You are on page 1of 4

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/254053430

Present status and technical challenges of micro hydropower plants in Nepal

Conference Paper · January 2012

CITATIONS READS

2 1,357

3 authors:

Parakram Pyakurel Bidhan Rajkarnikar


Solent University Kathmandu University
27 PUBLICATIONS   265 CITATIONS    4 PUBLICATIONS   9 CITATIONS   

SEE PROFILE SEE PROFILE

Hari Prasad Neopane


Kathmandu University
95 PUBLICATIONS   714 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Capacity and Competence development for introducing Francis Turbines in Nepalese Micro Hydropower projects View project

Development of sand erosion proof 20 kW micro- hydro class cross- flow turbine and its site demonstration in Nepal” View project

All content following this page was uploaded by Hari Prasad Neopane on 11 April 2016.

The user has requested enhancement of the downloaded file.


Present Status and Technical Challenges of Micro
Hydropower Plants in Nepal
Parakram Pyakurel, Bidhan Rajkarnikar, Dr. Hari Prasad Neopane*

Department of Mechanical Engineering, School of Engineering, Kathmandu University, Nepal


* E-mail of Corresponding Author: hari@ku.edu.np

Abstract

Micro hydropower (MH) plants have played an important role in electrifying rural villages in Nepal. There are well above 2000 MH
plants in the country which generate around 15 MW and electrify more than 150 thousand households. Nepal has developed good
technical capacity in MH turbine manufacturing and there are more than 20 MH turbine manufacturing companies. However, there
are various technical challenges in Nepali MH sector. The overall efficiencies of MH plants are very low and there are very less end
use devices in villages which have led to poor revenue generation from MH plants. Moreover, the country lacks skilled manpower in
villages where MH plants are located. Besides, Nepal does not have good technical competence in manufacturing Francis turbines
and MH generators so the country is still not self dependent on MH technology. In this paper, present status of micro hydropower
plants in Nepal is discussed and explores various technical challenges. Furthermore, it also recommends different solutions to
overcome the technical challenges.

Keywords: Micro Hydropower Plants, technical challenges, End-use Technologies, Plant Capacity Factor, Overall Efficiency

1. Introduction
Most of the MH plants installed in Nepal have used
Nepal is known for its huge water resources potential. Cross-flow turbines and Pelton turbines for power
The surface water available in about 6,000 rivers and generation. About 76 % of the turbines till 2004 were
rivulets of the country is estimated to be about 224.7 Cross-flow followed by 20 % MPPU and 13 % Pelton
billion m3 per annum or equivalent to an average flow [6]. These turbines were mostly designed and
of 7,125 m3/s. Therefore the total theoretical potential of manufactured locally in Nepal. Thus, over a period of
Micro Hydropower (MH) is very large [1]. MH sector time, Nepal has developed good technical competence
in Nepal has a long history dating back to the 1960s. in manufacturing Cross-flow and Pelton turbines. There
The History of waterpower in Nepal began with the are various companies in Patan Industrial Estate,
traditional water mills or ghatta used for grinding flour Lalitpur and Butwal which manufacture these types of
which was improved in later stages to higher efficient turbines. However, Nepal still lacks sufficient technical
Multi-Purpose Power Unit (MPPU). After the necessity capabilities in Francis turbine manufacturing. Also,
of electricity was realized in villages, the MH plants Nepal does not have Research & Development (R& D)
were used to produce electricity for villages where center and performance testing center dedicated to MH
national electricity grid was yet to be connected. Till sector which would enhance the overall technical
date, there are well above 2000 MH plants in Nepal capabilities in MH sector.
which generate a total of 15 MW. These MH plants
benefit around 150 thousand households [2], [3], [4]. In recent times, Rural Energy Development Programme
Thus, MH plants have made profound impact in the (REDP) tested a micro Francis Turbine at Handi Khola,
villages of Nepal. Sindhupalchowk, Nepal. In the pilot project, power
output increased by 6 kW when the Cross Flow turbine
2. Micro Hydropower Status in Nepal was replaced by a locally designed and fabricated micro
Francis. Moreover, the weight of the Francis was just 90
2.1 General kg compared to 400 kg for the Cross Flow turbine [3].
This can reduce the cost of material used for
The installation of Micro Hydropower plants are manufacturing turbines. This is also a major
supported by the Government of Nepal through achievement in the context of Nepal where the turbines
Alternative Energy Promotion Center (AEPC). AEPC and other equipments has to be carried by porters for
supports the installation of Micro Hydropower plants days to reach the project site. Such break through can be
through different donor funded programmes like Rural achieved much faster and in more scientific way by the
Energy Development Program (REDP) and Mini Grid establishment of Research and Development (R&D)
Support Programme under Energy Sector Assistance center and MH component performance testing center.
Program (MGSP/ESAP) [5].
MH Plant components like penstock pipes, bends, Verification Guidelines‟. This guideline describes the
expansion joint, valves, Electric Load Controllers procedure for verification of number of households
(ELC), transmission poles and conductors are served and power output produced for hydropower
manufactured in Nepal. However, many other schemes in the range above 5 kW and up to 500 kW [8].
components like bearings, power transmitting belts and
generators are normally imported from countries such as The power output verification guideline recommends
India and China. This is not only due to lack of two methods for power output measurements: the
competence to produce such components, but also due method using power measurement kit (with additional
to lack of R&D center. dump load) and measurement by true Root Mean
Square (RMS) clamp-on-power meter. However, it does
2.2 Standard Practice not mention about the performance testing and
verification of the rated output of different components
A guideline for detailed feasibility studies of MH of MH plants. This guideline also mentions the standard
projects has been prepared by AEPC to ensure the procedures for the verification of households that are or
quality of feasibility study reports and ultimately quality can be benefited by the constructed MH Plant.
of MH plants.
3. Technical Challenges in Micro
The guideline suggests at least 11 month exceedance Hydropower
flow based on Medium Irrigation Project (MIP) as the
design discharge for the power calculation. For the river There are various technical challenges in MH sector in
flow measurement, salt dilution method is suggested. Nepal. The technical challenges affect the performance
The guideline recommends assessment of demand for of MH plants and hence affect the energy revenue. This,
power and end-use possibilities in the feasibility study in turn, will affect the sustainability of the entire MH
report [7]. sector.
In the civil components, the guideline recommends Major technical challenges in MH sectors of Nepal are:
criteria of selection for intake, weir, gravel trap, settling
basin (sand trap), forebay, penstock supports (support a) Low overall plant efficiency
piers, anchor blocks), powerhouse building, tailrace and
b) Lack of MH R&D center
stop logs.
c) Lack of MH components performance testing
In the hydro-mechanical components, the guideline center
recommends design and selection criteria for trash rack, d) Low plant capacity factor
penstock pipe, expansion joints and valves. In the e) Lack of skilled manpower in villages
electro-mechanical components, the guideline mentions f) Lack of rigorous trainings to the operators and
about design and selection criteria of turbines and drive
managers of MH plants
system. According to the guideline, the efficiencies at
the rated output of turbines to be used in a feasibility
study are as follows: Despite the fact that MH sector has made a huge
contribution on providing electricity and improving
a) Pelton 5-30 kW: 70-80 % (the lower range is for living standard of people in rural villages, there is no
R&D center solely devoted to MH plant so far. Thus,
low-cost units and for off-optimum design)
there is no organization/ institution that work
b) Pelton above 30 kW: 75-85 % exclusively for efficiency monitoring and improvement
c) Cross-flow 5-30 kW: 60-70 % of MH plants. Since there is no such institution, the MH
d) Cross-flow above 30 kW: 65-78 % sector is plagued by low overall efficiency plants.

