HASIL OPNAME PEKERJAAN

DIVISI : Beton fc' 14.5 Mpa


ITEM PEKERJAAN : Saluran V (fore slope dan back slope) Hari/Tanggal : 17 November 2022
RUAS : KIRI (BARU) Lokasi : Site

Panjang (m) Lebar (m) Lebar Rata-rata (m) Tebal (m) Pengurangan Luas Volume (m3)
No. Ruas Station
a b c=(b1+b2)/2 d e f=(a x c x e)

0+000 3.25
1 17.00 3.29 0.15 8.38
0+017 3.32
2 43.24 3.36 0.15 21.79
0+060.24 3.40

0+000 3.50
3 3.10 3.45 0.15 0.72 1.50
0+003.10 3.40

0+000 3.22
4 42.80 3.30 0.15 3.78 20.62
0+042.80 3.38

0+000 3.40
5 36.50 3.39 0.15 18.56
0+036.50 3.38

0+000 3.38
6 18.00 3.39 0.15 9.15
0+018 3.40
TOTAL VOLUME 80.00
HASIL OPNAME PEKERJAAN

DIVISI : Beton fc' 14.5 Mpa


ITEM PEKERJAAN : Saluran V (fore slope dan back slope) Hari/Tanggal : 17 November 2022
RUAS : KIRI Lokasi : Site

Panjang (m) Lebar fore slop Lebar back slope Tebal (m) Pengurangan Luas Volume (m3)
No. Ruas Station
a b c d e f=ax(b+c)xd
0+000
1 58.80 1.80 1.50 0.15 29.11
0+058.80

0+000
2 14.50 1.80 1.50 0.15 7.18
0+014.50

0+000
3 24.20 1.80 1.50 0.15 11.98
0+024.20

0+000
4 88.20 1.80 1.50 0.15 3.69 43.11
0+088,2

0+000
5 82.00 1.80 1.50 0.15 40.59
0+082

0+000
6 192.05 1.80 1.50 0.15 95.06
0+192.05

0+000
7 35.00 1.80 1.50 0.15 17.33
0+035
0+000
8 92.70 1.80 1.50 0.15 45.89
0+092.70

0+000
9 158.80 1.80 1.50 0.15 78.61
0+158.80

0+000
9 126.15 1.80 1.50 0.15 62.44
0+126.15

0+000
10 53.30 1.80 1.50 0.15 26.38
0+053.30

TOTAL VOLUME 457.67


HASIL OPNAME PEKERJAAN

DIVISI : Beton fc' 14.5 Mpa


ITEM PEKERJAAN : Saluran V (fore slope dan back slope) Hari/Tanggal : 17 November 2022
RUAS : KANAN Lokasi : Site

Panjang (m) Lebar fore slop Lebar back slope Tebal (m) Pengurangan Luas Volume (m3)
No. Ruas Station
a b c d e f=ax(b+c)xd
0+000
1 57.20 1.80 1.50 0.15 28.31
0+057.20

0+000
2 100.00 1.80 1.50 0.15 49.50
0+100

0+000
3 75.80 1.80 1.50 0.15 37.52
0+075.80

0+000
4 159.80 1.80 1.50 0.15 79.10
0+159.80

0+000
5 55.50 1.80 1.50 0.15 27.47
0+055.50

0+000
6 80.00 1.80 1.50 0.15 39.60
0+080

0+000
7 38.20 1.80 1.50 0.15 18.91
0+038.20
0+000
8 284.50 1.80 - 0.15 76.82
0+284.50

0+000
9 55.40 1.80 - 0.15 14.96
0+055.40

TOTAL VOLUME 372.19


REKAPITULASI

PANJANG VOLUME
NO STA
M M3

1 RUAS KIRI (BARU) 160.64 80.00

2 RUAS KIRI (LAMA) 925.70 457.67

3 RUAS KANAN 1 SISI (FORE SLOPE) 339.90 91.77

4 RUAS KANAN (LAMA) 566.50 280.42

TOTAL 1,992.74 909.86


1,086.34

906.40