Structure excavation (common soil) cu.m 7.00 209.14 1,463.97
Embankment from Structure Excavation cu.m. 3.00 255.84 767.51
Pipe Culverts (610mm) Class II, RCPC ln.m. 6.00 3,345.09 20,070.54
Structural Concrete(Headwall, Cut-off wall) cu.m. 3.00 6,422.93 19,268.79
Reinforcing Steel (Headwall, Cut-off wall) kgs. 135.00 76.90 10,381.30
TOTAL ESTIMATED DIRECT COST 5,481,100.00
APPROVED BUDGET FOR THE CONTRACT 5,481,100.00
5,481,100.00
Prepared by: (0.00)
*Assumptions:
1. Establishment of Vertical & Horizontal Control is a one-time activity.
2. The Conduct of Profile and Cross Section Survey shall be at least once a month which shall serve as a
basis in the preparation of Monthly Statistical Report/Status Report as a requisite for Contract Billing, Monthly
Progress Report and other similar report which survey results maybe needed. Profile & Cross Section Survey
may be conducted as often as needed depending on the needed data to be gathered.
3. For presentation, profile & cross section survey shall be conducted on (1) Stake-Out Surveys (2) Once a month
in a year.
No. of Surveys = 1 Profile & Cross-Section Surveys
PROGRAMMED LENGTH OF ROAD : 2.00 km.
A. ESTABLISHMENT OF VERTICAL & HORIZONTAL CONTROL
Length of Canal : 2.10 km.
Capability : 5 km./day
Cycle Time:
2.10 km.
No. of Days = = 0.42 days
5 km./day
25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 0.55 days
say 0.50 days
or in Hours = 4.00 hours
1. Labor
1- Engineer x 1,281.67 /day x 0.50 days = 640.84
1- Instrumentation x 983.55 /day x 0.50 days = 491.78
1- Survey Aide x 760.07 /day x 0.50 days = 380.04
1- Driver x 809.97 /day x 0.50 days 404.99
5- Utility Worker x 558.75 /day x 0.50 days = 1,396.88
Total Labor Cost = 3,314.51
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Page 34
Fuel = 8.00 lit/hr x 41.00 /lit. 4.00 hrs. = 1,312.00
Spare Parts = 313.95 /hr. x 4.00 hrs. = 1,255.80
SUMMARY
a. Labor = 3,314.50
b. Spare Parts = 1,255.80
c. Fuel = 1,312.00
UNIT COST = 5,882.30
B. PROFILE SURVEY
Length of Canal : 2.00 km.
Capability : 2 km./day
Cycle Time:
2.00 km.
No. of Days = = 1.00 days
2 km./day
25 km x 1 day
Travel Time = = 0.13 days
25 kph x 8 hr
Total Number of Days = 1.13 days
say 1.50 days
or in Hours = 12.00 hours
1. Labor
1- Engineer x 1,281.67 /day x 1.50 days = 1,922.51
1- Instrumentation x 983.55 /day x 1.50 days = 1,475.33
1- Survey Aide x 760.07 /day x 1.50 days = 1,140.11
1- Driver x 809.97 /day x 1.50 days 1,214.96
5- Utility Worker x 558.75 /day x 1.50 days = 4,190.63
Total Labor Cost = 9,943.52
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Fuel = 8.00 lit/hr x 41.00 /lit. x 12.00 hrs. = 3,936.00
Spare Parts = 313.95 /hr. x 12.00 hrs. = 3,767.40
SUMMARY
a. Labor = 9,943.52
b. Spare Parts = 3,767.40
c. Fuel = 3,936.00
UNIT COST = 17,646.92
Page 35
5- Utility Worker x 558.75 /day x 5.50 days = 15,365.63
Total Labor Cost = 36,459.56
Page 36
2. Equipment Utilization
utilized = Pick-Up 4x4
rental = 313.95 /hr.
Fuel = 8.00 lit/hr x 41.00 /lit. x 44.00 hrs. = 14,432.00
Spare Parts = 313.95 /hr. x 44.00 hrs. = 13,813.80
SUMMARY
a. Labor = 36,459.56
b. Spare Parts = 13,813.80
c. Fuel = 14,432.00
UNIT COST = 64,705.36
D. PLOTTING AND COMPUTATION
1. Profile
Length of Canal : 2.00 km.
1. Materials/Office Supplies
Cross Section Paper = 150.00 /km. x 2.00 km. = 300.00
Data Book = 50.00 /km. x 2.00 km. = 100.00
Miscellaneous = 45.00 /km. x 2.00 km. = 90.00
Total Materials Cost 490.00
2. Labor
Length of Canal : 2.00 km.
Capability : 8 km./day
Cycle Time:
2.00 km.
No. of Days = = 0.25 days
8 km./day
Total Number of Days = 0.25 days
say 0.50 day
1- Engineering Asst. A x 1,281.67 /day x 0.50 days = 640.84
Sub-Total = 640.84
SUMMARY
a. Materials Cos = 490.00
b. Labor Cost = 640.84
UNIT COST = 1,130.84
2. Cross-Section
Length of Canal : 2.00 km.
1. Materials/Office Supplies
Cross Section Paper = 350.00 /km. x 2.00 km. = 700.00
Data Book = 75.00 /km. x 2.00 km. = 150.00
Miscellaneous = 55.00 /km. x 2.00 km. = 110.00
Total Materials Cost 960.00
2. Labor
Length of Canal : 2.00 km.
Capability : 0.4 km./day
Cycle Time:
2.00 km.