In the electrical components, the guideline mentions The above mentioned fact makes it very necessary to
about standards to be used for generator, powerhouse/ establish such R&D center which shall exclusively
control and protection system, earthing, transmission focus on MH plants and efficiency improvement. The
and distribution system, lightning protection and service R&D center can focus on following areas:
wire.
a) Research on efficiency improvement of turbines
The guideline for detailed feasibility studies of MH b) Research on low cost manufacturing of turbines
projects only ensures the quality standard during the c) Research on low cost construction of MH plants
design and feasibility stage of MH construction. Hence, d) Research on manufacturing of MH generators as
to make sure that the installers and manufacturers have
well as other components
met the specified standard, AEPC has also prepared
„Micro - Mini Hydro Power Output and Household e) Research on overall efficiency improvement of
MH plants
Along with the establishment of R&D center, it is also establishment of R&D and performance testing center to
necessary to establish a MH component performance address the low overall efficiency problem of MH plants;
testing center. The performance testing center shall have improvement of plant capacity factor by introducing
the following functions: more end use technologies and electricity intensive
businesses in villages; and providing rigorous trainings
a) Efficiency testing of turbines and generators to the village people to generate sufficient skilled
b) Calculating the overall efficiency of MH plants manpower to manage and operate MH plants.
c) Facilitating in the preparation of standard
guideline for construction and manufacturing of Acknowledgement
MH plants components such as turbines, ELC
This paper is based upon the materials drawn from
various papers and reports mentioned in the references,
Another issue seriously challenging the MH sector is
which have been extremely helpful in preparing this
low plant capacity factor. The plant capacity factors of
paper. Authors would like to express sincere thanks to
most of the MH plants are very low as MH plants do not
Alternative Energy Promotion Center (AEPC) and
operate 24 hours a day. The main reason for MH plants
Nepal Micro Hydropower Development Association
not operating 24 hours a day is lack of end use
(NMHDA) for providing required information to
technologies (loads other than lighting). Since lighting
prepare this paper.
is almost the only electrical load in village, it is not
necessary to operate the MH plant throughout the day. It
is very necessary to introduce different end use References
technologies such as rice hullers, oil expellers, water
[1] Nexant, SARI/Energy, “Regional Hydro-power
pumps and other devices consuming electricity so as to
Resources: Status of Development and Barriers, Nepal”,
improve the plant capacity factor. Such end use Prepared for United States Agency for International
technologies will not only improve plant capacity factor Development under South Asia Regional Initiative for
but also promote small scale businesses in villages Energy, 2002.
which will help reduce the unemployment and poverty. [2] Alternative Energy Promotion Center, Ministry of
Environment, Science and Technology, Government of
It is also necessary to give rigorous trainings related to Nepal, “Mini-Grid Yearbook of Nepal”, 2007.
every aspect of MH sector to people in villages because [3] Alternative Energy Promotion Center, Ministry of
such training will generate sufficient skilled manpower Environment, Government of Nepal, “Annual Progress
Report FY 2066/67 (2009/10)”, 2010.
that can make MH sector more lucrative. Some
[4] Water and Energy Commission Secretariat, Government
manufacturing companies provide training for fulfilling of Nepal, “Energy Sector Synopsis Report 2010”, 2010.
required skilled manpower. But there are no specific [5] B. Rajkarnikar, P. Pyakurel and Dr. H. P. Neopane,
institutions where trainee could get complete knowledge “Sustainability Issues of Micro Hydropower Plants in
about survey, design, installation, and manufacturing Nepal”, 3rd International RETRUD Conference, Nepal,
components. Nepal Micro Hydropower Development 2011.
Association (NMHDA) conducts the training for [6] Energy Forum, Sri Lanka, “Report of the South Asia
operators, managers and surveyors in association with Regional Workshop on Developing Standards for Micro-
ESAP, REDP and other donors including government Hydro Sector”, 2004.
[7] Alternative Energy Promotion Center, Ministry of
[6]. However, operators and managers of MH plants in
Environment Science and Technology, Government of
Nepal are still not competitive enough to make MH Nepal, “Guidelines for Detailed Feasibility Studies of
sector sustainable and profitable venture. Therefore, it is Micro-Hydro Projects”, 2004.
necessary to generate skilled manpower in villages that [8] Alternative Energy Promotion Center, Ministry of
can take MH sector into whole new level of profits. Environment, Government of Nepal, “Micro - Mini
Hydro Power Output and Household Verification
4. Conclusions and Recommendations Guidelines”, 2008.

Micro hydropower sector have a huge impact in rural


villages of Nepal. It has benefited many households
where national electricity grid is yet to be reached.
However, there are various technical challenges in the
MH sector of Nepal. Most of them are low overall plant
efficiency, low plant capacity factor and lack of
sufficient skilled manpower in villages.

It is thus very important to take various measures to


address the technical issues challenging MH sector in
Nepal. Some of the important measures to be taken are:

View publication stats

You might also like