You are on page 1of 15

SULIT

BAHAGIAN PEPERIKSAAN DAN PENILAIAN


JABATAN PENDIDIKAN POLITEKNIK DAN KOLEJ KOMUNITI
KEMENTERIAN PENDIDIKAN MALAYSIA

JABATAN KEJURUTERAAN AWAM

PEPERIKSAAN AKHIR
SESI DISEMBER 2018

DCQ5083: BUILDING WORKS MEASUREMENT 4

TARIKH : 22 April 2019


MASA : 2.30 PETANG - 4.30 PETANG (2 JAM)

Kertas ini mengandungi SEMBILAN (9) halaman bercetak.


Bahagian A: Esei Berstruktur (2 soalan)
Bahagian B: Esei Berstruktur (4 soalan)

Dokumen sokongan yang disertakan :


Buku Standard Method of Measurement 2

JANGAN BUKA KERTAS SOALAN INI SEHINGGA DIARAHKAN

(CLO yang tertera hanya sebagai rujukan)


SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

Notes:
Nota-nota:

1. Measurement of work must be referred to the principles laid down in


Standard Method of Measurement Building Works 2nd edition (SMM2).

Kerja-kerja pengukuran mestilah berasaskan prinsip-prinsip yang


dinyatakan di dalam Standard Method of Measurement of Buildings Works
2nd edition (SMM2).

2. Candidate is allowed to make any assumptions if the details or


specification are not provided or unclear. All assumptions must be clearly
stated in the answer scripts.

Calon dibenarkan membuat andaian jika spesifikasi dan perincian tidak


disediakan atau kurang jelas. Semua andaian mestilah dinyatakan dengan
jelas di dalam skrip jawapan.

3. Marks will be given for the knowledge of the subject, clear and systematic
setting of dimensions, adequacy and accuracy of description and
dimensions.

Markah akan diberi untuk pengetahuan tentang subjek, tata atur yang
sistematik, kecukupan dan ketepatan dimensi dan keterangan.

2 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

SECTION A: 50 MARKS
BAHAGIAN A: 50 MARKAH

INSTRUCTION:
This section consists of TWO (2) structured essay questions. Answer ALL questions.

ARAHAN:
Bahagian ini mengandungi DUA (2) soalan esei berstruktur. Jawab SEMUA soalan.

QUESTION 1
SOALAN 1

CLO1 (a) Referring to SMM2, explain clauses E.5.1 which related to precast concrete pile.
C2
Merujuk kepada SMM2, terangkan klausa E.5.1 yang berkaitan dengan cerucuk
konkrit pra tuang.
[3 marks]
[3 markah]

Table A1/ Jadual A1

No of Estimate
No of Supply
Type pile Size Penetration Others
point length
caps depth
6.00m Concrete
P3 8 3 200x200mm 14.00m
long grade 35
6.00m with weight
P5 3 5 200x200mm 14.00m
long of shoe and
6.00m head 5kg/no
P6 4 6 200x200mm 14.00m
long

3 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

CLO1 (b) Based on Table 1, carry out the quantities measurement for Maintaining and
C3 Handling Plant On Site, Supply Initial Pile and Supply Extension Pile.

Berpandukan Jadual A1, ukur kuantiti bagi Penyelenggaraan dan pengendalian


Jentera Di Tapak Bina, Pembekalan Cerucuk Permulaan dan Pembekalan
Cerucuk Sambungan.
[14 marks]
[14 markah]

(c) Conclude all the measured quantities in Question 1 (b), as the bill of quantities.
CLO1
C4
Rumuskan semua kuantiti terukur dalam Soalan 1(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]

QUESTION 2
SOALAN 2

CLO1 (a) Based on the Drawing No. DCQ5083/SERVICES/01-05, identify the builder
work in connection with sanitary fittings.
C2
Berpandukan Lukisan No. DCQ5083/SERVICES/01-05, kenalpasti kerja-kerja
pembina yang berkaitan dengan kerja lekapan kebersihan.
[3 Marks]
[3 markah]

CLO1 (b) Based on the Drawing No. DCQ5083/SERVICES/01-05, carry out the quantities
C3 measurement for sanitary fittings in Bath 2 ONLY.