No. of Days = = 5.00 days
0.4 km./day
Total Number of Days = 5.00 days
say 5.00 day
1- Engineering Asst. A x 1,281.67 /day x 5.00 days = 6,408.35
Sub-Total = 6,408.35
SUMMARY
a. Materials Cos = 960.00
b. Labor Cost = 6,408.35
UNIT COST = 7,368.35
Page 37
SUMMARY FOR PROFILE AND CROSS-SECTION SURVEY
Materials/Office
a. = 1,450.00 /survey x 1 surveys = 1,450.00
Supplies
b. Labor = 53,452.26 /survey x 1 surveys = 53,452.30
c. Spare Parts = 17,581.20 /survey x 1 surveys = 17,581.20
d. Fuel = 18,368.00 /survey x 1 surveys = 18,368.00
UNIT COST = 90,851.50
Page 38
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
--oOOo--
OFFICE OF THE MUNICIPAL ENGINEER
BREAKDOWN OF EXPENDITURES
AS SUBMITTED AS SUBMITTED
1. Labor 6,929,659.54 A. Total Direct Cost Err:509
2. Materials 15,010,035.48 B. OCM & Profit Err:509
3. Rental of Equipment Err:509 C. Value Added Tax Err:509
4. Provisional Sum D. Total Construction Cost
5. OCM & Profit Err:509 E. Eng'g & Admin. Overhead, %
6. Value Added Tax Err:509 F. RROW Acquisition
7. EAO, % G. Contingency 2,372,253.88
8. RROW Acquisition
9. Contingency 2,372,253.88
10. TOTAL ESTIMATED COST Err:509 H. TOTAL ESTIMATED COST Err:509
Approved by:
Approved by:
B.5 Project Billboard / Signboard 1.00 L.S. 4,244.64 4,244.64 848.93 254.68 1,103.61 5,348.25
B.7(2) Occupational Safety and Health Program 1.00 L.S. 242,050.00 242,050.00 48,410.00 2,420.50 50,830.50 292,880.50
B. EARTHWORKS
B.1. Clearing and Grubbing 394.00 sq.m. 15.40 6,067.60 3.10 1.00 1,615.40 7,683.00
B.2. Common Excavation 197.00 cu.m. 116.50 22,950.50 23.30 7.00 5,969.10 28,919.60
B.4. Foundation Fill 79.00 cu.m. 462.40 36,529.60 106.30 19.60 9,946.10 46,475.70
B.5. Disposal of excess materials 1,239.30 cu.m. 193.80 240,176.34 38.80 11.60 62,460.72 302,637.06
D. SURFACE COURSE
D.1. Portland Cement Concrete Pavement, 0.23m. THK. 2,810.00 cu.m. 7,604.30 21,368,083.00 1,520.90 222.50 4,898,954.00 26,267,037.00
D.1. RSB Furnishing and Stockpilling 895.67 cu.m. 58.60 52,486.43 11.70 0.60 11,016.78 63,503.20
D.1. RSB Cut, Bend & Place 895.67 cu.m. 11.90 10,658.51 2.40 0.70 2,776.59 13,435.09
E.1. Structure Excavation 29.10 cu.m. 87.40 2,543.34 17.50 5.30 663.48 3,206.82
E.2. Class "A" Concrete 132.20 cu.m. 9,130.30 1,207,013.79 1,826.10 214.20 269,725.01 1,476,738.80
E.3. RSB Furnishing and Stockpilling 13,765.90 cu.m. 58.60 806,681.74 11.70 0.60 169,320.57 976,002.31
E.4. RSB Cut, Bend & Place 13,765.90 cu.m. 11.90 163,814.21 2.40 0.70 42,674.29 206,488.50
E.5. Lean Concrete 23.10 cu.m. 1,532.60 35,403.06 306.50 19.30 7,525.98 42,929.04
E.6. Structural Backfill 74.80 cu.m. 841.20 62,921.76 168.20 17.20 13,867.92 76,789.68
Approved by:
b. Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 734.09 /hr. (incl. Fuel & operator)
EQUIPMENT:
9.00 lit/hr x 41 /liter
Fuel = = 6.71 /cu.m.
55 cu. m./hr.
734.09 /hr.
Spare Parts = = 13.35 /cu.m.
55 cu. m./hr.
c. Hauling
c.1. Hauling from Quarry Site to Dumpsite
AHD = 53.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 51.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 2.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 304.23 /hr.
Labor per day = 5 - Laborers x /day = - /day
Base Cost = 120.00 /cu.m.
Capacity of Truck = 4 cu.m./trip
Capability of five (5) Laborers
Cycle Time
with load = 51.00 kms. / 35.00 km./hr. = 1.46 hrs./trip
T-I
without load = 51.00 kms. / 45.00 km./hr. = 1.13 hrs./trip
with load = - kms. / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = - kms. / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / 35.00 km./hr. = - hrs./trip
with load = 2.00 kms. / 20.00 km./hr. = 0.10 hrs./trip
T-IV
without load = 2.00 kms. / 25.00 km./hr. = 0.08 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.89 hrs./trip
EQUIPMENT:
15.00 lit/hr x 2.77 hrs/trip x 41 /liter
Fuel = = 425.96 /cu.m.
4 cu.m./trip
304.23 /hr. x 2.89 hrs/trip
Spare Parts = = 219.59 /cu.m.
4 cu.m./trip
SUMMARY:
SAND GRAVEL
Base Cost = 120.00 /cu.m. = 120.00 /cu.m.
Fuel Cost = 425.96 /cu.m. = 425.96 /cu.m.
Spare Parts = 219.59 /cu.m. = 219.59 /cu.m.
