Professional Documents
Culture Documents
Homework Assignment #10
Homework Assignment #10
I PV
50,000
Eo
40,000
EY gg
ftp
pg 50,000
As SPI I 1 we
Iq
15,750
10,237.5
10,237.5 10.500
262.57
10,2375 15,750
5,512 5
I 10,237.5
10,500
0.975
10,237.5
15,750
0.65
project is determined as
CPI 0.975
5,653 85
d total cost
of completing this project EAC is
The
final
determined as
EAC ETC t AC
5,653.85 10,500
16,153.85
by 100
BAC
15,750
2.56
I think the
project cost overrun
only be 2.561 is not that
estimates
yourI
It's
25
325,000
If
243,750
243,750 250,000
6,250
Schedule variance SV EV PV
243,750 325,000
81,250
Eng
243,750 0.975
250,000
243,750
325,000
0.75
The
project is determined as
CPI 0.975
83,333.34
determined as
EAC ETC AC
83,333 34 250,000
333,333 34
by 100
BAC
325,000
2.5641
5 8
o g
11 13
95
3512
5 11 it
dlf
S
O 4
JE
ble 4 8 8 14
sea 816
63
3.06067
CPI
EV 3,100 0.96875
CPI
AC 3,200
EY 3,066.67
3,100 3,200
I 100
SU EV PV
Schedule Variance
3,100 3,066.67
33.33
slightly doing
in schedule
good
Additional money that will be required to finish the
project is determined as
1,445.16
total cost
of completing this project EAC is
The
final
determined as
3.22