You are on page 1of 1

Analisa Harga Satuan Penutup Atap Asphalt /m2

GAF Asphalt Shingles Timberline - 0,337 x 1 Mtr


HARGA JUMLAH
KOEFISIE
No. URAIAN PEKERJAAN SATUAN SATUAN HARGA
N
(Rp. ) (Rp. )
1 2 3 4 5 6
A TENAGA
1 Pekerja OH 110.000,00 0,200 22.000,00
2 Tukang Kayu OH 125.000,00 0,300 37.500,00
3 Kepala Tukang OH 145.000,00 0,003 435,00
4 Mandor OH 175.000,00 0,010 1.750,00
Jumlah 61.685,00
B BAHAN
1 Genteng Asphalt Timberline bundle 975.000,00 0,328 320.021,88
2 Underlayment FeltBuster roll 2.600.000,00 0,011 27.967,82
3 Plywood 12mm meranti grade A lbr 260.000,00 0,350 91.000,00
4 Paku 1inch (zinc-coated steel/custom) kg 40.000,00 0,050 2.000,00
5 Paku 2inch for plywood kg 30.000,00 0,200 6.000,00
Jumlah 446.989,70
C Jumlah A+B 508.674,70
D Overhead & Profit 15% 76.301,20
E Harga Satuan Pekerjaan (C+D) 584.975,90