TOTAL = 765.55 /cu.m. = 765.55 /cu.m.
SUMMARY
c. Equipment
utilize : 1 - bagger concrete mixer
rental = 99.14 /hr.
9.50 bag/cu.m. x 10 min./bag
Time of Mixer/cu.m. = = 1.583 hr./cu.m.
60 min./hr.
Fuel = 1.26 lit./hr. x 1.5833 hr./cu.m. x 41 /liter = 81.80 /cu.m.
Spare Parts = 99.14 /hr. x 1.5833 hr./cu.m. x = 156.97 /cu.m.
SUMMARY
a. Materials = 2,784.00 /cu.m.
c. Depreciation = - /cu.m.
d. Spare Parts = 495.95 /cu.m.
e. Fuel = 785.39 /cu.m.
UNIT COST = 4,065.34 /cu.m.
Page 47
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 150 bags/trip / / 300 bags/hr = 0.50 hrs./trip
Unloading = 150 bags/trip / / 300 bags/hr = 0.50 hrs./trip
total time = 2.21 hrs./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /bag
8 hr/day x 1 bag/trip
SUMMARY
1 Base Cost = 235.00 /bag
2 Hauling
a. Equipment Cost = 13.54 /bag
b. Labor Cost = 3.68 /bag
Total Hauling Cost = 17.22 /bag
5% VAT for Hauling Cost = 0.86 /bag
TOTAL COST = 253.08 /bag
say 253.10 /bag
B. Lumber
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost = 58.00 /bd.ft.
Capacity of Truck = 4,000 bd.ft./trip
Capability of five (5) Laborers
Loading = 4,000 bd.ft./trip
Unloading = 4,000 bd.ft./trip
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 4000 bd.ft./trip / / 4000 bd.ft./trip = 1.00 hrs./trip
Unloading = 4000 bd.ft./trip / / 4000 bd.ft./trip = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 0.74 /bd.ft.
4000 bd.ft./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 0.20 /bd.ft.
8 hr/day x 4000 bd.ft./trip
Page 48
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 25 bd.ft./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /bd.ft.
8 hr/day x 25 bd.ft./trip
SUMMARY
1 Base Cost = 58.00 /bd.ft.
2 Hauling
a. Equipment Cost = 0.74 /bd.ft.
b. Labor Cost = 0.20 /bd.ft.
Total Hauling Cost = 0.94 /bd.ft.
5% VAT for Hauling Cost = 0.05 /bd.ft.
TOTAL COST = 58.99 /bd.ft.
say 59.00 /bd.ft.
C. 1/2" Marine Plywood
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost = 820.00 /pc.
Capacity of Truck = 250 pc./trip
Capability of five (5) Laborers
Loading = 250 pc./hr
Unloading = 250 pc./hr
a. Hauling from Source To Dump Site
Cycle Time
with load = 22.00 kms. / / 35.00 km./hr. = 0.63 hrs./trip
T-I
without load = 22.00 kms. / / 45.00 km./hr. = 0.49 hrs./trip
with load = - kms. / / 25.00 km./hr. = - hrs./trip
T-II
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = - kms. / / 30.00 km./hr. = - hrs./trip
T-III
without load = - kms. / / 35.00 km./hr. = - hrs./trip
with load = 1.00 kms. / / 20.00 km./hr. = 0.05 hrs./trip
T-IV
without load = 1.00 kms. / / 25.00 km./hr. = 0.04 hrs./trip
Loading = 250 pc./trip / / 250 pc./hr = 1.00 hrs./trip
Unloading = 250 pc./trip / / 250 pc./hr = 1.00 hrs./trip
total time = 3.21 hrs./trip
920.00 /hr. x 3.21 hrs./trip
Equipment Cost = = 11.80 /pc.
250 pc./trip
2,000.00 /day x 3.21 hrs./trip
Labor Cost = = 3.21 /pc.
8 hr/day x 250 pc./trip
b. Manual Hauling from Dump Site to Job Site
Utilize : 1 Laborer @ 400.00 /day
Capability : 1 pc./trip
Cycle Time
with load = 0 km. / / 2.00 km./hr. = - hrs./trip
without load = 0 km. / / 5.00 km./hr. = - hrs./trip
total time = - hrs./trip
400.00 /day x - hrs./trip
Labor Cost = = - /pc.
8 hr/day x 1 pc./trip
Page 49
SUMMARY
Page 50
SUMMARY
E. Plain GISheet
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
SUMMARY
Page 51
say 70.70 /lin.m.
2 Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)
Equipment
1,746.00 /hr
Cost = = 31.75 /cu. m
55 /cu. m./hr.
3 Hauling
AHD = 53.00 kms. (TABUK CITY, KALINGA QUARRY) Speed (kph)
with Load w/o Load
Type of Road : Type I = 51.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 2.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilize Dump Truck (6W)
Capacity : 4.00 cu.m./trip
truck rental = 1,087.00 /hr.
Quarry Pit Fee : 120.00 /cu.m.
4 Screening of Aggregates
Capability
Sand = 6.00 cu. m./day
Gravel = 4.00 cu. m./day
1 -Laborers @ 400.00 /day
400.00 / day
Sand = = 66.67 /m3
6.00 m3/day
400.00 / day
Gravel = = 100.00 /m3
4.00 m3/day
Page 52
SUMMARY
SAND GRAVEL
1 Quarry Pit Fee = 120.00 /m3 = 120.00 /m3
2 Quarrying = 49.74 /m3 = 49.74 /m3
3 Loading = 31.75 /m3 = 31.75 /m3
4 Hauling = 784.58 /m3 = 784.58 /m3
5 Screening = 66.67 /m3 = 100.00 /m3
Total = 1,052.73 /m3 1,086.06 /m3
Plus: 5% VAT = 52.64 /m3 54.30 /m3
2% Excise Tax = 21.05 /m3 21.72 /m3
TOTAL COST = 1,126.42 /m3 = 1,162.09 /m3
say 1,126.40 /m3 say 1,162.10 /m3
G. 4" CHB
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost = 11.00 /pc.
Page 53
H. Steel Paving Forms 4"x10"x10'x1/8"
AHD = 23.00 kms. Speed (kph)
with Load w/o Load
Type of Road : Type I = 22.00 kms. 35.00 45.00
: Type II = - kms. 25.00 35.00
: Type III = - kms. 30.00 35.00
: Type IV = 1.00 kms. 20.00 25.00
: Type V (Manual Hauling) = - kms. 2.00 5.00
SUMMARY
Page 54
Utilized : 6x6 Cargo Truck with five (5) Laborers
truck rental = 920.00 /hr.
Labor per day = 5 - Laborers x 400.00 /day = 2,000.00 /day
Base Cost : 150.00 /pc.
Capacity of Truck = 8,000 pcs./trip
Capability of five (5) Laborers
Loading = 8,000 pcs./trip
Unloading = 8,000 pcs./trip
SUMMARY
RECAPITULATION
DESCRIPTION UNIT UNIT PRICE
1. Cement P/bag 253.10
2. Sand P/cu. m. 1,126.40
3. Gravel P/cu. m. 1,162.10
4. Reinforcing Steel Bar P /kg. 58.60
5. 1/2 " THK. Plywood P /pc. 835.80
6. Form Lumber P/bd. ft. 59.00
7. CWN P/kg. 100.60
8. Tie Wire P/kg. 100.60
9. 4' THK CHB P /pc. 17.60
10. Plain GI Sheet P/lin.m. 70.70
11. Steel Paving Forms 4"x10"x10'x1/8" P/lin.m. 260.70
11. Road Form Stakes P/pc. 150.50
INDIRECT COST (%) 20%
Page 55
IV. ITEM OF WORK
A. CONCRETING WORKS
2. Class "A" Reinforced Concrete (211 kscm for Road Conreting)
a. Materials
Cement = 9.50 bags /m3 x 253.10 / bag = 2,404.45 /m3
Sand = 0.45 m3 /m3 x 1,126.40 /m3 = 506.88 /m3
Gravel = 0.90 m3 /m3 x 1,162.10 /m3 = 1,045.89 /m3
S.Paving Form = 1.60 lin.m./cu.m. x 260.70 P/lin.m. = 417.12 /m3
R. Form Stake = 2.00 pcs./cu.m. x 150.50 P/pc. = 301.00 /m3
Material Cost . . . . . = 4,675.34 /m3
b. Labor
b.1 Fabrication, Placing & Dismantling of Forms
Capability = 3.50 cu. m./day
2 -Carpenters @ 550.00 /day = 1,100.00 /day
4 -Laborers @ 400.00 /day = 1,600.00 /day
2,700.00 /day
2,700.00 / day
Cost = = 771.43 /m3
3.50 m3/day
5,000.00 / day
Cost = = 1,428.57 /m3
3.50 m3/day
c. Equipment Utilization
Utilized : 1 - Transit Mixer
Rental = 1,151.00 /hr. (incl. fuel & operator)
9.50 bags /m3 x 4.00 min./bag
Time of Mixer/day = = 0.63 hrs./m3
60.00 min./hr.
SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 4,675.30 - 4,675.30 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 2,200.00 110.00 2,310.00 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = 729.00 36.45 765.45 /m3
TOTAL DIRECT COST = 7,604.30 146.50 7,750.80 /m3
Plus: 20% OCM & Profit = 1,520.90 76.00 1,596.90 /m3
UNIT COST = 9,125.20 222.50 9,347.70 /m3
say 9,347.70 /m3
1. Class "A" Reinforced Concrete (211 kscm for Siphon/Box Culvert & Other Structures)
a. Materials
Cement = 9.00 bags /m3 x 253.10 / bag = 2,277.90 /m3
Sand = 0.45 m3 /m3 x 1,126.40 /m3 = 506.88 /m3
Gravel = 0.90 m3 /m3 x 1,162.10 /m3 = 1,045.89 /m3
F. Lumber = 25.00 bd. ft./m3 x 59.00 /bd. ft. = 1,475.00 /m3
Plywood = 1.25 pc./m3 x 835.80 /pc. = 1,044.75 /m3
Tie Wire = 1.20 kgs. /m2 x 100.60 /kg. = 120.72 /m2
CWN = 2.00 kgs. /m3 x 100.60 /kg. = 201.20 /m3
Material Cost . . . . . = 6,672.34 /m3
Page 56
b. Labor
b.1 Fabrication, Placing & Dismantling of Forms
Capability = 3.50 cu. m./day
2 -Carpenters @ 550.00 /day = 1,100.00 /day
4 -Laborers @ 400.00 /day = 1,600.00 /day
2,700.00 /day
2,700.00 / day
Cost = = 771.43 /m3
3.50 m3/day
5,000.00 / day
Cost = = 1,428.57 /m3
3.50 m3/day
c. Equipment Utilization
Utilized : 1 - Bagger Mixer
Rental = 172.00 /hr. (incl. fuel & operator)
9.00 bags /m3 x 10.00 min./bag
Time of Mixer/day = = 1.50 hrs./m3
60.00 min./hr.
SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 6,672.30 - 6,672.30 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 2,200.00 110.00 2,310.00 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = 258.00 12.90 270.90 /m3
TOTAL DIRECT COST = 9,130.30 122.90 9,253.20 /m3
Plus: 20% OCM & Profit = 1,826.10 91.30 1,917.40 /m3
UNIT COST = 10,956.40 214.20 11,170.60 /m3
say 11,170.60 /m3
950.00 /day
Cost = = 11.90 /kg.
80.00 kgs./day kgs./day
Plus: 20% OCM & Profit = 2.40 /kg.
5% VAT (Labor) = 0.60 /kg.
5% VAT (OCM & Profit) = 0.10 /kg.
UNIT COST = 15.00 /kg.
say 15.00 /kg.
D. GRAVEL BLANKET
1. Materials
Gravel = 0.80 cu.m./cu.m. x 1,162.10 /cu.m. = 929.68 /m3
Sand = 0.45 cu.m./cu.m. x 1,162.10 /cu.m. = 522.95 /m3
Page 57
Material Cost . . . . . = 1,452.63 /m3
2. Labor
Capability = 5.00 cu. m./day
1 -Laborers @ 400.00 /day = 400.00 /day
400.00 /day
400.00 / day
Cost = = 80.00 /m3
5.00 m3/day
SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 1,452.60 - 1,452.60 /m3
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 80.00 4.00 84.00 /m3
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = - - - /m3
TOTAL DIRECT COST = 1,532.60 4.00 1,536.60 /m3
Plus: 20% OCM & Profit = 306.50 15.30 321.80 /m3
UNIT COST = 1,839.10 19.30 1,858.40 /m3
say 1,858.40 /m3
b. Labor
b.1 Laying
Capability = 14.00 sq. m./day
1 -Mason @ 550.00 /day = 550.00 /day
2 -Laborers @ 400.00 /day = 800.00 /day
1,350.00 /day
Page 58
SUMMARY
5%VAT TOTAL
1. Material Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 665.60 - 665.60 /m2
2. Labor Cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . = 175.60 8.78 184.38 /m2
3. Equipment Utilization . . . . . . . . . . . . . . . . . . . . . . . . = - - - /m2
TOTAL DIRECT COST = 841.20 8.80 850.00 /m2
Plus: 20% OCM & Profit = 168.20 8.40 176.60 /m2
UNIT COST = 1,009.40 17.20 1,026.60 /m2
say 1,026.60 /m2
Page 59
DERIVATION OF UNIT COST
(ABC/EPC/UCD)
PROPOSED ROAD CONCRETING FOR BARANGAY MANGGA
I. DAILY RATES TO BE USED
Page 60
Utilized: Truck - Tractor with Trailer/Lowbed
Rental 1,620.00 /hr. (incl. fuel, oil and operator)
AHD 13.00 kms. (Samonte, Quezon, Isabela To Project Site)
No. of Trips : Heavy Equipment : 6 trips
Cycle Time:
13 kms. 13 kms
Travel Time = + = 0.81 hrs./trip
25 kph 45 kph
Loading & Unloading = 1.50 hrs./trip
Delay, etc = 0.50 hrs./trip
Total Time = 2.81 hrs./trip
Rental = 1,620.00 /hr. x 2.81 hrs/trip = 4,550.40
*for one (1) trip only.
Total Mob. & Demob Cost = 4,550.40 /trip x 6 trips = 27,302.40
3. Project Billboard
WORK TO BE DONE
ACTIVITY
unit Quantity Unit Cost Estimated Cost
1. EARTHWORKS
a. Common Structure Excavation (Manual) cu.m 1.00 200.00 200.00
2. CARPENTRY WORKS
a. Wood Frame (2"x2") bd.ft 25.00 75.00 1,875.00
b. CWN kg. 2.00 100.60 201.20
Sub-total 2,076.20
3. TARPAULIN
a. Tarpaulin l.s. 1.00 2,500.00 2,500.00
3. LABOR
a. Laborer (Half-day) unit 2.00 200.00 400.00
Sub-total 400.00
TOTAL AMOUNT 5,176.20
=
TOTAL DIRECT COST 5,176.20
A. PERSONAL PROTECTIVE
EQUIPMENT (PPPE) UNIT QUANTITY UNIT COST TOTAL COST
Page 61
QUANTITY
B. MEDICAL TEAM/ SAFETY DAILY RATE TOTAL COST
OFFICER
No. of PersonnelNo. of Days (Prop.
Proj. Duration)
Sub-total C 20,650.00
=
TOTAL DIRECT COST 242,050.00
3,233.00 /hr.
Cost = = 15.40 /m2
210 m2/hr
Plus: 20% OCM & Profit = 3.10 /m2
5% VAT (Equipment) = 0.80 /m2
5% VAT (OCM & Profit) = 0.20 /m2
UNIT COST = 19.50 /m2
say 19.50 /m2
C. STRUCTURE EXCAVATION
1. Common Materials
a. Using Dozer
Utilized : 160 HP Dozer
Production : 25 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)
3,233.00 /hr.
Cost = = 129.30 /m3
25 m3/hr
Plus: 20% OCM & Profit = 25.90 /m3
12% VAT (Equipment) = 15.50 /m3
12% VAT (OCM & Profit) = 3.10 /m3
Page 62
UNIT COST = 173.80 /m3
say 173.80 /m3
a. Using Backhoe
Utilized : 1.0 cu.m. Backhoe
Production : 30 cu. m./hr.
Rental : 3,494.00 /hr. (incl. Fuel & operator)
3,494.00 /hr.
