Professional Documents
Culture Documents
NASHUA-PLAINFIELD CSD
PLAINFIELD MIDDLE SCHOOL
DEMOLITION
NASHUA-PLAINFIELD COMMUNITY SCHOOL DISTRICT
612 GREELEY STREET, NASHUA, IOWA
PROJECT MANUAL
ARCHITECT PROJECT NUMBER: I0601.04
DIVISION 31 – EARTHWORK
SECTION 311000 – SITE CLEARING 3 95-97
DIVISION 34 – APPENDIX
SECTION 340000 – SUDAS 10,010 - DEMOLITION OF BUILDING STRUCTURES 9 98-106
SECTION 341000 – CSI SUBSTITUTION REQUEST FORM 1 107
PAGE 1 OF 1
PROJECT MANUAL
Marion Office
700 11th Street, Suite 200
Marion, Iowa 52302
Telephone: 319-377-7604
Fax: 319-377-1175
I hereby certify that the portion of this technical submission described below was prepared
by me or under my direct supervision and responsible charge. I am a duly licensed
architect under the laws of the state of Iowa.
______________________________________________________________________
Signature Date
License number:
My license renewal date is June 30, _____________________________
______________________________________________________________________
NOTICE OF PUBLIC HEARING AND LETTING OF BIDS FOR THE OLD MIDDLE SCHOOL DEMOLITION,
NASHAU-PLAINFIELD COMMUNITY SCHOOL DISTRICT, hereafter referred to as the Owner.
Notice is hereby given that the Owner, 612 Greeley Street, Nashua, Iowa invites contractors to submit bids
for this project and that a public hearing will be held on the on the project.
Project Description: The proposed project consists of demolition of the old Plainfield Middle School building
including footing, foundations, and paving, terminating and capping utilities, and filling demolition site.
Bid Type: One lump sum contract will be awarded at the appointed time and place.
Pre-Bid Conference: A formal pre-bid meeting will be held on site June 3, 2021 at 1:00 p.m. for this
project. General Contractors and Subcontractors may set up an appointment through the architect to visit
the site
Project Access: The building will be available for inspection by contacting the architect or Administration
office to set up an appointment.
Documents: Plans and specifications governing construction of the proposed project have been prepared by
Martin Gardner Architecture PC., Marion, Iowa as Architect. All materials and procedures shall be in strict
accordance with said plans and specifications referred to and defining said proposed improvements and
are hereby made a part of this Advertisement and of the proposed contract by reference, and that the
contract shall be executed in compliance therewith.
Document Availability: Plans and specifications and proposed contract documents may be examined at the
offices of the Architect, and other locations as outlined in the Construction Documents. Copies of the plans
and specifications, form of contract and bid form may be obtained from Martin Gardner Architecture, P.C.,
700 11th Street, Suite 200, Marion, IA 52302 or 11502 390th Street, Strawberry Point, IA 52076, 319-
377-7604. The Architect's office will issue plans to all Contractors. A maximum of two sets of Construction
Documents will be provided to each General Contractor upon delivery of a $250 per set refundable
deposit to the office of the Architect. All other Subcontractors and Suppliers may obtain one set of
Construction Documents upon delivery of a $50 per set refundable deposit to the office of the Architect.
The drawings and specifications are available at the architect’s website www.MartinGardnerArch.com.
Plans and specifications to be viewed are in Adobe .pdf format and may be downloaded and printed. Be
aware that no warranty as to the compatibility of your computer software or hardware with the files
provided is made. Variations between the printed files provided above by the Architect and these
electronic files may exist. In the event that a conflict does exist, the printed documents issued by the
Architect will take precedence over the downloaded files.
Bid Forms: All bids shall be on the forms provided in the specifications for project. The provided forms of
proposal shall be submitted at the time required for bids.
Bid Security: Each bid shall be accompanied by a bid bond, certified check, cashier’s check or credit union
certified share draft, in a separate sealed envelope in an amount equal to five percent (5%) of the total
amount of the bid. If bid bond is submitted, it must be on an approved AIA bid bond form. The certified
check or cashier’s check shall be drawn on a bank in Iowa or a bank chartered under the laws of the
United States of America; certified share draft shall be drawn on a credit union chartered under the laws of
the United States. Bid security should be made payable to the Owner as security that if awarded a contract
the bidder will enter into a contract at the prices bid and furnish the required Contractor’s Bonds, Certificate
of Insurance, and other materials as may be required in the contract documents. The certified check,
cashier’s check, or certified share draft may be cashed, or the Bid Bond forfeited, and the proceeds
retained as liquidated damages if the Bidder fails to execute a contract and file acceptable Certificate of
Insurance within ten (10) days after the acceptance of the proposal by the Owner. No bidder may
withdraw a proposal within thirty (30) days after the date set for opening bids.
Project Bonding: The successful bidder shall be required to furnish a Contractor’s Performance and Labor
and Material Payment Bond on an approved AIA form in an amount equal to one hundred percent (100%)
of the contract price. The bonds are to be issued by responsible surety, approved by the Owner, and shall
guarantee the faithful performance of the contract and the terms and conditions therein contained and shall
guarantee the prompt payment for and of all materials and protect and save harmless the Owner from all
claims and damages of any kind caused by the operation of the Contractor, and shall guarantee the work
contracted for a period of one (1) year from the date of final acceptance of the improvements by the
Owner.
Sales Tax: The said project is a tax-exempt project. The Owner will issue exemption certificates from the
Iowa Department of Revenue, as specified in the 701 Iowa Administrative Code, Chapter 19, Rule 19.12.
These certificates shall be used by the successful bidder when purchasing materials or the completion of the
project.
Bid Filing: All bids must be filed at the Administration Office, located at 612 Greeley Street, Nashua, Iowa
50658, on or before 1:00 pm local time, June 11, 2021. Bids received after this time will not be accepted.
Bid Opening: Bids will be opened and publicly read aloud immediately after specified closing time.
Notice of Public Hearing- Notice is hereby given that the Nashua-Plainfield Community School Board will
meet electronically via zoom and in person in the JH/HS Commons located at Nashua-Plainfield
Community School High School at 612 Greeley Street, Nashua, Iowa 50658 on June 14, 2021 at 7:00
p.m. local time at which time and place a hearing will be held on the proposed demolition project, and
form of contract. Any interested party may appear to be heard.
Award of Contract: Notice is hereby given that the Owner will meet in the Board Room located at Nashua-
Plainfield Community School District High School at 612 Greeley Street, Nashua, IA 50658 on June 14,
2021 at 7:00 p.m. at which time and place the Owner will consider bids for said demolition.
Progress Payments: Payment to the Contractor will be made in monthly estimates and one final payment.
Monthly estimates will be equivalent to ninety-five percent (95%) of the contract value of the work
completed during the preceding calendar month. Such payments will in no way be construed as an act of
acceptance for any of the work partially or totally completed.
Final Payment: Final payment to Contractor will be made no earlier than forty-five (45) days from and after
final acceptance of work by the Owner, subject to the contract conditions and in accordance with the
provisions of Iowa Code chapters 26 and 573.
Project Schedule: The work under the contract shall commence on or before the date specified in the written
‘Notice of Proceed’ or if lieu of the notice to proceed, the execution of the contract and shall be
Substantially Completed on or before December 17, 2021 and fully completed and ready for acceptance
no later than December 31, 2021.
Iowa Preference: By virtue of statutory authority, preference will be given to products and provisions grown
and produced within the State of Iowa and to Iowa domestic labor.
The Owner hereby reserves the right to reject any or all bids and to waive informalities and irregularities
and to accept the lowest responsive and responsible bid.
By________________________________
Attest:_____________________________
1.2 PRE-BID CONFERENCE: On site, June 3, 2021 1:00 p.m. Contractors may also set an appointment with the
architect or adminstrative office to view the site.
1.5 DOCUMENTS ON FILE: Documents shall be available for inspection at the following locations and on our
website at www.MartinGardnerArch.com: Printed documents are available by contacting the Marion office of
the Architect.
MARTIN GARDNER ARCHITECTURE, P.C.- Contact this office to obtain copies of bid documents.
700 11th Street – Suite 200
Marion, IA 52302
1.7 SITE ACCESS: The existing building can be avalible for inspection by appointment by contacting the architect or
administration office 24 hours in advance.
1.12 PRICE GUARANTEE: Prices quoted shall be guaranteed for a period of fourty-five (45) days after the date of the
Bid.
1.13 IOWA SALES TAX: No sales tax on all applicable materials shall be charged to this project and all bid forms
submitted shall contain no said sales tax. Sales Tax Exemption Certificate will be issued by the Owner upon completion
of the contract for construction.
1.14 PROPOSED COMPLETION DATE: Substantial Completion shall be achieved by December 17, 2021 with Final
Completion no later than December 31, 2021.
ARTICLE 2 – DEFINITIONS
2.1 GENERAL: Bidding Documents include the Bidding Requirements and the proposed Contract Documents. The
Bidding Requirements consist of the Advertisement or Invitation to Bid, Instructions to Bidders, Supplementary Instructions
to Bidders, the bid form, and other sample bidding and contract forms. The proposed Contract Documents consist of the
form of Agreement between the Owner and Contractor, Conditions of the Contract (General, Supplementary and other
Conditions), Drawings, Specifications and all Addenda issued prior to execution of the Contract.
2.2 ADDITIONAL DEFINITIONS: Definitions set forth in the General Conditions of the Contract for Construction, AIA
Document A201, or in other Contract Documents are applicable to the Bidding Documents.
2.3 ADDENDA: Addenda are written or graphic instruments issued by the Architect prior to the execution of the
Contract which modify or interpret the Bidding Documents by additions, deletions, clarifications or corrections. All
addenda issued during the bidding period shall be included in the bids and will become a part of the Contract
Documents
2.4 BID OR PROPOSAL: A Bid or Proposal is a complete and properly executed proposal to do the Work for the sums
stipulated therein, submitted in accordance with the Bidding Documents.
2.5 BASE BID: The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in
the Bidding Documents as the base, to which Work may be added or from which Work may be deleted for sums stated
in Alternate Bids.
2.6 ALTERNATE BID: An Alternate Bid or Alternate is an amount stated in the Bid to be added to or deducted from the
amount of the Base Bid if the corresponding change in the Work, as described in the Bidding Documents, is accepted.
2.7 UNIT PRICE: A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials, equipment
or services or a portion of the Work as described in the Bidding Documents.
2.8 BIDDER: A Bidder is a person or entity who submits a Bid and who meets the requirements set forth in the Bidding
Documents.
2.9 SUB-BIDDER: A Sub-bidder is a person or entity who submits a bid to a Bidder for materials, equipment or labor for
a portion of the Work. The Sub-Bidder in submitting a proposal represents that to the extent applicable to his portion of
the Work that he is making the same representations outlined in Article 3 as the Bidder.
3.1 The Bidder and to extent applicable, the Sub-Bidder by making a Bid represents that:
3.1.1 The Bidder has read and understands the Bidding Documents or Contract Documents, to the extent that such
documentation relates to the Work for which the Bid is submitted, and for other portions of the Project, if any, being bid
concurrently or presently under construction.
3.1.2 The Bid is made in compliance with the Bidding Documents.
3.1.3 The Bidder has visited the site, become familiar with local conditions under which the Work is to be performed
and has correlated the Bidder's personal observations with the requirements of the proposed Contract Documents.
Submission of a bid will be considered evidence that the Bidder is familiar with local facilities and difficulties,
requirements of the bidding documents and of pertinent State and local Codes, the state of labor and material markets
and has made due allowance in his bid for all contingencies. Submission of a bid will also be considered evidence
that the Bidder will supply a complete and full usable installation at the completion of the work without additional cost
to the Owner.
3.1.4 The Bid is based upon the materials, equipment and systems required by the Bidding Documents without
exception. See Substitutions
4.1.1 EXAMINATION AND DOWNLOAD OF ELECTRONIC DOCUMENTS: Plans and specifications may also be
viewed on the Architect’s website, www.MartinGardnerArch.com. Plans and specifications to be viewed are in Adobe
.pdf format and may be downloaded and printed. Be aware that no warranty as to the compatibility of your computer
software or hardware with the files provided is made. Variations between the printed files provided above by the
Architect and these electronic files may exist. In the event that a conflict does exist, the printed documents supplied by
the Architect will take precedence over the downloaded files. Persons accessing our documents on our website are
requested to provide contact information so that project Addenda may be directly transmitted to them and plan holders
list can be accurately maintained. The Architect will not be responsible to provide Addenda or other information to
parties who fail to properly register their contact information on the website.
4.2. EXAMINATION OF PRINTED DOCUMENTS: Documents may be viewed at the locations shown in Section
1.5.
4.2.1 PROCUREMENT OF PRINTED DOCUMENTS: Bidders and Sub-bidders may obtain complete sets of the Bidding
Documents from the Marion office of the Architect. Two sets of plans and specifications will be issued to Prime
Contractors and one set of plans and specifications will be issued to other Sub-bidders including Subcontractors and
Suppliers
4.2.3 DEPOSIT REFUND: Deposits will be refunded upon return of the Plans and Specifications to the office of the
Architect in good condition within 14 days of the bid opening. Deposits for Documents not returned by that date will
be used to replace the missing documents which are to be used during construction. Prime Bidders who are awarded
the project may retain their Documents and the deposit will be returned to them. All Sub-bidders are to return their
plans for deposit refund unless the Bidder issues a confirmation that the Sub-bidder will be awarded work on the
project.
4.3 PROCUREMENT OF DOCUMENTS FROM OTHER SOURCES: Neither the Owner, Architect, nor Architect’s
Consultants will be responsible for the content nor completeness of Bidding Documents obtained from sources other than
the office of the Architect. Contractors using printed or electronic plan rooms including those listed above should verify
with their sources that all documents, including addenda are included in the materials.
4.4 PARTIAL DOCUMENT SETS: Bidders shall use complete sets of Bidding Documents in preparing Bids; neither the
Owner, Architect, or Architect’s Consultants assumes responsibility for omissions, errors or misinterpretations resulting
from the use of incomplete sets of Bidding Documents. No partial sets of documents will be issued.
5.1 TERMS OF USE: The Owner and Architect make copies of the Bidding Documents available on the above terms for
the purpose of obtaining Bids on the Work. No license or grant of use is conferred by issuance of copies of the Bidding
Documents.
5.2 DOCUMENT QUESTIONS: The Bidder shall carefully study and compare the Bidding Documents with each other,
and with other work being bid concurrently or presently under construction to the extent that it relates to the Work for
which the Bid is submitted, shall examine the site and local conditions, and shall at once report to the Architect items
which the Bidder or Sub-bidder believe to be errors, inconsistencies or ambiguities discovered.
5.2.1 BUILDING CODE ISSUES: Bidders and Sub-bidders are not required to perform building code reviews, but items
which are believed to be in conflict with local codes or interpretations of the Authorities Having Jurisdiction over the
project, shall be brought to the Architect’s attention for clarification.
5.3 DOCUMENT CLARIFICATIONS: Bidders and Sub-bidders requiring clarification or interpretation of the Bidding
Documents shall make an inquiry to the Architect as soon as items are encountered. Inquiries will be accepted verbally,
in person, via telephone or written request via email, fax, or mail. Written inquiries will typically be addressed with the
highest priority. Inquiries must be made at least three (3) business days before the receipt of bids to allow time for
addenda to be generated and transmitted via mail to all bidders. Bidders who provide email addresses will receive
email notification of addenda in addition to mailed copies. Inquiries received after this time of a procedural nature will
be answered but no changes in the Bidding Documents will be allowed.
5.4 DOCUMENT CHANGES: Interpretations, corrections and changes to the Bidding Documents will be made by
Addendum. Interpretations, corrections and changes of the Bidding Documents made in any other manner will not be
binding, and Bidders shall not rely upon them. Contractors are encouraged to speak with the Architect, but should be
aware that answers to questions cannot be considered final until thoroughly researched and properly documented in an
Addendum.
ARTICLE 6 – ADDENDA
6.1 DISTRIBUTION: Addenda will be transmitted to all who are known by the issuing office to have received a
complete set of Bidding Documents or who have registered at the Architect’s web site when the electronic plans were
accessed. Bidders who provide email addresses to the Architect will receive email notification in addition to mailed
notification.
6.2 AVAILABILITY: Copies of Addenda will be made available for inspection wherever Bidding Documents are on file
for that purpose, including the Architect’s website. Copies of Addenda may be obtained from the Architect’s office
without additional charge to plan holders and suppliers. Copies of Addenda will be emailed to Bidders who have
provided the Architect with email addresses.
6.3 DATE OF ISSUE: So that all Bidders have access to mailed documents, Addenda will be issued no later than three
business days prior to the date for receipt of Bids except an Addendum withdrawing the request for Bids or one which
includes postponement of the date for receipt of Bids.
