PEPERIKSAAN AKHIR
SESI DISEMBER 2018
Notes:
Nota-nota:
3. Marks will be given for the knowledge of the subject, clear and systematic
setting of dimensions, adequacy and accuracy of description and
dimensions.
Markah akan diberi untuk pengetahuan tentang subjek, tata atur yang
sistematik, kecukupan dan ketepatan dimensi dan keterangan.
2 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
SECTION A: 50 MARKS
BAHAGIAN A: 50 MARKAH
INSTRUCTION:
This section consists of TWO (2) structured essay questions. Answer ALL questions.
ARAHAN:
Bahagian ini mengandungi DUA (2) soalan esei berstruktur. Jawab SEMUA soalan.
QUESTION 1
SOALAN 1
CLO1 (a) Referring to SMM2, explain clauses E.5.1 which related to precast concrete pile.
C2
Merujuk kepada SMM2, terangkan klausa E.5.1 yang berkaitan dengan cerucuk
konkrit pra tuang.
[3 marks]
[3 markah]
No of Estimate
No of Supply
Type pile Size Penetration Others
point length
caps depth
6.00m Concrete
P3 8 3 200x200mm 14.00m
long grade 35
6.00m with weight
P5 3 5 200x200mm 14.00m
long of shoe and
6.00m head 5kg/no
P6 4 6 200x200mm 14.00m
long
3 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
CLO1 (b) Based on Table 1, carry out the quantities measurement for Maintaining and
C3 Handling Plant On Site, Supply Initial Pile and Supply Extension Pile.
(c) Conclude all the measured quantities in Question 1 (b), as the bill of quantities.
CLO1
C4
Rumuskan semua kuantiti terukur dalam Soalan 1(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
QUESTION 2
SOALAN 2
CLO1 (a) Based on the Drawing No. DCQ5083/SERVICES/01-05, identify the builder
work in connection with sanitary fittings.
C2
Berpandukan Lukisan No. DCQ5083/SERVICES/01-05, kenalpasti kerja-kerja
pembina yang berkaitan dengan kerja lekapan kebersihan.
[3 Marks]
[3 markah]
CLO1 (b) Based on the Drawing No. DCQ5083/SERVICES/01-05, carry out the quantities
C3 measurement for sanitary fittings in Bath 2 ONLY.
4 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
CLO1 (c) Conclude all the measured quantities in Question 2(b) as the bill of quantities.
C4
Rumuskan semua kuantiti terukur dalam Soalan 2(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
5 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
SECTION B : 50 MARKS
BAHAGIAN B: 50 MARKAH
INSTRUCTION:
This section consists of FOUR (4) essay questions. Answer TWO (2) questions only.
ARAHAN:
Bahagian ini mengandungi EMPAT (4) soalan esei. Jawab DUA (2) soalan sahaja.
QUESTION 1
SOALAN 1
CLO1 (a) Identify the usage of soil, waste and vent pipe.
C2
CLO1 (b) Based on the Drawing No. DCQ5083/SERVICES/01-05 carry out the quantities
C3 measurement for excavation works and piping woks for soil pipe ONLY.
(c) Conclude all the measured quantities in Question 1 (b) as the bill of quantities.
CLO1
C4
Rumuskan semua kuantiti terukur dalam Soalan 1(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
6 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
QUESTION 2
SOALAN 2
CLO 1 (a) Differentiate between one way and two way switch.
C2
CLO1 (b) Based on the Drawing No. DCQ5083/SERVICES/01-05, carry out the quantities
C3 measurement for switch and power plug.
(c) Conclude all the measured quantities in Question 2(b) as the bill of quantities.
CLO1
C4
Rumuskan semua kuantiti terukur dalam Soalan 2(b) sebagai senarai kuantiti.
[8 Marks]
[8 markah]
QUESTION 3
SOALAN 3
CLO1 (a) Based on SMM2, identify TWO (2) clauses of sheet pile measured in m2.
C2
Berdasarkan SMM2, kenalpasti DUA (2) klausa berkenaan cerucuk kepingan
yang diukur dalam m2.
[3 marks]
[3 markah]
7 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
(b) Based on the Drawing No. DCQ5083/SHEETPILE/01, carry out the quantities
CLO1
C3 measurement for item measured in m2 ONLY.
CLO1 (c) Conclude all the measured quantities in Question 3(b) as the bill of quantities.
C4
Rumuskan semua kuantiti terukur dalam Soalan 3(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
QUESTION 4
SOALAN 4
CLO1 (a) Referring to the SMM2, identify and explain the clause related to the excavation
C2 of plumbing works.
(b) Based on the Drawing No. DCQ5083/ SERVICES/01- 05, carry out the
CLO1
C3 quantities measurement for plumbing work from water tank to Bath 1 ONLY.
[14 marks]
[14 markah]
8 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
CLO1 (c) Conclude all the measured quantities in Question 4(b) as the bill of quantities.
C4
Rumuskan semua kuantiti terukur dalam Soalan 4(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
SOALAN TAMAT
9 SULIT