Cost = = 116.50 /m3
30 m3/hr
Plus: 20% OCM & Profit = 23.30 /m3
5% VAT (Equipment) = 5.80 /m3
5% VAT (OCM & Profit) = 1.20 /m3
UNIT COST = 146.80 /m3
say 146.80 /m3
c. Manual
Utilized : 1 - Laborer
Production : 2.00 cu. m./day
Daily Rate : 400.00 /day
400.00 /day
Cost = = 200.00 /m3
2 m3/day
Plus: 20% OCM & Profit = 40.00 /m3
5% VAT (Labor) = 10.00 /m4
5% VAT (OCM & Profit) = 2.00 /m3
UNIT COST = 252.00 /m3
say 252.00 /m3
D. CANAL EXCAVATION
1. Common Materials
a. Using Backhoe
Utilized : 1.0 cu.m. Backhoe
Production : 40 cu. m./hr.
Rental : 3,494.00 /hr. (incl. Fuel & operator)
3,494.00 /hr.
Cost = = 87.40 /m3
40 m3/hr
Plus: 20% OCM & Profit = 17.50 /m3
5% VAT (Equipment) = 4.40 /m3
5% VAT (OCM & Profit) = 0.90 /m3
UNIT COST = 110.20 /m3
say 110.20 /m3
3,233.00 /hr
Cost = = 53.88 /cu. m
60 /cu. m./hr.
2 Loading
Utilized : 1.0 cu.m. Loader
Production : 50 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)
Page 63
1,746.00 /hr
Cost = = 34.92 /cu. m
50 /cu. m./hr.
3 Hauling
use : 4.0 cu. m. Dump Truck
rental = 1,087.00 /hr.
AHD = 6 kms.
Shrinkage Factor = 15%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 6 kms. / 20 km./hr. = 0.30 hrs./trip
without load = 6 kms. / 25 km./hr. = 0.24 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 0.66 hrs./trip
1,087.00 /hr. x 0.66 hrs./trip
Cost = = 209.94 /cu. m
4 cu.m./trip x 85% s.f.
4 Spreading
Utilized : 160 HP Dozer
Production : 110 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)
3,233.00 /hr
Cost = = 29.39 /cu. m
110 /cu. m./hr.
5 Watering
Utilized : 5000 lit. Water Truck
Production : 70 cu. m./hr.
Rental : 1,672.00 /hr. (incl. Fuel & operator)
1,672.00 /hr
Cost = = 23.89 /cu. m
70 /cu. m./hr.
6 Compaction
Utilized : 8 Tons Vibratory Roller
Production : 40 cu. m./hr.
Rental : 1,616.00 /hr. (incl. Fuel & operator)
1,616.00 /hr
Cost = = 40.40 /cu. m
40 /cu. m./hr.
SUMMARY
Direct Cost 5%VAT TOTAL
1 Quarry Pit Fee = 70.00 - 70.00 /m3
2 Quarrying = 53.88 2.69 56.58 /m3
3 Loading = 34.92 1.75 36.67 /m3
4 Hauling = 209.94 10.50 220.44 /m3
5 Spreading = 29.39 1.47 30.86 /m3
6 Watering = 23.89 1.19 25.08 /m3
7 Compaction = 40.40 2.02 42.42 /m3
TOTAL DIRECT COST = 462.40 19.60 482.00 /m3
2% Excise Tax = 9.20 - 9.20 /m3
Plus: 20% OCM & Profit = 92.50 4.60 97.10 /m3
UNIT COST = 564.10 24.20 588.30 /m3
say 588.30 /m3
Page 64
E. STRUCTURE BACKFILL W/ COMPACTION (Side Borrow)
1. Manual
a. Backfilling
Utilized : 1 - Laborer
Production : 3.00 cu. m./day
Daily Rate : 400.00 /day
400.00 /day
Cost = = 133.33 /m3
3 m3/day
b. Compaction
Utilized : 1 - Laborer
Production : 5.00 cu. m./day
Daily Rate : 400.00 /day
400.00 /day
Cost = = 80.00 /m3
5 m3/day
SUMMARY
a. Backfilling = 133.33 /m3
b. Compaction = 80.00 /m3
TOTAL DIRECT COST 213.30 /m3
Plus: 20% OCM & Profit = 42.70 /m3
5% VAT (Labor) = 10.70 /m4
5% VAT (OCM & Profit) = 2.10 /m3
UNIT COST = 268.80 /m3
say 268.80 /m3
1,746.00 /hr
Cost = = 34.92 /cu. m
50 /cu. m./hr.
2 Hauling
use : 4.0 cu. m. Dump Truck
rental = 1,087.00 /hr.
AHD = 4 kms.
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 4 kms. / 20 km./hr. = 0.20 hrs./trip
without load = 4 kms. / 25 km./hr. = 0.16 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 0.48 hrs./trip
1,087.00 /hr. x 0.48 hrs./trip
Cost = = 129.53 /cu. m
4 cu.m./trip
4 Spreading
Utilized : 160 HP Dozer
Production : 110 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)
3,233.00 /hr
Cost = = 29.39 /cu. m
Page 65
Cost = = 29.39 /cu. m
110 /cu. m./hr.
SUMMARY
Direct Cost 5%VAT TOTAL
1 Loading = 34.92 1.75 36.67 /m3
2 Hauling = 129.53 6.48 136.01 /m3
3 Spreading = 29.39 1.47 30.86 /m3
TOTAL DIRECT COST = 193.80 9.70 203.50 /m3
Plus: 20% OCM & Profit = 38.80 1.90 40.70 /m3
UNIT COST = 232.60 11.60 244.20 /m3
say 244.20 /m3
M. Road Metalling
1 Quarrying
Utilized : 160 HP Dozer
Production : 65 cu. m./hr.