Berpandukan Lukisan No. DCQ5083/SERVICES/01-05, sediakan pengukuran


kuantiti bagi lekapan sanitari dalam Bilik Air 2 SAHAJA.
[14 marks]
[14 markah ]

4 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

CLO1 (c) Conclude all the measured quantities in Question 2(b) as the bill of quantities.

C4
Rumuskan semua kuantiti terukur dalam Soalan 2(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]

5 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

SECTION B : 50 MARKS
BAHAGIAN B: 50 MARKAH

INSTRUCTION:
This section consists of FOUR (4) essay questions. Answer TWO (2) questions only.

ARAHAN:
Bahagian ini mengandungi EMPAT (4) soalan esei. Jawab DUA (2) soalan sahaja.

QUESTION 1
SOALAN 1

CLO1 (a) Identify the usage of soil, waste and vent pipe.
C2

Kenalpasti kegunaan paip najis, buang dan pengudaraan.


[3 marks]
[3 markah]

CLO1 (b) Based on the Drawing No. DCQ5083/SERVICES/01-05 carry out the quantities
C3 measurement for excavation works and piping woks for soil pipe ONLY.

Berpandukan Lukisan No. DCQ5083/SERVICES/01-05, ukur kuantiti bagi item


pengorekkan dan kerja perpaipan untuk paip najis SAHAJA.
[14 marks]
[14 markah]

(c) Conclude all the measured quantities in Question 1 (b) as the bill of quantities.
CLO1
C4
Rumuskan semua kuantiti terukur dalam Soalan 1(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]

6 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

QUESTION 2
SOALAN 2

CLO 1 (a) Differentiate between one way and two way switch.
C2

Berikan perbezaan antara suis satu dan dua hala.


[3 marks]
[3 markah]

CLO1 (b) Based on the Drawing No. DCQ5083/SERVICES/01-05, carry out the quantities
C3 measurement for switch and power plug.

Berpandukan Lukisan No. DCQ5083/SERVICES/01-05, ukur kuantiti bagi suis


dan palam kuasa .
[14 marks]
[14 markah]

(c) Conclude all the measured quantities in Question 2(b) as the bill of quantities.
CLO1
C4
Rumuskan semua kuantiti terukur dalam Soalan 2(b) sebagai senarai kuantiti.
[8 Marks]
[8 markah]

QUESTION 3
SOALAN 3

CLO1 (a) Based on SMM2, identify TWO (2) clauses of sheet pile measured in m2.
C2
Berdasarkan SMM2, kenalpasti DUA (2) klausa berkenaan cerucuk kepingan
yang diukur dalam m2.
[3 marks]
[3 markah]

7 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

(b) Based on the Drawing No. DCQ5083/SHEETPILE/01, carry out the quantities
CLO1
C3 measurement for item measured in m2 ONLY.

Berdasarkan Lukisan No. DCQ5083/SHEETPILE/01, ukur kuantiti bagi item


yang diukur dalam m2 SAHAJA.
[14marks]
[14 markah]

CLO1 (c) Conclude all the measured quantities in Question 3(b) as the bill of quantities.
C4

Rumuskan semua kuantiti terukur dalam Soalan 3(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]

QUESTION 4
SOALAN 4

CLO1 (a) Referring to the SMM2, identify and explain the clause related to the excavation
C2 of plumbing works.

Merujuk SMM2, kenalpasti dan terangkan fasal berkaitan penggalian terhadap


kerja- kerja perpaipan.
[3 marks]
[3 markah]

(b) Based on the Drawing No. DCQ5083/ SERVICES/01- 05, carry out the
CLO1
C3 quantities measurement for plumbing work from water tank to Bath 1 ONLY.

Berpandukan Lukisan No. DCQ5083/SERVICES/01-05, ukur kuantiti bagi kerja


perpaipan dari tangki air ke Bilik Air 1 SAHAJA.

[14 marks]
[14 markah]

8 SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4

CLO1 (c) Conclude all the measured quantities in Question 4(b) as the bill of quantities.
C4

Rumuskan semua kuantiti terukur dalam Soalan 4(b) sebagai senarai kuantiti.

[8 marks]