Professional Documents
Culture Documents
CONTRACT MANAGEMENT
RSDP
More Than 1000
(1997-
Health Center
2010)
450,000 Condominium
Houses within 5 Years in AA
Good Road Condition imroved
from 22% to 54%
1. Description of the subject (Major Undertakings For The Last 25
YEARS)
04 Railway Planned
on GTP I
Part 1. Introduction
I Pre-Project Phase
2.
Planning and Design Phase
Contractor Selection
Project Mobilization
4 Tadesse A. Constructi
Training on Construction Project Management, Sep 2017,
1. Introduction
What is a project ?
1
What is project management?
Project manager
Areas of expertise
community etc
7 Training on Construction Project Management, Sep 2017, Tadesse A.
1. Introduction (Cont…)
1.2 What is project management
Project management is the application of
Balancing the competing demands for quality, scope, time and cost
understand and use knowledge and skills from at least five areas of
expertise:
The Project Management Body of Knowledge
Interpersonal skills.
Part 2.
I Constructio
n Project
16 2017, Tadesse A. Manageme
Training on Construction Project Management, Sep
Pre Project Phase
Planning
2.2 Design
Contract Document
1. Construction Documents
2.2.3
2. Bidding Requirements
3. Contract Documents
4. Bonds/Guarantee Forms
26
Training on Construction Project Management, Sep 2017, Tadesse A.
1. Construction Documents
27
Training on Construction Project Management, Sep 2017, Tadesse A.
2. Bidding Requirements
Standard Bidding Document
Donors’ Interest
Business Interest Professional Interest
29
Training on Construction Project Management, Sep 2017, Tadesse A.
2. Bidding Requirements
2.1 Bid Package
Bid Package: documents available to the contractor and
on which he must make a decision to bid or not.
A set of plans and technical specifications, proposal form,
general conditions, special conditions etc. that shows the
description of the project to be constructed
30
Training on Construction Project Management, Sep 2017, Tadesse A.
2. Bidding Requirements
2.2 Instruction to Bidders, ITB
It describe the scope of the bid and also include the
following points:
Source of fund (if it is financed from other agency);
Fraudulent and fraud practices;
Eligible bidders;
Eligible Materials, Equipment and Services;
Clarification of Bidding Document;
Site Visit;
Pre-Bid Meeting; and
Amendment of Bidding Document.
31
Training on Construction Project Management, Sep 2017, Tadesse A.
2. Bidding Requirements
2.3 Bid Data Sheet, BDS
The BDS include the following fundamental essence of
the contract:
Definitions, Engineer’s Authority to Issue Variations,
Performance Security, Inspection of Site, Program to
be Submitted, Cash Flow Estimate;
Bid Security, Minimum Amount of Third Party
Insurance;
Time for Issue of the Notice to Commence, Time for
Completion;
Amount of Liquidated Damages, Limit of Liquidated
Damages; and
Amount of Bonus for Early Completion, Limit of
Bonus.
32
Training on Construction Project Management, Sep 2017, Tadesse A.
2. Bidding Requirements
2.3 Bid Data Sheet, BDS
The BDS include the following fundamental essence of
the contract:
Defects Liability Period, Amount of Interim Payment
Certificates;
Percentage of Retention, Limit of Retention Money,
Amount of Advance Payment;
Start Repayment of Advance Payment, Monthly
Recovery of Advance Payment;
Number of Copies of Statement of Completion and
Final Statement;
Procedure for Settlement of Disputes;
Notice to Employer and Engineer; and
Origin of Materials and Plant.
33
Training on Construction Project Management, Sep 2017, Tadesse A.
2. Bidding Requirements
2.4 Evaluation and Qualification
Evaluation: describe the Adequacy of Technical Proposal, in
case of Multiple Contracts, the Conditions Governs, Completion
Time.
Qualification: describe the Eligibility, financial situation, staff,
experience , equipments.
2.5 Bidding Forms
It includes these forms:
Letter of bid (bid form);
Form of bid security;
Technical proposal forms (personnel, equipment);
Bidders qualification forms as bidders data, JV information,
Historical Contract Non-Performance, Current Contract
Commitments, Historical Financial Performance, Average
Annual Turnover, General and specific Experience.
34
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
Contract Documents (graphic and written) describe the
proposed construction (the ‘Work’) that results from
performing services, furnishing labor, and supplying and
incorporating materials and equipment into the construction.
It is legally enforceable requirements that become part of the
contract.
Include the following construction documents except
bidding forms:
Contract Agreement;
Conditions of Contract (General and Specific);
Specifications and Bill of Quantities (BOQ);
Drawings;
Addenda; and
Supplementary Contracts (Change Orders).
35
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.1 Contract Agreement
The agreement is the document that represents and
reflects the legal contract between the owner and the
contractor.
The purpose of the agreement is to record in written
form those items agreed between the owner and the
contractor.
It is simply a letter that constitutes legal evidence that a
contract exists, and forms the basis for its enforcement.
The Contract Agreement shall also declare the priority of
the Contract Documents i.e. which Contract Document
shall have precedence or priority over the other in case of
ambiguity or discrepancy between or among the relevant
parts of the Contract Documents.
36
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.1 Contract Agreement
The agreement should contain:
The date of agreement;
The names and address of contracting parties;
A brief description of the scope of work;
A list of contract documents with their precedence
(reference to other documents);
The procedures for payment;
The contract time, or dates for start and completion;
The signatures of contracting parties and witnesses;
International construction documents are also often based
on industry-prepared standard forms.
37
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.1 General
Conditions of Contract is the main component of a contract
which outlines the guidelines and relationships of parties to
successfully manage the project.
Standard forms of contract developed for construction activities
have mostly been drawn up by independent professional
organizations, rather than by one of the parties to the contract,
in order to establish or to consolidate a fair and just contract.
Purpose of Conditions of contract include:
Balanced representation of all relevant industry
participants;
Fair allocation of risk;
Manage and mitigate project risks; and
Facilitate a greater sense of partnership.
38
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.1 General
The condition of contract is a document that states the
obligations and rights of the parties and detail conditions
under which the contract is to be carried out.
Some of the subjects to be defined in the conditions of
contract are:
Definitions & interpretations;
Duty & responsibilities of the engineers;
Contract period;
Method of payment and periods;
Retention money;
Payment for materials on site; and
Payment for variation orders.
39
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.1 General
Some of the subjects to be defined in the conditions of
contract are:
Escalation (wages, cost of materials);
Procedures on sub contracting;
Insurance & indemnities;
Liquidated damages;
Granting of extension time; and
Conditions for contract termination.
40
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.1 General
A. General Conditions of Contract, GCC
A document called the General Conditions is an essential
part of the contract. It defines the responsibilities of the
parties involved in the contract, the owner and the
general contractor. It describes the guidelines that will be
used in the administration of the contract.
The conditions are intended to govern and regulate the
obligation of formal contract.
Various standard forms of General Conditions have been
developed by different organizations such as FIDIC, ICE,
JCT, BaTCoDA, MoWUD and PPA etc.
41
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.1 General
B. Special Conditions of Contract, SCC
The purpose of the Special Conditions is to provide an
extension of the General Provisions of the contract to fit
the specific project at hand.
It is also known as Conditions of Particular Application,
CPA.
They serve as amendments or augmentation to the
General Conditions.
Items included in the Supplementary Conditions are
entirely subject to the discretion of the owner.
42
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.1 General
B. Special Conditions of Contract, SCC
Special conditions of contract may include topics such as:
The number of copies of contract documents to be
received by the contractor;
Survey information to be provided by the owner;
Materials provided by the owner;
Changes in insurance requirements;
Requirements for security and temporary facilities;
Procedures for submittal and processing of shop
drawings;
Cost and schedule reporting requirements; and
Traffic control and street cleaning requirements.
43
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.1 General
C. Categories of Contract Forms
Conditions of contract can be international or domestic.
International Contract forms:
o ICE contract forms;
o NEC contract forms;
o JCT contract forms; and
o FIDIC contract forms.
Domestic contract forms:
o BaTCoDA 1987 contract forms;
o MoWUD 1994 contract forms;
o PPA 2006 contract forms; and
o PPPAA 2011 contract forms.
44
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.2 FIDIC Contract Forms
The Fédération Internationale des Ingénieurs-Conseils,
FIDIC (International Federation of National Associations
of Independent Consulting Engineers) organization was
founded in 1913 by France, Belgium and Switzerland.
Now with membership from over 74 countries, members
are generally national associations with the Ethiopian
Consulting Engineering and Architects Association being
one.
FIDIC has evolved into a leading body for development
of model standard forms of contract for use in the
international construction industry.
45
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.2 FIDIC Contract Forms
The following editions are relevant with respect to
international construction contract ( Red Book)
First Edition August, 1957;
Second Edition July, 1969;
Third Edition March, 1977;
Fourth Edition September, 1987;
Fourth Edition (a supplement) Summer 1992 ; (NB:
Amendments with regard to some of the Provisions of
the Conditions of Contract); and
Fourth Edition (further amendment) November, 1996
(NB: in relation to Dispute Adjudication Board,
Payment on Lump Sum Basis and Late Certification.)
46
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.2 FIDIC Contract Forms
Recently (1999 & 2006) FIDIC has published the following
conditions of contract. These are:
Conditions of Contract for Construction for Building and Engineering
Works Designed by the Employer: The Construction Contract (New
Red Book);
Conditions of Contract for Plant and Design-Build for Electrical and
Mechanical Plant, and for Building and Engineering Works, Designed
by the Contractor: The Plant and Design/Build Contract (New Yellow
Book);
Conditions of Contract for EPC/Turnkey Projects: The EPC/Turnkey
Contract: (Silver Book); and
Short form of Contract: The Short Form (Green Book).
Conditions of Contract for Construction: For Building and
Engineering Works Designed by the Employer: Multilateral
Development Bank (MDB) Harmonized Edition, March, 2006,
FIDIC;
47
Training on Construction Project Management, Sep 2017, Tadesse A.
48 Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.3 MoWUD Contract Forms
Officially, known as “Standard Conditions of Contract for
Construction of Civil Work Projects”.
It has been in practice since December, 1994.
It contains 75 clauses including Form of Agreement & Form
of Performance Bond.
Its structure & content resembles that of FIDIC fourth
edition Standard Conditions of Contract for Civil
Engineering Works.
The Project Delivery System adopted is that of Design-Bid-
Build.
The type of contract is based on BOQ i.e. it is an ad
measurement contract type (see Clauses 55-57).
The role of the Engineer is maintained.
49
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.4 PPA/PPPAA Contract Forms
The PPA, under its legal mandate provided under The
Public Procurement Proclamation, it has prepared &
issued certain standard tender & contract documents for
the purpose of public procurement.
The conditions of contract are applicable to the
procurements of the federal government.
It has been in practice since January 2006.
It recently revised by PPPAA since August 2011.
50
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.4 PPA/PPPAA Contract Forms
The Standard Conditions of Contract cover the following
types of procurement.
These are Standard Conditions of Contract for the
procurement of:-
Consultancy Services;
Non-consultancy Services;
Works; and
Goods; Including Simple Request for Quotations &
Local Purchase Order;
51
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.4 PPA/PPPAA Contract Forms
The Standard Conditions of Contract for the purpose of
the procurement of Works have been prepared for
International Competitive Bidding (ICB) & National
Competitive Bidding (NCB), separately.
User’s Guide has been also prepared, separately, both for
the ICB & the NCB.
The Conditions of Contract have been also prepared
both in Amharic & English languages.
The conditions of contract are based on Design-Bid-
Build project delivery system.
52
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.2 Standard Conditions of Contract
3.2.4 PPA/PPPAA Contract Forms
The type of contract could be based on BOQ, in which
case it becomes measurement based. Or based on
Activities Schedule, in which case it becomes lump sum.
The documentation is divided in to the following three
parts, namely,
Bidding Procedure;
Schedule of Requirements; and
Contract.
53
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.3 Specifications
Specification is a written standard to be used in
conjunction with the drawings, so together with
drawings and the specifications fully describe and define
the requirements of the contract, to include the quality
that is to be achieved.
Specification may also be know as Technical Provisions.
They supplement the drawings and provide information
that cannot be shown in graphic form, or information
that is too lengthy to be placed within the drawings.
They guide bidders in the preparation of cost proposals
as well as field execution of the work.
They also guide the contractor through the processes of
ordering materials and construction and installation of
the facility.
54
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.3 Specifications
It helps as a standard assuring the critical performance
and other requirements for the works.
It is advisable to use Ethiopian standards (ES) and
technical specifications (BaTCoDA 1991) for the works;
however, if they are inappropriate for the specific work,
internationally accepted standards and specifications such
as those issued by ISO can be specified.
Specifications provide information regarding:
The quality of materials;
The quality of workmanship;
Erection and installation methods; and
Measurement, test and inspection requirements and
methods.
55
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.3 Specifications
Specifications have restricted application, usually to a
specific item or work operation. The designer or
specification writer is therefore able to assign
responsibility for each provision of the specifications to
the desired specific party.
Specifications must satisfy these basic criteria:
Technical accuracy and adequacy;
Definite and clear stipulations;
Fair and equitable requirements;
A format that is easy to use during bidding and
construction; and
Legal enforceability.
56
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.4 Drawings
Drawings are the means by which the designer conveys
the physical, quantitative, and visual description of the
project (physical structure) to the contractor.
They are also known as plans or blueprints.
The contract drawings are organized into sections
numbered sequentially. Drawings for a building project
may include the following type:
Architectural drawings;
Structural drawings;
Sanitary drawings;
Electrical drawings; and
Mechanical drawings.
57
Training on Construction Project Management, Sep 2017, Tadesse A.
3. Contract Documents
3.5 Addenda
Any change to the bid documents after they are released
for bidding but before bids are actually received requires
the issuance of an addendum.
This formal document changes the original bid
documents and becomes a part of the bid package.
At the time of bid opening, bidders must in their bid
documents, acknowledge all addenda.
Technically addenda may be issued to change the bid
opening date, to modify the original design, to delete or
add items, or to correct errors.
Addenda may not be issued within about five days of bid
opening unless the bid date is also extended accordingly.
58
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.1 General
A bond or guarantee is an arrangement under which the
performance of a contractual duty owed by one person
(A) to another (B) is backed up by a third party (C).
What happens is that C promises to pay B a sum of
money if A fails to fulfill the relevant duty.
In this context A is commonly known as the principal
debtor or simply principal; B is called the beneficiary;
and C is called the bondsman, surety or guarantor.
59
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.2 Bid Bonds
Bid Bonds guarantee that the bidder will carry out the
terms of a contract at the bid price upon award of the bid.
Thus it is a guarantee that a contractor will enter into a
contract at the amount of bid and post the appropriate
performance bonds, providing financial assurance that the
bid has been submitted in good faith.
These bonds are used by owners to pre-qualify
contractors submitting proposals on contracts.
60
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.2 Bid Bonds
Bid Bonds guarantee that the bidder will carry out the
terms of a contract at the bid price upon award of the bid.
Thus it is a guarantee that a contractor will enter into a
contract at the amount of bid and post the appropriate
performance bonds, providing financial assurance that the
bid has been submitted in good faith.
These bonds are used by owners to pre-qualify
contractors submitting proposals on contracts.
61
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.2 Bid Bonds
Bid bonds have two purpose:
To guarantee that the contractor will enter into a
contract if determined to be the lowest responsive
bidder and
To guarantee the contractor will provide the required
payment and performance bonds, and insurance
policies.
When the performance and payment bonds have been
submitted, the contractor is released from the bid bond
obligations.
62
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.2 Bid Bonds
Bid Withdrawal
If a bid is withdrawn before the bid is opened, the bid
security shall be returned to the bidder. No action is taken
against the bidder or bid security if a bidder is permitted
to withdraw the bid before award.
Conversely, a successful bidder may not withdraw the bid
after bid opening without forfeiture of bid security, unless
the bidder can establish by clear and convincing evidence
that a non judgmental mistake was made in the bid.
If withdrawal of a bid after bid opening is permitting, no
action may be taken against the bidder or bid security.
63
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.3 Performance Bond
The Contractor, upon receiving the Letter of Acceptance,
shall obtain and provide to the Employer before signing the
Contract, the Performance Guarantee in the value of ten
percent of the Contract Sum, as a guarantee of the proper
execution of the Works in accordance with the Contract.
This guarantee shall be issued by a licensed bank or
financial institution acceptable to the Employer.
The obtaining of such guarantee shall in all respects be at
the expense of the Contractor.
The Performance Security shall be valid until a date 28
days from the date of issue of the Certificate of Completion
in the case of a Bank Guarantee, and until one year from
the date of issue of the Completion Certificate in the case of
a Performance Bond.
64
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.3 Performance Bonds
Performance bonds guarantee the performance of the
contract requirements at that stated bid price. In effect,
the surety is saying it guarantees the performance of the
contractor, or it will complete the project as described in
the plans and specifications.
Performance Bonds guarantee the contractor will
faithfully perform the contract or the terms of the
contract.
This protects the owner from financial loss should the
contractor fail to perform the contract in accordance with
its terms and conditions.
Performance bonds frequently incorporate payment bond
(labor and materials) and maintenance bond liability.
65
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.3 Performance Bonds
While a bid bond is submitted with the bid, a
performance bond is submitted by the winning bidder
upon award of the contract.
The surety is in the position of being asked to guarantee
the contractor’s performance.
Therefore, the contactor must demonstrate an ability to
perform before the surety is willing to issue payment and
performance bonds.
The sureties will visit the contractor’s home office and
job sites, and will contact the owners of recently
completed contracts.
66
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.3 Performance Bonds
If a contractor defaults on performance of the contract,
the surety has three basic choices:
Buy back the bond. This amounts to giving the
owner a check for the amount of the penal value of
the bonds.
Replace the contractor. Negotiate or advertise for
bids for the purpose of obtaining another contractor
to finish the work.
Finance the contractor. The bonding company runs
the risk of spending more than the value of the bond,
but this is still a common option because the
contactor is familiar with the project.
Today most sureties try to replace the contractor.
67
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.4 Payment Bonds
Payment Bonds ensure subcontractors, laborers and
material suppliers used in fulfilling a contract will be
paid.
A payment bond is a contract bond that guarantees
payment of the contractor's obligation under the contract
for subcontractors, laborers and material suppliers
associated with the project, providing assurance that they
will be paid if the contractor defaults.
The payment bond is a protection for those supplying
labor or materials to a public job.
In most cases, payment bonds and performance bonds
are issued together as one bond; the same application
covers both.
68
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.4 Advance Payment Bond
These are bonds or guarantees given to the owner by the
contractor assuring the owner that the contractor will pay
back any advance payment that he has received.
The Employer shall make advance payment to the
Contractor of the amounts stated in the PCC by the date
stated in the PCC, against provision by the Contractor of
an Unconditional Bank Guarantee in a form and by a
bank acceptable to the Employer in amounts and
currencies equal to the advance payment.
The Guarantee shall remain effective until the advance
payment has been repaid, but the amount of the
Guarantee shall be progressively reduced by the amounts
repaid by the Contractor.
Interest shall not be charged on the advance payment.
69
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.4 Advance Payment Bond
The Contractor is to use the advance payment only to pay
for Equipment, Plant, Materials, and mobilization
expenses required specifically for execution of the
Contract. The Contractor shall demonstrate that advance
payment has been used in this way by supplying copies of
invoices or other documents to the Project Manager.
The advance payment shall be repaid by deducting
proportionate amounts from payments otherwise due to
the Contractor, following the schedule of completed
percentages of the Works on a payment basis. No
account shall be taken of the advance payment or its
repayment in assessing valuations of work done,
Variations, price adjustments, Compensation Events,
Bonuses, or Liquidated Damages.
70
Training on Construction Project Management, Sep 2017, Tadesse A.
4. Bond/Guarantee Forms
4.5 Defects Liability Security
After primary taking over, 5% guarantee is submitted to
employer for defect liability, valid for 365 days or as
stipulated in PCC.
4.6 Insurance Certificates
Insurance for Works and Contractor’s Equipment,
Insurance against Injury to Persons and Damage to
Property ,
Insurance for Contractor’s Personnel.
71
Training on Construction Project Management, Sep 2017, Tadesse A.
2.3 Contractor Selection
Pre/Post Qualification
74
2.3.2 Evaluation Criteria
To qualify for award of the Contract, in accordance with ITB Sub-
75
2.4 Project Mobilization Phase
Legal and
2.4 contractual
Project
organization
issues
and start up
Property insurance,
Liability insurance,
Employee insurance and other types.
constructed
2.4.2 Project organization and start up ( Cont…)
The PM at this stage shall study, identify and decide on availability of various
resources in the vicinity of the project site & determine which resources and
amount will be mobilized
2.4.2 Project organization and start up ( Cont…)
8. Site Establishment
Resources mobilization
communication
Accommodation of labor and staffs
Contract Administration
Resources Management
85
Training on Construction Contract Management, Sep 2017, Tadesse A.
Basic Principles of a Contract
87
Training on Construction Contract Management, Sep 2017, Tadesse A
0. Principles of Contract
0.1 Contract: Definition
The earliest recorded reference to a building contract
comes from one of the laws of Hammurabi, the
Babylonian conqueror:
“If a contractor builds a house for a man this man shall
give the contractor two shekels of silver as recompense.
If a contractor builds a house and does not build it
strong enough and it collapses and kills the owner the
contractor shall be put to death.”
88
Training on Construction Contract Management, Sep 2017, Tadesse A
0. Principles of Contract
0.1 Contract: Definition
According to Art. 1675 of the 1960 Civil Code of Ethiopia:
“A contract is an agreement whereby two or more persons
as between themselves create, vary or extinguish
obligations of a proprietary nature.”
The definition encompass the following main points:
The contract is an agreement;
The agreement is to be made between two or more
persons;
The agreement is binding between such two or more
persons;
The agreement is to create, vary and extinguish
obligations;
The nature of obligations is proprietary.
89
Training on Construction Contract Management, Sep 2017, Tadesse A
0. Principles of Contract
0.2 Elements of Contract
According to Art. 1678 of the Civil Code, no valid
contract shall exist unless:
The parties are capable of contracting and give their
consent sustainable at law.
The object of the contract is sufficiently defined and
is possible and lawful.
The contract is made in the form prescribed by law.
The following are the fundamental elements of contract.
Capacity of the contracting parties;
Consent of the contracting parties;
Object of the contract; and
Form of contract, if any.
90
Training on Construction Contract Management, Sep 2017, Tadesse A
0. Principles of Contract
0.3 Effects of Contract
91
Training on Construction Contract Management, Sep 2017, Tadesse A
0. Principles of Contract
0.4 Purpose of Construction Contracts
The fundamental purpose of construction contract is to:
Describe scope of work;
Establish time frame;
Establish cost and payment provisions;
Establish commercial terms and conditions;
Set obligations, remedial rights and relationships;
Manage multiple risks;
Balance risk;
Set project execution plan;
Establish control mechanisms;
Minimize disputes; and
Improves economic return of investment.
92
Training on Construction Contract Management, Sep 2017, Tadesse A
Contract Administration
96
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.2 Variation: Definition
“Variation work is the work that can be imposed with in
the contract documents. It is a change or alteration to
the plans or specifications for a number of reasons
implicit in the original agreement, these reasons could
include, but are not limited to, omissions in the design
documents, recognition of better methods or materials to
achieve the required effect, resolution of problems
recognized, resolution of unforeseen conditions not
anticipated, and similar adjustments with in the intent of
the original contract.”
97
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.3 Types of Changes
There are several types of changes in the construction
work process. Changes can be classified into:
Formal Changes;
Constructive Changes;
Cardinal changes;
Design Related Changes; and
Payment changes.
98
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.3 Types of Changes
Formal Changes: Formal changes are change order
which is directed by the owner or owner’s representative.
Constructive Changes: is a type of change that lacks the
formal directive authorizing a change in work.
Cardinal Changes: is as intensive as it changes the entire
character of the work required under the contract.
Design Related Changes: Design error can be considered
as a change to the construction Contract.
Payment Changes: Disputes arise when one party fails to
pay the other.
99
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
With respect to causes that lead to changes, changes can
be divided into two categories:
Technical Changes; and
Administrative Changes.
With respect to their originators changes can be
categorized:
Owner related changes;
Design Consultant related changes;
Contractor related changes; and
Other changes.
100
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
2.4.1 Technical Changes
In the category of technical changes, there are four types
of causes namely
Planning and design;
Underground conditions;
Safety considerations; and
Natural incidents.
101
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
2.4.2 Administrative Changes
The category of administrative changes consists of:
Changes of work rules/regulations: The work rules or
regulations enforced during the initial period of planning and
design may be revised by the governing agency latter in the
construction stage.
Changes of decision making authority: Project risks incurred
by the change of decision making authority are external and
beyond the control of both the client and the contractor.
Special needs for project commissioning and ownership
transfer: the user party, during the course of commissioning,
may raise request to modify its requirements for the built
facility.
Neighborhood pleading: Usually neighborhood concerns are
considered in the stage of planning and design.
102
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
2.4.3 Causes of variation with respect to their originator
A. Owner related changes
1. Change of plans or scope by owner.
2. Change of schedule by owner.
3. Owner's financial problems.
4. Replacement of materials or procedures.
5. Change in specifications by owner.
B. Contractor related changes
1. Unavailability of equipment.
2. Differing site conditions.
3. Defective workmanship.
4. Unfamiliarity with local conditions.
5. Contractor's lack of required data.
103
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
2.4.3 Causes of variation with respect to their originator
C. Design Consultant related changes
1. Change in design by consultant.
2. Errors and omissions in design.
3. Conflicts between contract documents.
4. Inadequate working drawing details.
5. Noncompliance design with government regulations.
6. Noncompliance design with owner's requirement.
7. Change in specifications by consultant.
104
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
2.4.3 Causes of variation with respect to their originator
D. Other changes
1. Weather conditions.
2. Safety considerations.
3. Change in government regulations.
4. Change in economic conditions.
5. Socio-cultural factors.
6. Unforeseen problems.
105
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
2.4.4 Effects of Variation
Variation order impact on the project cost and/or progress
varies with the following:
The larger the scope (measured by the cost), the
greater the impact.
The later in time the change order is implemented,
the greater the impact.
The better the management of the change order
process, the less the impact.
There are many effects of variation order to either parties
of the construction project. Some well known ones
include: Delay, Cost overrun, Claim and Dispute .
106
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Variation
2.4 Causes of Changes
2.4.5 Variation Provisions
Variation is the addition, omission or alteration of works in terms
of quality, form and function necessary to complete the works
contained in the main contract.
Construction contracts provision for variation.
Variations: Sub-Clause 51.1 (MoWUD 1994, FIDIC IV); Sub-
clause 13.1 and 13.3 (FIDIC 1999, 2006 MDB);
Engineer’s power to order variation: Sub-clause 51.2 (MoWUD
1994, FIDIC IV);
Valuation of variation: Sub-clause 52.1 (MoWUD 1994, FIDIC IV)
Engineer’s power to fix rates: Sub-clause 52.2 (MoWUD 1994,
FIDIC IV); and
Variation exceeding 10% (15%): Sub-clause 52.3 (MoWUD 1994,
FIDIC IV).
107
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Powers & Responsibilities of the Engineer
The Engineer, not a party to the contract between the
employer and the contractor, is in fact empowered under
various clauses of the MoWUD 1994, PPA 2006, FIDIC
4th edition and FIDIC1999, 2006 MDB conditions of
contract.
These powers include to:
Give instructions;
Make decisions and/or determinations; and
Order variations, etc.
The above decisions are binding on the parties to the
contract unless and until they are subsequently or varied
by DRB, ADR or an arbitrator.
108
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Powers & Responsibilities of the Engineer
The engineer is considered as:
109
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Delays & Time Extension
4.1 Delays
Delay caused by employer
If the employer delayed in site handover/possession (MoWUD
1994 Sub-clause 42.1; FIDIC IV clause 42.2; and FIDIC 1999,
2006 MDB sub-clause 2.1) and to effect payment (MoWUD
1994 and FIDIC IV Clause 60).
If the Engineer failed to give instruction and notice on time, do
not provide drawings on time, etc.
Remedial right of the contractor
Financial claim; and
Time extension.
Delay caused by contractor
Delay of progress of works and failure to meet completion time.
Remedial right of the Employer
Liquidated damage.
110
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Delays & Time Extension
4.2 Grounds for Extension of Time according to FIDIC
The following factors are the major grounds for Extension
of Time.
Opening up and inspection of defective work;
Delay in the supply of information;
Delay on the part of nominated sub-contractors/
suppliers;
The execution of work not forming part of the contract;
The supply of materials by the employer;
The exercise by the government of any power which
directly affects the works;
Carrying out of work by statutory power; and
Failure by the employer to give access over employer’s
land.
111
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Delays & Time Extension
4.2 Grounds for Extension of Time according to FIDIC
The following factors are the major grounds for Extension
of Time (FIDIC 1999, 2006 MDB).
Clause 8.4(a) due to Variation;
Clause 8.4(b) see below in conjunction with other
relevant Sub-clauses;
Clause 8.4 (c) due to exceptionally adverse climatic
conditions;
Clause 8.4 (d) due to unforeseeable shortages in the
availability of personnel, or Goods caused by
epidemic or governmental action;
Clause 8.4(e) due to any delay, impediment or
prevention caused by or attributable to the Employer,
the Employer’s personnel (including the Engineer see
Clause 1.1.2.6) or the Employer’s other contractors;
112
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Delays & Time Extension
4.2 Grounds for Extension of Time according to FIDIC
The following factors are the major grounds for Extension of
Time (FIDIC 1999, 2006 MDB).
Clause 8.4(b)cum Clause 1.9(a) due to delay in issuing
drawing & instructions by the Engineer to the Contractor;
Clause 8.4(b) cum Clause 2.1(a) due to delay in providing
access to the Site by the Employer;
Clause 8.4(b) Clause 4.7(a) due to delay caused due to
error in Setting out;
Clause 8.4(b) cum Clause 4.12(a) delay due to
unforeseeable physical conditions;
Clause 8.4(b)cum Clause 4.24(a) delay caused due to
discovery & reporting of Fossils;
Clause 8.4(b)cum Clause 7.4(a) delay caused by the
Employer in relation to Testing;
113
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Delays & Time Extension
4.2 Grounds for Extension of Time according to FIDIC
The following factors are the major grounds for
Extension of Time (FIDIC 1999, 2006 MDB).
Clause 8.4(b)cum Clause 8.8 delay caused by
suspension as ordered by the Engineer;
Clause 8.4(b)cum Clause 8.11 delay caused due to
prolonged suspension provided the Contractor opted
for resuming the performance of the Works after
such prolonged suspension;
Clause 8.4(b)cum Clause 16.1(h) delay caused to the
Contractor due to suspension or reduction in the
progress of the Works by the Contractor due to delay
in payment;
114
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
115
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
5.1 Contract Price
The contract price is dealt with in different ways by
different contracts.
If the contract is ad-measurement, the bid by the
contractor is based upon the work described and
quantified in the contract bills.
If any quantities are altered because of variations in the
client’s requirements, then the contract sum will be
altered. Otherwise, the contractor is paid the amount of
the tender.
116
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
5.2 Time of Payment
It is common practice in the construction industry, for
payment of the contract sum to be made by installments.
This is because the total value of each contract forms a
large proportion of a contractor’s annual turnover.
Payment by installments should eliminate the need for
the contractor to borrow money pending final payment.
The time of payment should be as clearly depicted in the
contract document.
117
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
5.3 Payment Obligation according to FIDIC
5.3.1 Payment of the contract price
Clause 14.2 cum Clause 14.7(a) in relation to Advance
Payment.
Clause 14.7(b) in relation to Interim Payment.
Clause 14.13 cum Clause 14.7(c) in relation to Final
Payment.
Clause 14.9 in relation to the first half of the Retention
Money.
Clause 14.9 in relation to the second half of the
Retention Money.
118
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
5.3 Payment Obligation according to FIDIC
5.3.2 Other Payment Obligations (relative to claims or
other wise)
Clause 1.9(b) payment of cost & profit due to delay in
issuing drawings & instructions by the Engineer;
Clause 2.1(b) payment of cost & profit due to delay
caused in providing access to the Site;
Clause 4.7 payment of cost & profit due to error in
Setting out;
Clause 4.12(b) payment of cost due to delay caused by
unforeseeable physical conditions;
Clause 4.24(b) payment of cost in case of discovery &
reporting of Fossils;
119
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
5.3 Payment Obligation according to FIDIC
5.3.2 Other Payment Obligations (relative to claims or
other wise)
Clause 7.4(b) payment of cost in case of Testing for
which the Employer is responsible;
Clause 8.9(b) payment of cost in case of suspension of
Works;
Clause 10.3(b) payment of cost & profit in case of
interference with Tests on Completion;
Clause 11.6 payment of cost in case of further tests for
which the Employer is responsible;
Clause 13.7 cum 14.3(b) payment of cost in case of
Adjustment for Changes in Legislation;
120
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
5.3 Payment Obligation according to FIDIC
5.3.2 Other Payment Obligations (relative to claims or
other wise)
Clause 13.8 payment of cost in case of Adjustment for
Changes in Cost.
Clause 14.3(a) cum Clause 13.2 payment of additional
payment to the Contractor derived from savings due to
the effects of Value Engineering.
Clause 14.8 payment of financing charges in case of
delay in payment.
Clause 15.4( c ) entitlement to a balance of costs, if any,
in case of termination of the Contract by the Employer
due to the default of the Contractor, after completion of
the Works by the Employer or another contractor;
121
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Payment
5.3 Payment Obligation according to FIDIC
5.3.2 Other Payment Obligations (relative to claims or other
wise)
Clause 16.1(b) payment of cost & profit in case of
suspension & reduction of the progress of the Works by the
Contractor;
Clause 16.4 payment of any loss or damage sustained by
the Contractor due to termination of the Contract by the
Contractor due default of the Employer;
Clause 17.4(b)cum Clause 17.3(f) & (g) payment of cost &
profit in case of Employer’s risks;
Clause 19.7 payment of costs in relation to Plant, Materials,
other costs & liabilities, cost of removal of the Temporary
Works, cost of the repatriation of Contractor’s Personnel;
Clause 20.1 cum Clause 14.3 payment of claims;
122
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Price Adjustment
6.1 General
It is common to come across price escalation in
construction projects due to the following factors:
Cost of material;
Design and specification;
Project specific factors;
Competition and market condition; and
Macroeconomic conditions.
There fore price escalation provisions are stated in many
contract forms.
Two methods of price adjustment:
Basic price (base date price) (Clause 70.1 MoWUD 1994; FIDIC
IV edition, clause 13.7 FIDIC 1999, 2006); and
Indices/Adjustment formula (clause 47.1 PPA 2006, clause 13.8
FIDIC 1999, 2006 MDB).
123
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Price Adjustment
6.2 Purpose
The purpose of a Price Adjustment clause is to provide a
mechanism for reimbursing contractors for changes in
input prices over which they have no control at all.
The adjustment to be applied to the amount otherwise
payable to the Contractor, as valued in accordance with
the appropriate schedule and certified in payment
Certificates, shall be determined from formulae for each
of the currencies in which the contract price is payable.
No adjustment is to be applied to work valued on the
basis of cost or current prices.
Ln En Mn
Pn a b c d ........
Lo Eo Mo
124
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Price Adjustment
6.3 PPPAA 2011 Provision
125
Training on Construction Contract Management, Sep 2017, Tadesse A.
7. Default of Parties
7.1 Default of Employer
Breach of contract by the employer (Sub-clause 69.1 of
MoWUD 1994 and FIDIC IV); Clause 16 of FIDIC 1999,
2006 (outlines employers default as a basis for
contractor’s entitlement to suspend and terminate the
contract).
Non-payment, late or under payment;
None or late possession of site;
Obstruction of works;
Non-coordination of work of the main contractor;
Failure to allow the engineer to function in an
independent role; and
Delay in providing drawings, information and
approvals.
126
Training on Construction Contract Management, Sep 2017, Tadesse A.
7. Default of Parties
7.2 Default of Contractor
Breach by the contractor includes (Sub-clause 63.1 of
MoWUD 1994 and FIDIC IV); Clause 15.2 of FIDIC
1999, 2006 (outlines contractors default as a basis for
Employer’s entitlement to suspend and terminate the
contract)
Abandonment or total failure to complete;
Delay in completion; and
Defective works or materials.
127
Training on Construction Contract Management, Sep 2017, Tadesse A.
7. Default of Parties
7.3 Suspension
The Engineer may instruct the contractor to suspend
some or all of the works as appropriate (Sub-clause 8.11
of FIDIC 1999, 2006 MDB).
If it continues for more than 84 days, the contractor asks
permission to proceed.
If the engineer fails to respond within 28 days the
contractor can terminate the contract.
The contractor has a right to suspend or reduce progress
of work giving 28 days prior notice, if he is not paid
within 28 days after the Engineer approved the payment
certificate and delivered to the employer as per sub-
clause 60.10 (FIDIC IV Sub-clause 69.4).
128
Training on Construction Contract Management, Sep 2017, Tadesse A.
7. Default of Parties
3.4 Termination
Termination can be a result of completion, discharge of
obligation, default of one party, force majeur etc.
One of the contracting party has a right to terminate the
contract on the ground of breach by the other party.
Ground of termination by the Employer:
Bankruptcy/Insolvency of the contractor;
Failure to execute the work in accordance with the contract;
failure to proceed with due diligence; neglect in carrying out
obligations under the contract,
Abandoning the contract;
The contractor has, to the detriment of good workmanship,
defiance of the Engineer’s instruction to the contrary, and
Assigning (sub-let) any part of the contract; and
Suspending the execution of work for 28 days after received
Engineer’s written notice to proceed.
129
Training on Construction Contract Management, Sep 2017, Tadesse A.
7. Default of Parties
3.4 Termination
Ground of termination by the Contractor:
Bankruptcy/Insolvency of the employer; being a
company goes into liquidation, other than for the
purpose of a scheme of reconstruction or amalgamation;
Failure of the employer to make payment within the
time stated by the contract;
Obstructing or interfering with the issue of any
certificate by the engineer;
Replacing the engineer against the reasonable
objections of the contractor; (FIDIC IV) and
Employer giving formal notice to the contractor for
unforeseen reasons, due to economic dislocation, it is
impossible for him to meet his contractual obligations.
130
Training on Construction Contract Management, Sep 2017, Tadesse A.
7. Default of Parties
3.4 Termination
If termination due to default of the Employer, the
contractor has the right to be compensated for the damages
that arise from the termination which include:
Idle equipment and workmen;
Material on site;
Forced demobilization; and
Anticipated profit.
If termination is due to the default of the contractor:
The employer may use contractor’s equipment for
completion of the works as he thinks proper after
termination (FIDIC IV Sub-clause 63.1).
Contractor’s equipment on site are deemed to be the
property of the employer (PPA 2006 Sub-clause 61.1).
131
Training on Construction Contract Management, Sep 2017, Tadesse A.
8. Obligation & Right of Parties
8.1 Contractor’s Obligation
The obligations of the contractor, under the FIDIC 1999
and 2006 MDB Conditions of Contract, may be
generalized as follows:
Completion obligation;
Quality performance obligation;
Timely performance obligation;
Obligation to provide securities, indemnity and
insurance;
Obligation to supply information and notice;
Administrative obligation; and
Obligation upon or after completion.
132
Training on Construction Contract Management, Sep 2017, Tadesse A.
8. Obligation & Right of Parties
8.2 Employer’s Obligation
133
Training on Construction Contract Management, Sep 2017, Tadesse A.
8. Obligation & Right of Parties
8.3 Remedial right of the Contractor
The remedial rights of the contractor, can be contractual and
legal remedies.
Contractual remedies
Financial remedies:
o Cost;
o Profit;
o Financing charges; and
o Indemnity.
Extension of time;
Other remedies:
o Deceleration of progress of the Works;
o Suspension; and
o Termination.
134
Training on Construction Contract Management, Sep 2017, Tadesse A.
8. Obligation & Right of Parties
8.3 Remedial right of the Contractor
Legal remedies
Specific Performance;
Cancellation of Contract;
General damages; and
Other remedies, if any.
135
Training on Construction Contract Management, Sep 2017, Tadesse A.
8. Obligation & Right of Parties
8.4 Remedial right of the Employer
The remedial rights of the Employer, can be contractual
and legal remedies.
Contractual remedies
Financial remedies:
o Delay damages;
o Indemnity; and
o Deduction of contract price.
Extension of time (in case of defects liability period);
Other remedies:
o Suspension; and
o Termination.
136
Training on Construction Contract Management, Sep 2017, Tadesse A.
8. Obligation & Right of Parties
8.4 Remedial right of the Employer
Legal remedies
Specific Performance;
Cancellation of Contract;
General damages;
Other remedies, if any;
137
Training on Construction Contract Management, Sep 2017, Tadesse A.
Exercise
Compare the provisions in PPA 2006, PPA 2011, MoWUD
1994 and FIDIC 1987 GCC on the following issues
Variations;
Powers and responsibility of the engineer;
Payment
141
Training on Construction Contract Management, Sep 2017, Tadesse A.
1. Claims Management
1.1 Claim: Definition
Claims in construction industry are defined as demands
for compensation in terms of money, time extension or a
combination of both a party rightly or wrongly believes
entitled to.
Claim is mostly concerned with entitlements and
liabilities arising under, or as a result of, a legally valid
contract.
A construction claim is therefore can be a demand for
payment of additional compensation, adjustment of the
parties' respective contractual obligations, extension of
time or compensating delay damages, or any other
change with regard to the contractual conditions or terms.
A claim is an assertion to a contractual right.
142
Training on Construction Contract Management, Sep 2017, Tadesse A.
1. Claims Management
1.2. Causes of Claims
Causes for claims include among other things the occurrences
of deviations from the promises made under the construction
contract during the performance of the Construction Contract.
Completion time;
Construction cost;
Quality performance; and
Safety requirements.
Claims may occur when the terms and conditions of the
contract change in such a way that the contractor is unable to
recover expenses and profits.
When the provisions of the contract documents and
specifications lack clarity, a correct interpretation of the
documents may result in extra expenditure, which a
contractor is forced to cover through claims.
143
Training on Construction Contract Management, Sep 2017, Tadesse A.
1. Claims Management
1.2. Causes of Claims
Contractors attempt to obtain work by submitting an
artificially low price and hoping to make up the difference
through claims later on.
The constraints of time, finances and other factors force a
contractor to cut corners as much as possible.
Where the form of contract transfers the risks to the
employer (esp. in DBB delivery system), the contractor
may be tempted to claim.
The following factor also contribute for claims:
Poor or unclear tender and/or contract documents;
Poor or inadequate administration of responsibilities
by stakeholders; and
Unforeseen or uncertain situations during execution
of the Construction Project.
144
Training on Construction Contract Management, Sep 2017, Tadesse A.
1. Claims Management
1.3. Understanding Claims
As part of the unique nature of civil engineering projects and
due to the unpredictability of their nature, civil engineering
projects are prone to be claim sensitive.
No matter how carefully drawn the contract documents may
be, situations can, and usually do arise, which were not
exactly as expected by the parties.
This fact seems to have been overlooked by the parties
executing major projects in the Ethiopia.
The fact that claims are in a way unavoidable should not
create an atmosphere of resignation/apprehension but should
encourage the development of a resolution mechanism.
In such cases, the best approach is not to have an
antagonistic approach toward their resolution but create an
atmosphere of partnership between all parties.
145
Training on Construction Contract Management, Sep 2017, Tadesse A.
1. Claims Management
1.3. Understanding Claims
The antagonistic approach is partly a result of lack of
experience in handling claims, inadequate
understanding of contractual and legal requirements, in
addition to an attitude of avoiding responsibility.
146
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Procedures for Claims
2.1. General
Recognizing the inevitability of claims, many
international civil engineering projects provide means of
handling claims in their contractual provisions.
These procedures set out a systematic approach to the
submission of claims and to their handling.
Claim procedures under the following contract forms is
dealt:
FIDIC IV (1987),
FIDIC 1999 and 2006 MDB,
MoWUD 1994, and
PPA 2006 (Reading Assignment).
147
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Procedures for Claims
2.2. FIDIC IV Claim Procedures
In order to avoid ambiguity in the handling of claims, the
FIDIC IV edition sets out in Clause 53 detailed procedures
for claims as follows:
The contractor gives his intention to claim within 28
days after the event give rise to the claim has first
arisen;
The contractor keeps contemporary records on the
claim issue;
The engineer examines such contemporary records;
The contractor submits detailed particulars of the
amount claimed and the grounds upon which the claim
is based;
The engineer to make determination based on the
available contemporary records.
148
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Procedures for Claims
2.3. FIDIC 1999, 2006 MDB Claim Procedures
FIDIC 1999, 2006 MDB edition sets out in clause 20.1
detailed procedures for claims which include:
The contractor gives notice to the engineer within 28
days after the event give rise to the claim has first
arisen;
The contractor submits supporting particulars to the
claim as relevant to the circumstances;
The contractor send to the Engineer within 42 days a
detailed claim with supporting particulars of the
amount claimed (extension of time and/or additional
payment); and
The engineer shall respond within 42 days after
receiving the detailed claim with approval,
disapproval or detailed comments.
149
Training on Construction Contract Management, Sep 2017, Tadesse A.
2. Procedures for Claims
2.4. MoWUD 1994 Claim Procedures
MoWUD 1994 has a brief description claims in clause
52.5 stating “the contractor sends an account giving
particulars as detailed as possible every month to the
Engineer.”
It do not state the time frame the Engineer will respond to
the claims.
Besides, the contractor is required to submit every month
the amount of additional works executed together with
claims.
Any claim not included in the particulars will not be
considered by the Engineer.
150
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
Civil Engineering projects are uploaded with a variety of
claims which attributes to their unique nature and
unpredictability.
Such claims can be categorized as follows:
Claims within the provision of the contract;
Claims outside the provision of the contract;
Claims in tort;
Quantum Meruit claims;
Ex-gratia claims; and
Disruption and delay claims.
151
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
3.1. Claims within the provision of the contract
Claims as a result of certain anticipated and specified
events and for which a remedy is designated in the
contract.
Claims as a result of an event where a certain term of the
contract is breached and for which a remedy is not
designated in the contract.
Certain ‘common’ breaches of contract, such as denied
access or late information are also covered by claims
procedures included within the claims clauses of the
contract.
Claims made under the expressed provisions of a contract
which are dealt with under the provisions of the contract.
The terms of the contract define the situations in which
such claims may be made and how they may be handled.
152
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
3.2. Claims outside the provision of the contract
153
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
3.3. Claims in Tort
Tort is a legal term used to describe the various wrongs,
which may give rise to civil proceedings, mainly in the
form of action for damages.
Although the law of tort regulates a wide variety of
unlawful behavior, those related to construction include:
nuisance, slander, libel, trespasses and negligence.
In construction projects the emission of: excessive dust,
noise, vibration, fumes, seepage, gasses, smoke etc.
produced by someone may expose him to liability for
nuisance.
The court may order the nuisance to be stopped by an
injunction or may award damages or both.
154
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
3.4. Quantum Meruit Claims
155
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
3.5. Ex-gratia Claims
Ex-gratia claims made with no foundation in the
contract or at law but only in a sense of “fairness” or
equity.
Such claims depend upon ‘ex-gratia’ or ‘kindness
payments’ by the employer made in the particular
circumstances.
Sometimes such payments are made to avoid or to
terminate claims negotiations or a dispute.
An ‘Ex-gratia’ claim might be made to recover cost
incurred by the contractor, the expenditure of which gave
benefit to the employer, but for which there are no
grounds for recovery under the contract.
156
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
3.6. Disruption and Delay Claims
These claims arise as a result of unanticipated changes
and lack of timely responses and actions.
The following events may bring about such claims:
Design changes or incomplete design;
Delay to give information, late issue/approve
drawings and works;
Delay in site handover (FIDIC Sub-clause 42.2);
Right of way related issues; and
Early occupancy (considered as interfering and
disrupting the works).
157
Training on Construction Contract Management, Sep 2017, Tadesse A.
3. Types of Claims
3.6. Disruption and Delay Claims
The possible causes of delay in construction projects
include:
Delay caused by the Contractor: unjustified and non-
compensable.
Delay caused by Employer/Engineer: Justified and
compensable.
Delay caused by External factors: Justified,
compensable or non-compensable.
Delay caused by both the contractor and Employer:
justified or unjustified and compensable or non-
compensable.
158
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Construction Disputes
4.1 Dispute: Definition
Dispute can be defined in many ways. Some of them
given by different authors are presented as follows:
Brown et al., (1993): a dispute is defined as a class or
kind of conflict, which manifests itself in distinct and
justifiable issues. It involves disagreement over issues
capable of resolution by negotiation, mediation or third
party adjudication.
Bachner (1988): a dispute will not exist until a claim is
asserted by one party which is disputed by the other
party.
159
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Construction Disputes
4.1 Dispute: Definition
Kumaraswarmy and Yogeswaran (1997): a dispute can
be said to exist when a claim or assertion made is made
by one party is rejected by the other party and that
rejection is not accepted.
The Oxford dictionary defines Conflict as a dispute or
two parties failing to reach a common understanding.
It is therefore wise to resolve the conflicts within the
industry than involving people who are not well vest
about the industry.
160
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Construction Disputes
4.2 Dispute Categories
Construction disputes may take different forms in relation to
the demands in relation to: time (delay), cost, both time and
cost and other form of disputes.
4.2.1 Delay (time) related Disputes
The contractor or the employer may have their own respective
claims with respect to delay .
The employer’s claim is related to liquidated damages.
The contractor’s claim mostly related to prolongation and/or
disruption claims.
Prolongation: a critical delay which results when the time
necessary to complete a critical activity is prolonged, thus
extending the time for completion of the whole of the works.
Disruption: the effect of an event or a number of events on
efficiency of execution of the works, irrespective of whether
or not there had been a delay to a critical activity
161
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Construction Disputes
4.2 Dispute Categories
4.2.2 Financial (Cost) related Disputes
Delays in completion of the works might result in a number
of added costs to the contractor.
If such delay is determined by the engineer to be the
responsibility of the employer, then a number of claims for
financial compensation can be pursued by the contractor.
These claims include:
Direct costs,
On-site establishments, and
Off-site (head office) overhead.
Finance charges and interest,
Profit on direct costs,
Loss of profit, and
Interest on late payment.
162
Training on Construction Contract Management, Sep 2017, Tadesse A.
4. Construction Disputes
4.2 Dispute Categories
4.2.2 Financial (Cost) related Disputes
Delays in completion of the works might result in a number
of added costs to the contractor.
If such delay is determined by the engineer to be the
responsibility of the employer, then a number of claims for
financial compensation can be pursued by the contractor.
These claims include:
Direct costs,
On-site establishments, and
Off-site (head office) overhead.
Finance charges and interest,
Profit on direct costs,
Loss of profit, and
Interest on late payment.
163
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Disputes Resolution
5.1 General
Dispute resolution may have the following aspects/
dimensions:
Preventive,
Amicable settlement:
o Negotiation,
o Mediation, and
o Conciliation.
Judgmental:
o Adjudication,
o Arbitration, and
o Litigation.
164
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Disputes Resolution
5.1 General
The concept of ADR (Alternative Dispute Resolution),
Alternative to what?
The concept of ADR is related to alternative to litigation
or sometimes alternative to all binding decision making
process (including the decision of the adjudicator and
arbitrator).
Both preventive and amicable dispute resolution systems
may be categorized under ADR. There is no any binding
or imposed decision by a third party in preventive and
amicable settlement.
165
Training on Construction Contract Management, Sep 2017, Tadesse A.
5. Disputes Resolution
3.2 Dispute Prevention
The following aspects may contribute to the prevention
of construction disputes.
To have a well planned, studied, and designed project;
To have a clear, accurate and complete tender dossier,
and document;
To have a clear, accurate and complete contract document;
To have a balanced (in terms of allocation and distribution
of risks, rights and obligations among the contracting
parties) contract document;
To discharge the expected contractual and legal
obligations by the contracting parties;
To have a good project governance; and
To have a well thought and suitable dispute prevention
system.
166
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.1 Amicable Settlement
The very feature of amicable settlement is that the
disputing parties shall have full control both over the
process and the outcome.
There is no third party imposition of solution on the
parties to the dispute.
The following are some of the highly recognized
amicable settlement methods.
Negotiation;
Mediation; and
Conciliation.
167
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.1 Amicable Settlement
6.1.1 Negotiation
Negotiation is a give and take process, a serious attempt
to reach a settlement agreement (Sub-clause 67.2 of
FIDIC IV; Sub-clause 20.5 of FIDIC 1999, 2006 MDB).
Negotiation could be:
Direct negotiation; or
Assisted negotiation.
Direct negotiation is held directly between parties to the
dispute. The parties may, of course, be assisted by their
own internal advisors.
In case of assisted negotiation, mediation and
conciliation come in to picture.
168
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.1 Amicable Settlement
6.1.2 Mediation
Mediation describes the process of a neutral and
disinterested person helping disputing parties to
negotiate a resolution to their dispute.
Mediation is simply a facilitated or assisted negotiation.
To agree or not to agree is left to the decision of the
parties.
The mediator helps disputing parties to understand the
dispute in a way that will maximize their chances to
reach a mutually acceptable and lasting solution.
A mediator facilitates the discussion or negotiation, but
will never propose a solution for the settlement of the
dispute.
169
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.1 Amicable Settlement
6.1.2 Mediation
The advantages of mediation include informality, speed and
economy; but more importantly perhaps, it often leads to an
agreed settlement between the parties rather than an imposed
award or judgment.
The process or structure of mediation is described as follows:
Setting the Table;
Story Telling;
Determining Interests;
Setting out the Issues;
Brainstorming Options;
Selecting the Durable Options; and
Closure.
170
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.1 Amicable Settlement
6.1.3 Conciliation
Conciliation is a voluntary form of dispute resolution where
a neutral party, the Conciliator, is appointed to facilitate
negotiation between the parties in dispute and to act as a
catalyst for them to reach a resolution of their dispute.
Unlike the mediator, the conciliator under the conciliation
process, takes a more active role probing the strengths and
weaknesses of the parties’ case,
Making suggestions;
Giving advice;
Finding persuasive arguments for and against each of
the parties’ positions; and
Creating new ideas which might induce them to settle
their dispute.
171
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.1 Amicable Settlement
6.1.4 Difference of Mediation and Conciliation
Under the mediation method of dispute resolution, if the
parties to the dispute fail to reach agreement, the
mediator himself is then required to draw up and propose
a solution which represents what, in his view, is a fair
and reasonable compromise of the dispute.
