You are on page 1of 8

4th shift scenario – cutting area

Hugo López 08.07.2020


4th shift proposal

Explanation:

➢ The 4th shift proposal is used when we would like to use 100% of capacity installed of
machine(s), that is the 21 shifts available of the week, that is an additional 23% of
available capacity

➢ The concept is to have 4 groups of people, working 12 x 12 shifts, in a 4x3 and 4x4
configuration, rotating as follows: Every month in days, every 2 weeks in day / night

➢ Every month, 1 day must be a rest day, in order to make the rotation between groups
smooth and not to overburden people, and to do a full maintenance to increase
equipment reliability

➢ The overall working hours in total per person is 42 hrs, (12 x 3 + 12 x 4) / 2

2
4th shift proposal

Benefits:

➢ Overtime is eliminated completely

➢ People is more willing to work like this since they will have 3 and 4 resting days
respectively

➢ 100% machine utilization, added capacity 23%

➢ Time to do a full maintenance once per month, to maintain optimum equipment


utilization. Another possibility is to stop 1 machine per shift, during 1 week, so that
reliability of equipment is always achieved

3
4th shift proposal

Strategy

➢ Will be only for people for cutting area

➢ Additional HC will be temporarily needed, since this scenario will be used for 8
weeks, until the neccesary wire stocks are recovered.

+10 cutting operators; the cutting operator position is a special category with higher salary in MX plant. To
avoid increasing the salary, a temporary bonus will be given to selected operators with a special contract
agreement with them.

+1 Technician, a temporary contract with an intern will be given for this position.

+2 people from Logistics (WH & wires), will be temporarily hired.

+1 QA inspector, will be temporarily hired.

4
Julio 2020
Domingo Lunes Martes Miércoles Jueves Viernes Sábado
1 2 3 4

Example of the shift proposal with the 4


groups. Must
5 start with6 a resting Saturday
7 to 8 9 10 11
give maintenance of equipments, and a N/A
N/A
Sunday to start operations

12 13 14 15 16 17 18
G1 G1 G1 G3 G3 G3 G3
G2 G2 G2 G4 G4 G4 G4

19 20 21 22 23 24 25
G1 G1 G1 G3 G3 G3 G3
G2 G2 G2 G4 G4 G4 G4

26 27 28 29 30 31 Notes:
G2 G2 G2 G4 G4 G4
G1 G1 G1 G3 G3 G3

5
Agosto 2020
Domingo Lunes Martes Miércoles Jueves Viernes Sábado
1
G4
G3

2 3 4 5 6 7 8
G2 G2 G2 G4 G4 G4 G4
G1 G1 G1 G3 G3 G3 G3

9 10 11 12 13 14 15
N/A G3 G3 G1 G1 G1 G1
N/A G4 G4 G2 G2 G2 G2

16 17 18 19 20 21 22
G3 G3 G3 G1 G1 G1 G1
G4 G4 G4 G2 G2 G2 G2

23 24 25 26 27 28 29
G4 G4 G4 G2 G2 G2 G2
G3 G3 G3 G1 G1 G1 G1

30 31 Notes:
G4 G4
G3 G3

6
Septiembre 2020
Domingo Lunes Martes Miércoles Jueves Viernes Sábado
1 2 3 4 5
G4 G2 G2 G2 G2
G3 G1 G1 G1 G1

6 7 8 9 10 11 12
G4 G4 G4 G2 G2 G2 G2
G3 G3 G3 G1 G1 G1 G1

13 14 15 16 17 18 19
N/A
N/A

20 21 22 23 24 25 26

27 28 29 30 Notes:

7
Hugo López