PRELIMINARIES

Item Description Unit Qty Rate Amount (RM)

A Generally

B Definitions

C Location of Site and Visit to Site

D Scope of Works

E Form of Contract

F Appendix to the Conditions of Contract

G Temporary Lighting and Power Supply sum 1 32,000.00 32,000.00

H Temporary Hoarding and Gates sum 1 44,000.00 44,000.00

I Temporary Access Roads sum 1 15,000.00 15,000.00

J Temporary Drains, Silt Trap and Washing Tyres of Vehicles sum 1 28,000.00 28,000.00

K Project Signboard (2 nrs) sum 1 14,000.00 14,000.00

L Site Security, Safeguarding the Works and Watching sum 1 60,000.00 60,000.00

M Temporary Water Supply sum 1 22,000.00 22,000.00

N Discrepancies in Drawings sum 1 12,500.00 12,500.00

O Site Supervisory Staff sum 1 110,000.00 110,000.00

P Insuring the Works sum 1 38,000.00 38,000.00

Q Plant and Equipment sum 1 250,000.00 250,000.00

R Construction Industry Development Board Levy sum 1 23,000.00 23,000.00

S Setting Out sum 1 24,500.00 24,500.00

T Programme and Progress Charts sum 1 18,000.00 18,000.00

U Existing Services sum 1 18,000.00 18,000.00

V As-Built Drawings sum 1 20,000.00 20,000.00

Carried Forward
729,000.00
Item Description Unit Qty Rate Amount (RM)
Brought Forward 729,000.00

W Progress Reports and Progress Photographs sum 1 16,000.00 16,000.00

X Safety, Health and Welfare of Workmen and Fire Regulations sum 1 15,000.00 15,000.00

Y Standard Operating Procedures (SOP) sum 1 13,000.00 13,000.00

Z Mosquito Prevention sum 1 9,000.00 9,000.00

AA Site Meetings sum 1 15,000.00 15,000.00

AB Interim Progress Payment sum 1 74,000.00 74,000.00

AC Sait Facilities sum 1 21,000.00 21,000.00

AD Clearing of Site and Clearing of Building, etc. sum 1 12,000.00 12,000.00

AE Any Other Items

i)

ii)

iii)

Total Preliminaries Carried to Final Summary 904,000.00