Rental : 3,233.00 /hr. (incl. Fuel & operator)
Equipment
3,233.00 /hr
Cost = = 49.74 /cu. m
65 /cu. m./hr.
2 Loading
Utilized : 1.0 cu.m. Loader
Production : 55 cu. m./hr.
Rental : 1,746.00 /hr. (incl. Fuel & operator)
Equipment
1,746.00 /hr
Cost = = 31.75 /cu. m
55 /cu. m./hr.
3 Hauling
use : 4.0 cu. m. Dump Truck
rental = 1,087.00 /hr.
AHD = 25 kms.
Shrinkage Factor = 5%
Type of Road : Poorly Maintained Road
speed of dump truck with load = 20 km./hr.
without load = 25 km./hr.
Cycle Time
travel time
with load = 25 kms. / 20 km./hr. = 1.25 hrs./trip
without load = 25 kms. / 25 km./hr. = 1.00 hrs./trip
Loading, Unloading, Maneuvering, delays, etc. = 0.12 hrs./trip
total time = 2.37 hrs./trip
1,087.00 /hr. x 2.37 hrs./trip
Cost = = 676.99 /cu. m
4 cu.m./trip x 95% s.f.
4 Spreading
Utilized : 110 HP Grader
Production : 70 cu. m./hr.
Rental : 1,658.00 /hr. (incl. Fuel & operator)
1,658.00 /hr
Cost = = 23.69 /cu. m
70 /cu. m./hr.
5 Compaction
Utilized : 8 Tons Vibratory Roller
Production : 60 cu. m./hr.
Rental : 1,616.00 /hr. (incl. Fuel & operator)
1,616.00 /hr
Cost = = 26.93 /cu. m
60 /cu. m./hr.
Page 66
SUMMARY
Direct Cost 5%VAT TOTAL
1 Quarrying = 49.74 2.49 52.23 /m3
2 Loading = 31.75 1.59 33.33 /m3
3 Hauling = 676.99 33.85 710.84 /m3
4 Spreading = 23.69 1.18 24.87 /m3
5 Compaction = 26.93 1.35 28.28 /m3
TOTAL DIRECT COST = 809.10 40.50 849.60 /m3
Plus: 20% OCM & Profit = 161.80 8.10 169.90 /m3
UNIT COST = 970.90 48.60 1,019.50 /m3
say 1,019.50 /m3
Page 67
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
A.1
B.1
F.1
Engineer II Engineer II
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
-
-
F.1 -
-
Engineer II Engineer II
Farm to Market Road Barucoc - San Juan
Quezon, Isabela
Engineer II Engineer II
DETAILED UNIT COST ANALYSIS
Subtotal A 290.28
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Dump Truck 0 1.00 1,420.00 - 1.00
Payloader 0 1.00 1,810.96 - 1.00
Bulldozer 0 1.00 3,492.53 - 1.00
Subtotal B -
Subtotal A -
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Low bed trailer 2 1.00 3,750.00 7,500.00 1.00
Payloader 1 1.00 1,810.96 1,810.96 1.00
Bulldozer 1 1.00 3,492.53 3,492.53 1.00
Backhoe 1 1.00 1,537.00 1,537.00 1.00
Dump truck 2 1.00 1,420.00 2,840.00 1.00
Motorized Road Grader 1 1.00 2,260.48 2,260.48 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00
Plate Compactor 1 1.00 123.00 123.00 1.00
Dump truck 1 1.00 1,420.00 1,420.00 1.00
Subtotal B 25,443.79
Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Dump Truck 2 1.00 1,420.00 2,840.00 1.00
Payloader 1 1.00 1,810.96 1,810.96 1.00
Bulldozer 1 1.00 3,492.53 3,492.53 1.00
Subtotal B 8,143.49
Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Backhoe 2 1.00 1,537.00 3,074.00 1.00
Payloader 1 1.00 1,810.96 1,810.96 1.00
Payloader 1 0.25 1,810.96 452.74 1.00
Dump truck 2 1.00 1,420.00 2,840.00 1.00
Minor Tools (10% of Labor Cost) 21.63
Subtotal B 8,199.33
Subtotal C -
SUMMARY
A. Labor 216.32
B. Equipment 8,199.33
C. Materials -
D. Total Estimated Direct Cost 8,415.65
E. Direct Unit Cost 140.26
F. OCM 0.12 1,009.88
G. Profit 0.08 673.25
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 504.94
L. Unit Cost 176.73
DETAILED UNIT COST ANALYSIS
Subtotal A 395.86
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Backhoe 2 1.00 1,537.00 3,074.00 1.00
Dump Truck 1 1.00 1,420.00 1,420.00 1.00
PayLoader 1 1.00 1,810.96 1,810.96 1.00
Motorized Road Grader 2 1.00 2,260.48 4,520.96 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00
Minor Tools (10% of Labor Cost) -
Subtotal B 15,285.74
Subtotal A 273.29
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Backhoe 2 1.00 2,689.75 5,379.50 1.00
Plate Compactor 1 1.00 215.25 215.25 1.00
Minor Tools (10% of Labor Cost) 27.33 1.00
Subtotal B 5,622.08
Subtotal C -
SUMMARY
A. Labor 273.29
B. Equipment 5,622.08
C. Materials -
D. Total Estimated Direct Cost 5,895.37
E. Direct Unit Cost 599.12
F. OCM 0.12 707.44
G. Profit 0.08 471.63
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 353.72
L. Unit Cost 754.89
DETAILED UNIT COST ANALYSIS
Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Motorized Road Grader 1 1.00 2,260.48 2,260.48 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00
Subtotal B 6,720.30
Subtotal C -
SUMMARY
A. Labor 216.32
B. Equipment 6,720.30
C. Materials -
D. Total Estimated Direct Cost 6,936.62
E. Direct Unit Cost 23.12
F. OCM 0.12 832.39
G. Profit 0.08 554.93
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 416.20
L. Unit Cost 29.13
DETAILED UNIT COST ANALYSIS
Subtotal A 216.32
Name and capacity No of units No of hours Hourly rate Amount
B. Equipment
Motorized Road Grader 1 1.00 2,260.48 2,260.48 1.00
Vibratory Roller 1 1.00 1,916.40 1,916.40 1.00
Water Truck/Pump 1 1.00 2,543.42 2,543.42 1.00
Subtotal B 6,720.30
Subtotal C 13,951.88
SUMMARY
A. Labor 216.32
B. Equipment 6,720.30
C. Materials 13,951.88
D. Total Estimated Direct Cost 20,888.49
E. Direct Unit Cost 417.77
F. OCM 0.12 2,506.62
G. Profit 0.08 1,671.08
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 1,253.31
L. Unit Cost 526.39
DETAILED UNIT COST ANALYSIS
Subtotal C -
SUMMARY
A. Labor 478.18
B. Equipment 3,280.91
C. Materials -
D. Total Estimated Direct Cost 3,759.09
E. Direct Unit Cost 3,759.09
F. OCM 0.12 451.09
G. Profit 0.08 300.73
H. Mineral Tax
I. Excise Tax
J. Contractor's Tax 0
K. VAT 0.05 225.55
L. Unit Cost 4,736.45
Republic of the Philippines
Province of Isabela
MUNICIPALITY OF QUEZON
Office of the Municipal Engineer
Road Construction
Width per lane : 2.50 m
No. of Lanes : 2.00
Width of Shoulder : 1.00 m
Thickness of surface road : 0.23 m
Length of Road : 562.00 m
Thickness of PCC : 0.23 m
2. Earthworks
Clearing and Grubbing Area (sq.m.) Volume (cu.m.)
Station Remarks
Width Area Fill Cut Fill Cut
0+000 7.00 0.14 0.35
0+020 7.00 14.00 0.14 0.35 2.80 7.00
0+040 7.00 14.00 0.14 0.35 2.80 7.00
0+060 7.00 14.00 0.14 0.35 2.80 7.00
0+080 7.00 14.00 0.14 0.35 2.80 7.00
0+100 7.00 14.00 0.14 0.35 2.80 7.00
0+120 7.00 14.00 0.14 0.35 2.80 7.00
0+140 7.00 14.00 0.14 0.35 2.80 7.00
0+160 7.00 14.00 0.14 0.35 2.80 7.00
0+180 7.00 14.00 0.14 0.35 2.80 7.00
0+200 7.00 14.00 0.14 0.35 2.80 7.00
0+220 7.00 14.00 0.14 0.35 2.80 7.00
0+240 7.00 14.00 0.14 0.35 2.80 7.00
0+260 7.00 14.00 0.14 0.35 2.80 7.00
0+280 7.00 14.00 0.14 0.35 2.80 7.00
0+300 7.00 14.00 0.14 0.35 2.80 7.00
0+320 7.00 14.00 0.14 0.35 2.80 7.00
0+340 7.00 14.00 0.14 0.35 2.80 7.00
0+360 7.00 14.00 0.14 0.35 2.80 7.00
0+380 7.00 14.00 0.14 0.35 2.80 7.00
0+400 7.00 14.00 0.14 0.35 2.80 7.00
0+420 7.00 14.00 0.14 0.35 2.80 7.00
0+440 7.00 14.00 0.14 0.35 2.80 7.00
0+460 7.00 14.00 0.14 0.35 2.80 7.00
0+480 7.00 14.00 0.14 0.35 2.80 7.00
0+500 7.00 14.00 0.14 0.35 2.80 7.00
0+520 7.00 14.00 0.14 0.35 2.80 7.00
0+540 7.00 14.00 0.14 0.35 2.80 7.00
0+560 7.00 14.00 0.14 0.35 2.80 7.00
0+562 7.00 1.40 0.14 0.35 0.28 0.70
TOTAL 393.40 10.15 78.68 196.70
1.PCC
Vc = Length x Width x Thickness
Vc = 562.00 x 5.00
Vc = 2,810.00 sq.m.
2. Subgrade Preparation
V = Length x Width
V = 562.00 x 7.00
V = 3,934.00 sq.m.
Approved by:
A.1
B.1
F.1
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment
Name and Capacity No of Unit/s No. of Hours Monthly Rate Amount (PhP)
Equipment
F.1
F.1
F.1
Item No./Description : 311(1)c1 Portland Cement Concrete Pavement (Unreinforced) - 0.23 m thick, 14 days
Quantity : 70
Unit of Measurement : sq.m.
Output per hour - As Submitted : 70.00
Output per hour - As Evaluated :
F.1
F.1
Item No./Description : 500 (1)a1 Pipe Culverts (610mm) Class II, RCPC
Quantity : 1
Unit of Measurement : ln.m.
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated :
Approved by:
A.1. Laborer
Approved by:
Approved by:
B. MATERIALS
Approved by:
DESCRIPTION QTY UNIT UNIT COST ESTIMATED DIRECT COST OCM & PROFIT VAT TOTAL INDIRECT COST TOTAL COST
A. EARTHWORKS
B. ROAD CONSTRUCTION
Approved by: