1. PURPOSE:
The objective of this procedure is to ensure that the containers are planned for discharging / loading from / to the
vessel.
2. SCOPE:
This procedure encompasses guidelines with regard to the actions to be taken from the initial receipt of
Vessel / Container details from the Shipping Line / Agent through to final issue of the discharge / loading
Planning of the vessel.
3. PROCEDURE:
Start
No
Planning Documentation In order? Correct errors by VOA
Yes
Yes
No If vessel call Cancellation notice shall
VOA be given
skipped
End
Controlled Copy
Visakha Container Terminal Pvt. Ltd. Page 2 of 4
Start
Upload the
Planning Documentation In TOS Screen
BAPLIE & IAL
End
Start
Controlled Copy
Visakha Container Terminal Pvt. Ltd. Page 3 of 4
Upload the
Planning Documentation In TOS Screen
EAL
Criteria:
Loading Containers Stability (vessel trim / list)
planned in vessel profile Heavy containers in down and
Vessel Planner
screen in TOS light in up
Stack weight and
Yard allocation
Controlled Copy
Visakha Container Terminal Pvt. Ltd. Page 4 of 4
End
Note: Hard copies of discharge and loading plans shall be filed in the vessel file. Retention Period two (2) years.