6.4 VERIFICATION OF ADDENDA: Each Bidder shall ascertain prior to submitting a Bid that the Bidder has received all
Addenda issued, and the Bidder shall acknowledge their receipt in the Bid. Verification of such information may be
made at the Architect’s website, www.MartinGardnerArch.com.
ARTICLE 7 – SUBSTITUTIONS
7.1 SPECIFIED MATERIALS: The materials, products and equipment described in the Bidding Documents establish a
standard of required function, dimension, appearance and quality to be met by any proposed substitution. Unless
otherwise approved by Addendum, the Bidders and Sub-bidders shall submit a Base Bid and Alternates that include the
materials and/or equipment items of manufacturers as listed in Construction Documents, plans and specifications.
7.2 REQUEST FOR SUBSTITUTION: No substitution will be considered prior to receipt of Bids unless written request for
approval has been received by the Architect at least five (5) days prior to the date for receipt of Bids.
7.2.1 FORM OF SUBSTITUTION REQUEST: Preferred Form of Request CSI 1.5C. Such requests shall include the name
of the material or equipment for which it is to be substituted and a complete description of the proposed substitution
including drawings, performance and test data, and other information necessary for an evaluation. A statement setting
forth changes in other materials, equipment or other portions of the Work, including changes in the work of other
contracts that incorporation of the proposed substitution would require, shall be included. The burden of proof of the
merit of the proposed substitution is upon the proposer. The Architect's decision of approval or disapproval of a
proposed substitution shall be final.
A. If the Architect approves a proposed substitution prior to receipt of Bids, such approval will be set forth in an
Addendum. Bidders shall not rely upon approvals made in any other manner.
B. No substitutions will be considered after the Contract award unless specifically provided for in the Contract
Documents.
8.2.1 BID SECURITY: Each separate proposal shall be accompanied by a bid bond, certified or cashier’s check or a
credit union certified share draft in a separate envelope equal to five percent (5%) of the total amount of the proposal.
Bid Security, if in the form of a bid bond, must be in the form of AIA A310-2010 Bid Bond. Submit Bid Security in a
separate envelope as noted below.
8.3.1 All copies of the Bid, the bid security, if any, and any other documents required to be submitted with the Bid shall
be enclosed in opaque envelopes and assembled as noted in 8.1.3 above.
8.3.2 VERIFICATION OF TIME OF SUBMITTAL: Iowa Public bidding laws require timely submission of bids. Bids shall
be deposited at the designated location prior to the time and date for receipt of Bids. Bids received after the time and
date for receipt of Bids will be returned unopened. Where a time stamp is available it shall be used to show proof of
timely submission, the time shown by the stamp will be final. Where times are affixed manually, the time shall be
determined by mobile phone and the time of submission noted on the bid.
8.3.3 RESPONSIBILITY FOR DELIVERY OF BIDS: The Bidder shall assume full responsibility for timely delivery at the
location designated for receipt of Bids. Failure of the US Mail or other service to make delivery on time is not
acceptable.
8.3.4 BID MEDIUM: All bids must be submitted in written form. Oral, telephonic, telegraphic, and facsimile or other
electronically transmitted bids will not be considered.
8.4.2 BID WITHDRAWAL: The Bidder may withdraw his bid from consideration after the deadline for submittal and
after the opening of the bids provided that the Owner has not formally accepted the bids. Once the bid has been
formally accepted by the Owner, withdrawal of the bid requires forfeiture of the Bid Security.
8.5 OPENING OF BIDS: Bids for this project will be opened at the date and time noted in Article 1 above. All
properly prepared bids will be read aloud as they are opened. Bids not accompanied by a Bid Security and
completed DBE form will be returned unopened. Bids to public agencies will be tabulated and the results of all bids will
be made available to all Bidders.
9.1.2 USE OF INFORMATION DURING BIDDING: These unit prices may be used for comparison purposes to
determine if the Bid of the apparent low Bidder is in the best interests of the Owner. Bidders who fail to submit this
form by the deadline may be disqualified from the project.
9.1.3 USE OF THE INFORMATION DURING CONSTRUCTION: The prices provided on this form are to be used for
addition or deletion of Work for the items indicated on the form. Unless otherwise directed, these costs are to be used
to compute the additional cost or savings when the project scope of work is modified. The Owner reserves the right to
request recomputation of proposed costs where significant quantities of material are involved in the change.
9.2 CONTRACTOR'S QUALIFICATION STATEMENT Bidders to whom award of a Contract is under consideration may
be requested to submit a properly executed AIA Document A305, Contractor's Qualification Statement.
9.2.1 OWNER'S FINANCIAL CAPABILITY
The Owner shall, at the request of the Bidder to whom award of a Contract is under consideration and no later than
seven days prior to the expiration of the time for withdrawal of Bids, furnish to the Bidder reasonable evidence that
financial arrangements have been made to fulfill the Owner's obligations under the Contract. Unless such reasonable
evidence is furnished, the Bidder will not be required to execute the Agreement between the Owner and Contractor.
9.3.1 PROJECT MANAGER AND PROJECT SUPERINTENDENT RESUMES FOR BUILDING CONSTRUCTION
CONTRACT:
.1 To be submitted within 24 hours of the opening of bids by the apparent low Prime Contractors. In the
case of close bids the Architect may request additional contractors to submit this form for further
evaluation.
.2 Resumes shall demonstrate education and experience requirements shown in Section 00800.1.3.
9.3.2 Contractors who fail to submit this proposal by the time requested or whose personnel qualifications fail to meet
the required standards may be disqualified.
9.3.4 SUBMITTAL OF ADDITIONAL ITEMS FOR ALL CONTRACTS: Prior to execution of the final contract for
construction the following items will be required to be submitted.
