Explanation:
➢ The 4th shift proposal is used when we would like to use 100% of capacity installed of
machine(s), that is the 21 shifts available of the week, that is an additional 23% of
available capacity
➢ The concept is to have 4 groups of people, working 12 x 12 shifts, in a 4x3 and 4x4
configuration, rotating as follows: Every month in days, every 2 weeks in day / night
➢ Every month, 1 day must be a rest day, in order to make the rotation between groups
smooth and not to overburden people, and to do a full maintenance to increase
equipment reliability
2
4th shift proposal
Benefits:
➢ People is more willing to work like this since they will have 3 and 4 resting days
respectively
3
4th shift proposal
Strategy
➢ Additional HC will be temporarily needed, since this scenario will be used for 8
weeks, until the neccesary wire stocks are recovered.
+10 cutting operators; the cutting operator position is a special category with higher salary in MX plant. To
avoid increasing the salary, a temporary bonus will be given to selected operators with a special contract
agreement with them.
+1 Technician, a temporary contract with an intern will be given for this position.
4
Julio 2020
Domingo Lunes Martes Miércoles Jueves Viernes Sábado
1 2 3 4
12 13 14 15 16 17 18
G1 G1 G1 G3 G3 G3 G3
G2 G2 G2 G4 G4 G4 G4
19 20 21 22 23 24 25
G1 G1 G1 G3 G3 G3 G3
G2 G2 G2 G4 G4 G4 G4
26 27 28 29 30 31 Notes:
G2 G2 G2 G4 G4 G4
G1 G1 G1 G3 G3 G3
5
Agosto 2020
Domingo Lunes Martes Miércoles Jueves Viernes Sábado
1
G4
G3
2 3 4 5 6 7 8
G2 G2 G2 G4 G4 G4 G4
G1 G1 G1 G3 G3 G3 G3
9 10 11 12 13 14 15
N/A G3 G3 G1 G1 G1 G1
N/A G4 G4 G2 G2 G2 G2
16 17 18 19 20 21 22
G3 G3 G3 G1 G1 G1 G1
G4 G4 G4 G2 G2 G2 G2
23 24 25 26 27 28 29
G4 G4 G4 G2 G2 G2 G2
G3 G3 G3 G1 G1 G1 G1
30 31 Notes:
G4 G4
G3 G3
6
Septiembre 2020
Domingo Lunes Martes Miércoles Jueves Viernes Sábado
1 2 3 4 5
G4 G2 G2 G2 G2
G3 G1 G1 G1 G1
6 7 8 9 10 11 12
G4 G4 G4 G2 G2 G2 G2
G3 G3 G3 G1 G1 G1 G1
13 14 15 16 17 18 19
N/A
N/A
20 21 22 23 24 25 26
27 28 29 30 Notes: