You are on page 1of 14

10/23/2021

Project Management:
A Systems Approach to
Planning, Scheduling, and Controlling
Twelfth Edition

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Chapter Twelve
Network Scheduling
Techniques

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

1
10/23/2021

Learning Outcomes
After careful studying this chapter You should be able to:
 Identify the three types of scheduling techniques and their
respective and advantages & disadvantages
 Differentiate between activity-on-arrow and activity-on-node
networks
 Describe the four types of precedence networks
 Define basic network terminology such as activities, events,
critical path, and slack (float)
 Differentiate between positive and negative slack
 Describe the schedule compression techniques and crashing
and fast-tracking (concurrent engineering)
 Explain the importance of the work breakdown structure in
network development

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Learning Outcomes (cont.)


• Discuss the steps, and their order, for the development of a
network
• Distinguish between the types of dependencies
• Perform a forward and backward pass
• Explain what is resources leveling resource-limited planning
• Differentiate between effort and duration which network
technique uses optimistic, most likely, and pessimistic estimates
and the use of dummy activities
• Lag
• Compare between unlimited versus limited resource
planning/scheduling

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

2
10/23/2021

Scheduling Techniques
• Gantt or bar charts
• Milestone charts
• Line of balance
• Networks
 Program evaluation and review technique (PERT)
 Arrow diagram method (ADM) [Sometimes called
the critical path method (CPM)]
 Graphical evaluation and review technique (GERT)
 Precedence diagram method (PDM)
Excerpted from Project Management 12E
by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Bar (Gantt) Chart


MONTHS AFTER GO-AHEAD
TASKS 1 2 3 4 5

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

3
10/23/2021

Milestone Chart

ACTIVITY
TESTING
ANALYSIS
REPORT
PRESENTATION
TIME

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Standard PERT Nomenclature

3 WEEKS
6 3

COMPLETE TESTING COMPLETE FINAL REPORT


LEGEND

EVENT

ACTIVITY

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

4
10/23/2021

Dependencies
31 31

26 18 18 26

7 7

BURST POINT SINK

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Conversion from Bar to PERT


1 2

BAR CHART 3 4 5

6 7

TIME
3 2
1 2
1 2
PERT CHART 3 2 4 2 5
1
1 4
6 7
Excerpted from Project Management 12E
by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

5
10/23/2021

Simplified PERT Network


3
1 2 5 6 7 8 9
4

LEGEND: (TIME = WEEKS)


EVENT
ACTIVITY
CRITICAL PATH ACTIVITY

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Dummy Activities
D

A PRECEDING
ACTIVITY ACTIVITY
DUMMY A -
B -
C B
B D A, B
C

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

6
10/23/2021

Slack Identification

ACTIVITY EARLIEST START TIME

EARLIEST FINISH TIME

C (8,10)
2 (15,17)

LATEST FINISH TIME


TIME
LATEST START TIME

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Types of Slack

[ 20, 26 ] [ 30, 36 ]
[ 24, 30 ] [ 24, 30 ]

POSITIVE SLACK NEGATIVE SLACK

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

7
10/23/2021

Negative Slack
FORWARD PASS

3 4

BACKWARD PASS

1 2
CUSTOMER’S CUSTOMER’S
START DATE FINISH DATE

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Schedule Compression
• Elimination of some parts of the project
• Addition of more resources
• Substitution of less time-consuming
components or activities
• Parallelization of activities
• Shortening critical path activities
• Shortening early activities
• Shortening longest activities
Excerpted from Project Management 12E
by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

8
10/23/2021

Schedule Compression
(Continued)

• Shortening easiest activities


• Shortening activities that are least costly
to speed up
• Shortening activities for which you have
more resources
• Increasing the number of work hours per
day
Excerpted from Project Management 12E
by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Resource Leveling
Resource leveling is an attempt to eliminate
the manpower peaks and valleys by
smoothing out the period-to-period resource
requirements. The ideal situation is to do
this without changing the end date.
However, in reality, the end date moves out
and additional costs are incurred.

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

9
10/23/2021

Resource Allocation
Resource allocation (or resource limited
planning) is an attempt to find the shortest
possible critical path based upon the
available or fixed resources. The problem
with this approach is that the employees may
not be qualified technically to perform work
on more than one activity in a network.

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Planning Objectives (Primary)

• Best time
• Least cost
• Least risk

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

10
10/23/2021

Planning Objectives (Secondary)

• Studying alternatives
• Optimum schedules
• Effective use of resources
• Communications
• Refinement of the estimating process
• Ease of project control
• Ease of time or cost revisions

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Planning Objectives (Limitations)

• Calendar completion
• Cash or cash flow restrictions
• Limited resources
• Management approvals

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

11
10/23/2021

Program Crashing Costs


ALL ACTIVITIES CRASHED

MINIMUM COST
160,000 TOTAL CRASH CRASH B
PROGRAM COST, $

150,000
CRASH E
140,000 CRASH F
130,000 CRASH A
NORMAL OPERATIONS
120,000
110,000
10 12 14 16 18 20 22 24
PROGRAM COMPLETION TIME, WEEKS

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Precedence Network
MONTHS AFTER GO-AHEAD
TASKS 1 2 3 4 5

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

12
10/23/2021

Types of Precedence Charts

FINISH START
FINISH-TO-START ACTIVITY 1 ACTIVITY 2

START
START-TO-START ACTIVITY 1
START

ACTIVITY 2

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Types of Precedence Charts


FINISH
FINISH
FINISH-TO-FINISH ACTIVITY 1

ACTIVITY 2
PERCENT COMPLETE

ACTIVITY 1
50 %

20 %
ACTIVITY 2

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

13
10/23/2021

Activity Information

EARLY START TIME DURATION EARLY FINISH


01/06/17 2 WORK-WEEKS 14/06/17

TOTAL
SLACK (TS)
ACTIVITY 4 $250,000
FREE SLACK
(FS)

LATE START COST/PROFIT LATE FINISH


15/06/17 CENTER 2810 28/06/17

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

Schedule Compression Myths


Compression Myth Reality
Technique
Use of overtime Work will progress at the same The rate of progress is less on overtime, more mistakes
rate on overtime. may occur, and prolonged overtime may lead to
burnout.

Adding more The performance rate will It takes time to find the resources; it takes time to get
resources (i.e., increase due to the added them up to speed; the resources used for the training
crashing) resources. must come from the existing resources.

Reducing scope (i.e., The customer always requests The customer needs all of the tasks agreed to in the
needed, reducing more work than actually statement of work.
functionality) needed.
Outsourcing Numerous qualified suppliers The quality of the suppliers’ work can damage your
exist. reputation; the supplier may go out of business; and
the supplier may have limited concern for your
scheduled dates.
Doing series work in An activity can start before the The risks increase and rework becomes expensive
parallel previous activity has finished. because it may involve multiple activities.

Excerpted from Project Management 12E


by Harold Kerzner. Copyright 2017 by
John Wiley & Sons, Inc. All rights reserved.

14

You might also like