.1 PROOF OF INSURANCE
.3 SCHEDULE OF PROJECT VALUES
.4 LIST OF SUBCONTRACTORS AND SUPPLIERS.
9.3.5 LIST OF SUBCONTRACTORS AND SUPPLIERS FOR BUILDING CONSTRUCTION CONTRACT: The Bidder shall,
as soon as practicable or as stipulated in the Bidding Documents, after notification of selection for the award of a
Contract, furnish to the Owner through the Architect in writing:
.1 a designation of the Work to be performed with the Bidder's own forces;
.2 names of the manufacturers, products, and the suppliers of principal items or systems of materials and
equipment proposed for the Work; and
.3 names of persons or entities (including those who are to furnish materials or equipment fabricated to a
special design) proposed for the principal portions of the Work.
9.3.6 QUALIFICATIONS OF THE CONSTRUCTION TEAM: The Bidder will be required to establish to the satisfaction of
the Architect and Owner the reliability and responsibility of the persons or entities proposed in the list of subcontractors
and suppliers to furnish and perform the Work described in the Bidding Documents.
9.3.7 REJECTION OF SUBCONTRACTORS OR SUPPLIERS: Prior to the execution of the Contract, the Architect will
notify the Bidder in writing if either the Owner or Architect, after due investigation, has reasonable objection to a
person or entity proposed by the Bidder. If the Owner or Architect has reasonable objection to a proposed person or
entity, the Bidder may, at the Bidder's option, (1) withdraw the Bid or (2) submit an acceptable substitute person or
entity with an adjustment in the Base Bid or Alternate Bid to cover the difference in cost occasioned by such substitution.
The Owner may accept the adjusted bid price or disqualify the Bidder. In the event of either withdrawal or
disqualification, bid security will not be forfeited.
9.3.8 USE OF SPECIFIED ENTITIES: Persons and entities proposed by the Bidder and to whom the Owner and Architect
have made no reasonable objection must be used on the Work for which they were proposed and shall not be
changed except with the written consent of the Owner and Architect.
END OF SECTION
PART 1 - GENERAL
1.1 GENERAL
A. The "General Conditions of the Contract for Construction, "AIA Document A201-2017, Articles 1
through 15 inclusive, is a part of ALL CONTRACTS FOR THIS PROJECT and is bound herein.
B. The following supplements modify, change, delete from or add to the "General Conditions of the
Contract for Construction, "AIA Document A201-2017”. Where any Article of the General Conditions
is modified or any Paragraph, Subparagraph or Clause thereof is modified or deleted by these
Supplementary Conditions, the unaltered provisions of that Article, Paragraph, Subparagraph or Clause
shall remain in effect.
3.9.2 Project Manager: The Contractor shall employ a competent Project Manager who shall attend all
project meetings, shall be responsible for review and processing of all shop drawings, shall have
authority to direct the Superintendent, Subcontractors, and Suppliers, and shall be the primary point of
contact for all contract matters on the project. The Project Manager may have assistants as required for
the project. The Project Manager shall be in fiscal and time schedule control of the Project. The Project
Manager may manage more than one project at a time provided that service to this project is provided
in a timely manner. Project managers must be experienced in construction with experience in contracts,
scheduling, and related on site experience. Project managers shall have a minimum of five years as a
project superintendent or five years as a project manager or be able to demonstrate broad construction
experience and knowledge over a long period of time that has prepared the individual for management
of the project.
3.9.3 Superintendent: The superintendent shall be considered to be a project foreman who is at the site
and involved in the project as note below. Superintendents are considered a part of the project work
force and shall in addition to supervisory functions provide skilled construction work. Inquiries and
questions at the jobsite shall be first directed to the superintendent. Only upon his direction shall
questions from the jobsite be directed to the Architect. The superintendent shall coordinate onsite
construction activities with the Owner when needed to facilitate construction or resolve onsite
construction conflicts including when the Owner is occupying the building, providing part of the
building labor or materials, or has separate Contractors working on the project. Questions regarding
construction documents, which are not clearly apparent to the superintendent shall be directed to the
Architect for interpretation. As a minimum Superintendents shall have five years of successful
experience as a lead framing carpenter and three years or five projects as a project superintendent or
be able to demonstrate broad construction experience and knowledge over a long period of time that
has prepared the individual for management of the project.
3.9.4 Submittal of Qualifications (Applies only to Building Construction Contract): The Contractor, as
soon as practical after the award of the Contract, but prior to formal acceptance of the Contractor's
proposal by the Owner, shall furnish in writing to the Owner through the Architect the name and
qualifications of the proposed Project Manager and Superintendent. The Architect may reply within 14
days to the Contractor in writing stating (1) whether the Owner or Architect has reasonable objection to
the proposed Project Manager or Superintendent or (2) that the Architect requires additional information
or time to review. Upon notice that a candidate is not acceptable the Contractor shall submit the name
and qualifications of alternate personnel or withdraw their proposal for the project. If no written
objection is filed within 14 days the Contractor's selection shall be considered acceptable. The
Contractor shall not employ on this project any Project Manager or Superintendent to whom the Owner
or Architect has made reasonable and timely objection.
3.9.5 Change in Personnel: The Superintendent and Project Manager shall be assigned to the project
for the duration of the project, and shall be replaced on the project only if dismissed from employment
with the construction company, has an illness that would require long absences from the work site, is
requested to be removed by the Owner and Architect \, or upon request by the General Contractor for
approval of the Owner and Architect. Any change in the Superintendent or Project Manager on the
project shall be requested by the Contractor in writing at least two weeks prior to the change and shall
be approved by the Architect and Owner in writing prior to any change. Any of the following will be
deemed to be a failure to pursue the project in a timely manner and will be pursued according to
Article 1.07 below or other provisions of the General Conditions as may be appropriate.
1. Absence from the project by the Superintendent at critical times in the project or when the
construction trades are working at the site.
2. Reassignment of the Superintendent to other projects where the Superintendent is required to
be full-time,
3. Repeated failure of the Superintendent or Project Manager to respond in a timely manner to
inquiries from the Owner, Subcontractors, Suppliers, or the Architect
4. Repeated failure of the Superintendent or Project Manager to attend project meetings”
END OF SECTION
1.1 DEFINITIONS
A. Procurement Substitution Requests: Requests for changes in products, materials, equipment, and methods of
construction from those indicated in the Procurement and Contracting Documents, submitted prior to receipt of
bids.
B. Substitution Requests: Requests for changes in products, materials, equipment, and methods of construction
from those indicated in the Contract Documents, submitted following Contract award. See Section 012500
"Substitution Procedures" for conditions under which Substitution requests will be considered following
Contract award.
1.4 SUBMITTALS
A. Procurement Substitution Request: Submit to Architect. Procurement Substitution Request must be made in
writing in compliance with the following requirements:
1. Requests for substitution of materials and equipment will be considered if received no later than 5 days
prior to date of bid opening.
Submittal Format: Submit three (3) copies of each written Procurement Substitution Request, or one (1)
electronic copy using CSI Substitution Request Form 1.5C.
2. Submittal Format: Submit Procurement Substitution Request, using format provided on Project Web site.
a. Identify the product or the fabrication or installation method to be replaced in each request.
Include related Specifications Sections and drawing numbers.
b. Provide complete documentation on both the product specified and the proposed substitute,
including the following information as appropriate:
1) Point-by-point comparison of specified and proposed substitute product data, fabrication
drawings, and installation procedures.
2) Copies of current, independent third-party test data of salient product or system
characteristics.
3) Samples where applicable or when requested by Architect.
4) Detailed comparison of significant qualities of the proposed substitute with those of the
Work specified. Significant qualities may include attributes such as performance,
weight, size, durability, visual effect, sustainable design characteristics, warranties, and
specific features and requirements indicated. Indicate deviations, if any, from the Work
specified.
5) Material test reports from a qualified testing agency indicating and interpreting test
results for compliance with requirements indicated.
6) Research reports, where applicable, evidencing compliance with building code in effect
for Project, from ICC-ES (International Code Council Evaluation Service) or other code
compliance agency.
7) Coordination information, including a list of changes or modifications needed to other
parts of the Work and to construction performed by Owner and separate contractors,
which will become necessary to accommodate the proposed substitute.
8) List of similar installations for completed projects with project names, addresses and
names of addresses for architects and owners who will act a reference as to the
performance of the product.
c. Provide certification by manufacturer that the substitute proposed is equal to or superior to that
required by the Procurement and Contracting Documents, and that its in-place performance will
be equal to or superior to the product or equipment specified in the application indicated.
d. Bidder, in submitting the Procurement Substitution Request, waives the right to additional
payment or an extension of Contract Time because of the failure of the substitute to perform as
represented in the Procurement Substitution Request.
B. Architect's Action:
1. Architect may request additional information or documentation necessary for evaluation of the
Procurement Substitution Request. Architect will notify all bidders of acceptance of the proposed
substitute by means of an Addendum to the Procurement and Contracting Documents.
C. Architect's approval of a substitute during bidding does not relieve Contractor of the responsibility to submit
required shop drawings and to comply with all other requirements of the Contract Documents.
END OF SECTION
DATE: _____________________________
ARCHITECT’S PROJECT NO: I0601.04
The proposed project consists of demolition of the old Plainfield Middle School building including footing,
foundations, and paving, terminating and capping utilities, and filling demolition site.
CERTIFICATIONS Base Bid, Single-Prime (All Trades) Contract: The undersigned Bidder, having carefully examined the
Procurement and Contracting Requirements, Conditions of the Contract, Drawings, Specifications, and all subsequent
Addenda, as prepared by Martin Gardner Architecture and the Architect's consultants, having visited the site, and
being familiar with all conditions and requirements of the Work, hereby agrees to furnish all material, labor, equipment
and services, including all scheduled allowances, necessary to complete the construction of the above-named project,
according to the requirements of the Procurement and Contracting Documents, for the stipulated sum of:
The undersigned, having examined the contract documents and having familiarized himself with the nature of the work
to be done and the conditions under which the work will be performed, in accordance with the drawings and
specifications proposes to provide the required labor, services, materials and equipment, and to perform the work
required for completion of the project at the price set forth hereafter.
ACKNOWLEDGEMENT OF ADDENDA: The undersigned Bidder acknowledges receipt of and use of the following
Addenda in the preparation of this Bid:
Addendum No. 1, dated ____________________.
Addendum No. 2, dated ____________________.
Base Bid:
____________________________________________________________($______________________________________)
Alternate Bid A-1: Remove remaining south parking lot paving, regrade and seed as described on the construction
drawings.
____________________________________________________________($______________________________________)
Commencement Date: Commencement of construction will be contingent upon the Owner giving a Written Notice
to Proceed.
Completion Dates: Contractor shall achieve Substantial Completion for this project as described in Section 002113
– Instructions to Bidders.
The undersigned bidder states that this proposal is made in conformity with contract documents and agrees that, in the
event of any discrepancies or differences between any condition of his proposal and the contract documents prepared
by Martin Gardner Architecture, P.C., Kyle D. Martin, A.I.A., the provisions of the latter shall prevail.
