You are on page 1of 1

Kiln mechanical dept,

Dangote cement PLC,

Obajana, Kogi state.

24/11/222.

To ,

Human resources manager /admin

Dangote cement plc,

Obajana, Kogi state.

Dear sir,

Shift roaster reschedule

This is to notify you that the attached engineers on roster (Alabi Jimoh and Ottoide Andrew)

Will be covering the shift as per attached schedule ,due to unavailability of one engineer

(Stanley onyeagoro )who would be proceeding on his annual leave from 24 th, nov, to Dec.

6,th,2022.This roster is for the basis of shift coverage until he resume back on 07,12,2022

Please ,act and make necessary action on payment/remuneration appropriately as per

attached schedule

SIGN :

Bernard Abudu (Kiln 3) James Fadimu Senior maintce mgr.

AGM (kiln 3) SGM(KILN)