Conciliation is a more formal process than mediation
and it generally involves the engagement of legal
representatives, thus making it a more expensive process
than mediation.
172
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
The very feature of the judgmental dispute resolution is
that the third party known as the court judge, the
arbitrator or the adjudicator decides the case before
him/her for the parties.
The parties to the dispute shall have no control over the
process (especially in case of the court system) and/or the
outcome in all the three cases.
Under the judgmental dispute resolution the following are
recognized:
Adjudication ;
Arbitration; and
Litigation.
173
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
6.2.1 Adjudication
Adjudication can be defined as a process whereby an
appointed neutral and impartial party is entrusted to take
the initiative in ascertaining the facts; the law relating to a
dispute and to reach a decision within a short period of
time.
Under the new FIDIC conditions of contract Dispute Board
(DB) is suggested (Sub-clause 20.2 of FIDIC 1999, 2006
MDB).
Dispute Board can, according to ICC, be of three types,
namely,
Dispute Review Board (DRB);
Dispute Adjudication Board (DAB);
Combined Dispute Board(CDB);
174
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
6.2.1 Adjudication
Adjudication can take the following types:
Permanent adjudication; or
Ad-hoc adjudication.
The permanent one is normally set up at the course of the
contract which remains in place and the members are
remunerated throughout its duration.
An ad-hoc adjudication is only established after the dispute
has been arisen and its existence comes to an end after it
gives its Determination, Recommendation or Decision.
The Adjudication could also be composed of:-
Sole member; or
Three members.
175
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
4.2.2 Arbitration
Arbitration is a process whereby parties in dispute agree to
submit the matter in dispute to the decision of a person or
persons in whom they have confidence, trust and undertake
to abide by that decision.
Many contract forms have arbitration provisions such as:
Sub-clause 67.3 of FIDIC IV and Sub-clause 20.6 of FIDIC
1999, 2006 MDB.
According to Article 3325(1) of the Civil Code: “The arbitral
submission is the contract whereby the parties to a dispute
entrust its solution to a third party, the arbitrator, who
undertakes to settle the dispute in accordance with the
principles of law.”
The parties to the dispute control the process but not the
outcome i.e. the decision called the award.
176
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
4.2.2 Arbitration
The pre-requisite to a valid arbitration are the following:
The existence of a dispute;
Agreement to refer the dispute to arbitration when the
dispute arises;
Agreement to be bound by the award; and
Initiation of the arbitration.
In relative terms, the following may be taken as advantages of
arbitration.
Neutrality; (of the arbitrators)
Confidentiality; (no publicity of both the process and the
outcome)
Procedural flexibility; (the parties in dispute are capable
of designing their own process)
177
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
4.2.2 Arbitration
In relative terms, the following may be taken as
advantages of arbitration.
Expert arbitrators well versed with the industry;
Speed and cost;
Finality of awards; (no appeal, if not always)
Enforcement of awards; (recognition of the award by
national courts)
Limited powers of arbitrators; ( no coercive power)
Multi-party disputes; (no joiner and no consolidation
of third parties without their express consent)
Awards not binding on third parties.
178
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
4.2.3 Litigation
Litigation takes place at the court of law having jurisdiction
over the case. The courts play here their dispute resolution
role.
Litigation is the most serious and adversarial method of
dispute resolution.
The procedure before the court is so rigid and not tailor
made to the construction dispute resolution.
The courts are following the standard procedure established
under the civil procedure code, which applies for all types of
disputes brought to them.
The advantages of arbitration are all missing under litigation.
The clear disadvantage of litigation is that it being the most
time consuming.
179
Training on Construction Contract Management, Sep 2017, Tadesse A.
6. Disputes Resolution Mechanisms
6.2 Judgmental Settlement
4.2.3 Litigation
The clear advantage of litigation is that the court itself
enforces its own orders and judgments.
The role of courts, however, very important in terms of:
Enforcing an agreement to arbitrate;
Recognizing and enforcing domestic arbitral award;
Recognizing and enforcing foreign arbitral award;
Rendering judicial assistance to the arbitration
process or to the settlement agreement;
Hearing appeals against the arbitral award, if not
final and appealable; and
Setting aside of an arbitral award, if, legally qualified
to be set aside.
180
Training on Construction Contract Management, Sep 2017, Tadesse A.
THANK YOU!
181
Training on Construction Contract Management, Sep 2017, Tadesse A.
Project Time Management/Control
182
183
Cont…
184
2. Activity Sequencing
Activity sequencing involves identifying and documenting the
185
Cont…
186
3.Activity Resource Estimating
Estimating schedule activity resources involves determining
187
4. Activity Duration Estimating
The process of estimating schedule activity durations uses
188
Cont…
189
5. Schedule Development
Project schedule development, an iterative process, determines
190
Cont…
191
6. Schedule Control
Schedule control is concerned with:
management system
192
Cont…
193
in
planning,
estimating,
budgeting and,
controling costs so that the project can be completed
within the approved budget.
To achieve this purpose we need to develop a
proper cash flow
160
140
120
Cost ($)
100
Activity Days Cost ($) Cost/day
80
A 2 200 100
60
B 5 500 100
C 2 200 100 40
D 7 500 71.4 20
E 1 100 100 0
F 2 100 50 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Day
Day Activity Cost of day Total cost
Cumulative Expenses
1 A 100 100
2 A 100 200 1800
7 B 100 700
Cost ($)
1000
8 C,D 171.4 871
9 C,D 171.4 1043 800
14 D 71.4 1500 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
15 F 50 1550
Day
16 F 50 1600
Source: Dr. L. K. Gaafar
Example 1
Month Budgeted Cost in Month Cumulative Budgeted Cost at end
(Birr) of month (Birr
January 500,000 500,000
February 1,000,000 1,500,000
March 2,000,000 3,500,000
April 2,500,000 6,000,000
May 3,500,000 9,500,000
June 5,000,000 14,500,000
July 5,000,000 19,500,000
August 4,000,000 23,500,000
September 3,000,000 26,500,000
October 2,000,000 28,500,000
November 1,000,000 29,500,000
December 500,000 30,000,000
198
Total for Year 30,000,000 30,000,000
Chart 1
Chart 1: Cumulative Cost Curve Based on Budget Costs at Planned Time
35000000
30000000
20000000
15000000
10000000
5000000
0
0 Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar
199 Months of Project
200
Chart 3
40000000
Chart 3: Comparison of Budget & Actual Costs Based on Actual Timing
35000000
Actual Cost of Work
Completed (Table 3)
30000000
Cumulative Costs: Birr
20000000
10000000
5000000
0
0 Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar
Months of Project
201
All together
Estimate of Final Cost (Contract Sum)
Current Date
Maintenance
Construction Period
202 Period
Earned Value Analysis
The earned value technique uses the cost and schedule
203
Earned Value Analyses (Cont…)
Planned value (PV) is the budgeted cost for the work scheduled to be
204
Cont…
Planned Numerical Examples on Earned Value Analysis
Week Price
1 18000
Actual Performance
After 5 weeks
2 18000
3 72000
4 72000
5 125000
Total 305,000
Numerical Examples on Earned Value Analysis
Week Price
1 18000
2 18000
SV = EV – PV
3 72000
CV= EV – AC 4 72000
5 125000
207
Total 305,000
Resource Management
of resources such as: welders, laborers and a certain type of welding machine.
After each activity has been assigned its resources, the next step is to
is absolutely necessary.
Accordingly, the primary focus, for purposes of scheduling, in time
requirement that is "smooth" and where peaks and valleys are eliminated.
Given that the resource requirements of those activities on the critical path
are fixed, some order or priority needs to be established for selecting which
activity and which particular resource associated with this activity should
be given priority in the smoothing process.
Resource leveling shift non-critical activities within their float times so as
to move resources from the peak periods (high usage) to the valley periods
(low usage), without delaying the project
Cont…
217
Cont…
218
Cont…
219
THANK YOU!
220
Training on Construction Contract Management, Sep 2017, Tadesse A.