The contractor in submitting this proposal agrees that the above schedule is acceptable and that he has made all
provisions in his proposal to deliver the project by the above date provided the Owner accepts the above proposal or
combination of proposals and submits to the contractor a Notice to Proceed or a contract for construction within forty-
five (45) working days of the receipt of bids. If Notice to Proceed or the contract is received after forty-five (45) days
than that number of days shall be added to the above completion date.
All of the above to commence after receipt of either a written Notice to Proceed or the executed Agreement furnished
by the Owner, subject to factors which may delay, extend, suspend or terminate the work as set forth in the contract
documents.
The contractor hereby submits this proposal in an envelope marked with the project name and “Proposal”. In a
separate envelope accompanying the proposal shall be a Bid Bond as noted in the Instructions to Bidders. Mark this
envelope with the project name and “Bid Bond”
BY: ____________________________________________________
(Authorized Signature)
TITLE: __________________________________________________
A. Bidder: ____________________________________________________.
B. Project Name: Old Middle School Demolition
C. Project Location: 401 Main Street, Plainfield, Iowa
D. Owner: Nashua-Plainfield Community School District
E. Architect: Martin Gardner Architecture, P.C.
F. Architect Project Number: I0601.04
4 Attached to the Bid Form: Bid Bond OR a certified check for the amount required.
11 Verified that the Bidder can provide Certificates of Insurance in the amounts indicated.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section Includes:
1. Project information. Section 1.3
2. Work covered by Contract Documents. Section 1.4
3. Sequence of construction. Section 1.5
4. Work by Owner. Section 1.6
5. Work under separate contracts. Section 1.7
6. Future work. Section 1.8
7. Purchase contracts. Section 1.9
8. Owner-furnished products. Section 1.10
9. Access to site. Section 1.11
10. Condition of Existing Building or Condition of Site Section 1.12
11. Coordination with occupants. Section 1.12
12. Work restrictions. Section 1.13
13. Specification and drawing conventions. Section 1.14
14. Miscellaneous provisions. Section 1.15
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing
temporary use of Owner's facilities.
The proposed project consists of demolition of the old Plainfield Middle School building including footing,
foundations, and paving, terminating and capping utilities, and filling demolition site.
B. Type of Contract:
1. Project will be constructed under single prime contract
F. Employee Identification: All employees shall either wear a name badge identifying their name, company,
and company contact information.
G. Employee Screening: Not required.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for alternates.
1.3 DEFINITIONS
A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding
requirements that may be added to or deducted from the base bid amount if Owner decides to accept a
corresponding change either in the amount of construction to be completed or in the products, materials,
equipment, systems, or installation methods described in the Contract Documents.
1. Alternates described in this Section and on the Proposal Form are part of the Work only if enumerated
in the Construction Contract.
2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to
incorporate alternate into the Work. No other adjustments are made to the Contract Sum by the
inclusion or exclusion of an Alternate.
1.4 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the
alternate into Project. Include as part of each alternate, labor, material, miscellaneous devices, accessory
objects, and similar items incidental to or required for a complete installation whether or not indicated as part
of alternate.
B. Notification: Immediately following award of the Contract, notify each party involved, in writing, of the status
of each alternate. Indicate if alternates have been accepted, rejected, or deferred for later consideration.
Include a complete description of negotiated revisions to alternates.
C. Execute accepted alternates under the same conditions as other work of the Contract.
D. Timing: The Owner reserves the right to accept alternates bids up to 45 days after the bid date, which may
occur after the award of the base bid and execution of the contract. If the contract has been awarded, the
Owner reserves the right to modify the agreement within the timeframe indicated.
E. Schedule: A schedule of alternates is included on the Proposal Form Specification Sections referenced in
schedule contain requirements for materials necessary to achieve the work described under each alternate.
PART 3 - EXECUTION
SCHEDULE OF ALTERNATES:
A. Alternate A-1: Remove remaining south parking lot paving, regrade and seed as described on the construction
drawings.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 012100 "Allowances" for products selected under an allowance.
2. Section 012300 "Alternates" for products selected under an alternate.
3. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals
for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by
the Contract Documents and proposed by Contractor.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project
conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty
terms.
2. Contractor Substitutions for Convenience: Changes proposed by the Contractor that are not required
in order to meet other Project requirements but may offer time, ease the ordering process or offer other
advantages to Contractor
3. Contractor Substitutions for Cost: Changes proposed by the Contractor that are not required by the
project but will result in a cost reduction for the project.
4. Owner Substitutions for Convenience: Changes proposed by the Owner that are not required in order
to meet Project requirements but provide the Owner with a perceived better project condition or other
advantage.
5. Owner Substitutions for Cost: Changes proposed by the Owner strictly to reduce the project cost.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not
later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions
are satisfied. If the following conditions are not satisfied, Architect will return requests without action,
except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated
results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been
coordinated with other portions of the Work, is uniform and consistent, is compatible with other
products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Not allowed.
C. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after
commencement of the Work. Requests received after that time may be considered or rejected at discretion of
Architect.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions
are satisfied. If the following conditions are not satisfied, Architect will return requests without action,
except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation,
or other considerations, after deducting additional responsibilities Owner must assume.
Owner's additional responsibilities may include compensation to Architect for redesign and
evaluation services, increased cost of other construction by Owner, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated
results.
d. Substitution request is fully documented and properly submitted.
e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work.
h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been
coordinated with other portions of the Work, is uniform and consistent, is compatible with other
products, and is acceptable to all contractors involved.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract
modifications.
B. Related Requirements:
1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for
substitutions made after the Contract award.
total amount of purchases and credits to be made. If requested, furnish survey data to sub-
stantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include a statement outlining the affect the proposed change would have upon the construction
schedule or submit a revised schedule.
e. Quotation Form: Use forms acceptable to Architect.
