1 prelim 186,500.

00
2 109,915.00
3 392,120.00
4 78,965.00
5 120,000.00

887,500.00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL A
A project signboard ls 7,000.00

B site survey and setting out ls 29,000.00

C temporary diversion and relocation of existing


overhead and underground services ls 10,000.00

D construction plan ls 11,000.00

E contractor's plant ls 8,000.00

A/7 65,000.00 65,000.00

A Temporary water and power supplies for the works ls 4,500.00

B Temporary Access and maintenance of existing roads Ls 7,500.00

C Control of workmen, plant and machinery at site Ls 8,000.00

A/8 20,000.00 20,000.00

A contractor's office and storage Ls 10,000.00

B Care and protection of materials and works ls 5,000.00

C shop drawing, samples and mock-ups ls 4,000.00

D Progress photograps Progress Reports ls 2,000.00

A/9 21,000.00 21,000.00

A Material testing laboratory and staff ls 2,000.00

B Survey instruments and personnel ls 10,000.00

C site item for S.O/ Office Equipment And Facilities Ls 2,000.00

D fire LS 500.00

F safe working area ls 5,000.00

A/10 19,500.00 19,500.00

B safety healt and welfare LS 1,000.00

A/11 1,000.00 1,000.00

B traffic safety ls 4,000.00

keeping the site tidy


C ls 2,000.00

D as-built drawing ls 8,000.00

A/12 14,000.00 14,000.00


A clearing, cleaninig and making good on completion ls 10,000.00

B form of contract ls 2,000.00

C performance bond ls -

A/13 12,000.00 12,000.00

A Employees Social Security Act 1969 ls 2,000.00

B Insurrance of works ls 2,000.00

E site agent and assistants ls 24,000.00

A/14 28,000.00 28,000.00

A protection of existing services ls 1,000.00

B services and maintenance ls 5,000.00

A/15 6,000.00 6,000.00

A/7 65,000.00
A/8 20,000.00
A/9 21,000.00
A/10 19,500.00
A/11 1,000.00
A/12 14,000.00
A/13 12,000.00
A/14 28,000.00
A/15 6,000.00

186,500.00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL B:BAIK PULIH SURAU DAN BILIK PERSALINAN

KERJA MEROBOH DAN MEMBUANG SISA BINAAN


1 KERJA NO.1 HINGGA NO.8 LS 48,000.00

B 1/4 48,000.00 48,000.00

A meroboh sebahagian dinding , tingkap dan aksesori


kelengkapan surau 60m2 ls 8,000.00

BAIK PULIH SURAU


B kerawang jenis islamik 2m2 no.3 3 2,480.00 7,440.00

C bata 113mm termasuk plaster dan cat m2 23 171.00 3,933.00

d pintu panel 0.9m x 2.1m termasuk frame aluminium no 2 2,250.00 4,500.00

e mozek non slip 300mm x 300mm m2 25 200.00 5,000.00

B 2/4 20,873.00 20,873.00

BAIK PULIH bilik persalinan

a pasang taing susur tangan GI 50mm termasuk cat m 30 500.00 15,000.00

b konkrit lantai 200mm m2 34 438.00 14,892.00

c bina tiang 300mm x 300mm x 3000mm no 2 1,200.00 2,400.00

d tukar bumbung metal deck yang rosak 35m2 ls 8,750.00

B 3/4 41,042.00 41,042.00

B1/4 48,000.00
B2/4 20,873.00
B3/4 41,042.00

109,915.00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL C:naiktaraf kemudahan infrastruktur (provi)

pelantar
A membina tangga 1700mm (P) x 1500mm (L) no 1 2,500.00 2,500.00

B membina footing 300mm x 300mm x 150mm no 2 300.00 600.00

c tiang 200mm x 200mm x 700mm no 2 600.00 1,200.00

d lantai 200mm m2 16 438.00 7,008.00

laluan penjalan kaki


e lantai 200mm m2 17 438.00 7,446.00

f dinding bata tanah liat 113mm m2 6 171.00 1,026.00

tangga ke tasik
g cat keseluruhan susur tangan m 300 35.00 10,500.00

C1/3 30,280.00 30,280.00

tangga ke tasik
a cat lantai berbentuk anak panah no 2 450.00 900.00

laluan penjalan kaki ke pelantar terapung


B lantai 200mm m2 630 438.00 275,940.00

naiktaraf pelantar terpung


c baik pulih pelantar terapung seperti penyambung
antara pelantardan cat semula frame dan ganti baru G!
84m2 LS 30,000.00

d kayu jenis balau 100mm lebar x 50mm lm2 32 1,250.00 40,000.00

e tiang susur tangan no 32 250.00 8,000.00

f tali jut 15mm m 280 25.00 7,000.00

C2/3 361,840.00 361,840.00

C1/3 30,280.00
C2/3 361,840.00

392,120.00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL D:- PEPARITAN (ALL PROVI)

a kerja2 memasang longkang 300mm dia m 115 200.00 23,000.00

b penutup longkang besi 12mm m 115 228.00 26,220.00

c dinding bata tanah merah 113mm m2 95 171.00 16,245.00

d sump 1000mm x 1000mm no 3 4,500.00 13,500.00

78,965.00
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
BILL D: provisional sump

a baik pulih tangga dan pelantar ps 100,000.00

b kerja luar jangkan ps 20,000.00

120,000.00