8. The Architect will review the quotation and either request clarification from the Contractor or forward
the quotation to the Owner.
9. The Owner will make a determination as to whether the quotation will be accepted.
10. If accepted, the Architect will prepare the necessary notices or change order.
11. Submittal of a proposed change to the Contractor does not restrict the Owner’s right to conduct the
change in the work with their own forces or a separate Contractor.
12. Unless specifically approved advance all changes resulting in an increase in the project cost are to
be performed on a time and material basis using the estimate of costs as the maximum cost. All sav-
ings shall be maintained by the Owner. Work is to be performed on a time and material basis using
the estimate of cost as a maximum expense. The final cost shall be documented with labor records,
material breakdowns, and profit and overhead documented as separate costs.
B. Architect-Initiated Proposals: Should the Architect decide that a change in the Contract Documents or the
built construction is required, the following procedures shall be followed:
1. The Architect will issue a detailed description of proposed changes.
2. The Architect will make an initial determination as to if the proposed change will require a change in the
Contract Sum or Contract Time. The Architect may request initial information from the Owner or Contractor
to determine the scope and potential costs of the proposed change. The Architect will include Consultants in
this process whenever appropriate. Where appropriate, the Architect will provide to the Owner, the cost of
additional fees for the Architect and Consultants.
3. Methods for communication include but are not necessarily limited to Architect’s Information to Clarify,
Change Directive, or Field Directive.
4. Upon receipt of the request the Contractors shall promptly inform the Architect of any additional information
needed to properly address the proposed change.
5. Work Change Proposal Requests issued by the Architect are not instructions either to stop work in
progress or to execute the proposed change.
6. After the receipt of the Proposal Request, submit to the Architect within the time specified, a quotation
detailing cost adjustments to the Contract Sum and the Contract Time necessary to execute the
change.
a. Include a list of quantities of products and labor required or eliminated and unit costs, with
total amount of purchases and credits to be made. If requested, furnish survey data to sub-
stantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change,
including, but not limited to, changes in activity duration, start and finish times, and activity
relationship. Use available total float before requesting an extension of the Contract Time.
e. Quotation Form: Use forms acceptable to Architect.
7. The Architect will review the quotation and either request clarification from the Contractor or forward
the quotation to the Owner.
8. The Owner will make a determination as to whether the quotation will be accepted.
9. If accepted, the Architect will prepare the necessary notices or change order.
10. Submittal of a proposed change to the Contractor does not restrict the Owner’s right to conduct the
change in the work with their own forces or a separate Contractor.
11. Unless specifically approved advance all changes resulting in an increase in the project cost are to
be performed on a time and material basis using the estimate of costs as the maximum cost. All sav-
ings shall be maintained by the Owner. Work are to be performed on a time and material basis us-
ing the estimate of cost as a maximum expense.
The final cost shall be documented with labor records, material breakdowns, and profit and over-
head documented as separate costs.
C. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Con
tractor may initiate a claim by submitting a request to the Architect for a change to any part of the project.
1. Seek clarification of the construction documents to be certain that the proposed change is not already
included in the construction documents.
2. Include a statement outlining reasons for the change and the effect of the change on the Work. Pro-
vide a complete description of the proposed change. Indicate the effect of the proposed change on
the Contract Sum and the Contract Time.
3. Include a list of quantities of products and labor required or eliminated and unit costs, with total
amount of purchases and credits to be made. If requested, furnish survey data to substantiate quanti-
ties.
4. Overhead and profit charges by anyone contractor shall not exceed ten percent (10%) of the esti-
mated cost of labor and material estimates. Contractors may elect, with agreement of the Architect
and Owner, to charge project manager time to the change in lieu of an overhead and profit fee.
5. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
6. Include costs of labor and supervision directly attributable to the change.
7. Include an updated Contractor's construction schedule or written statement that indicates the effect of
the change, including, but not limited to, changes in activity duration, start and finish times, and ac-
tivity relationship. Use available total float before requesting an extension of the Contract Time. The
current schedule for completion of the project will be considered to remain in effect unless it is ad-
dressed with this submission.
8. Comply with requirements in Division 1 Section "Substitution Procedures" if the proposed change
requires substitution of one product or system for product or system specified.
9. Submit the request to the Architect. The Architect will review and request additional information if
needed to clarify the request.
10. The Architect may determine that the request is unwarranted or propose an alternate method of re-
solving the issue.
11. The Architect will present the request to the Owner for review.
12. If accepted by the Owner, a change order will be issued by the Architect.
13. Unless specifically approved advance all changes resulting in an increase in the project cost are to
be performed on a time and material basis using the estimate of costs as the maximum cost. All sav-
ings shall be maintained by the Owner. Work is to be performed on a time and material basis using
the estimate of cost as a maximum expense. The final cost shall be documented with labor records,
material breakdowns, and profit and overhead documented as separate costs.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications
for Payment.
B. Related Requirements:
1. Section 012600 "Contract Modification Procedures" for administrative procedures for handling
changes to the Contract.
2. Section 013200 "Construction Progress Documentation" for administrative requirements governing the
preparation and submittal of the Contractor's construction schedule.
1.3 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various
portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent
stage of completion, and for total installed value of that part of the Work.
8. Each item in the schedule of values and Applications for Payment shall be complete. Include total cost
and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place
may be shown either as separate line items in the schedule of values or distributed as general
overhead expense, at Contractor's option.
9. Schedule Updating: Update and resubmit the schedule of values before the next Applications for
Payment when Change Orders or Construction Change Directives result in a change in the Contract
Sum.
F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect
by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments
if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information
about application.
G. Waivers of Mechanic's Lien: at the end of the project, submit waivers of mechanic's lien from entities lawfully
entitled to file a mechanic's lien arising out of the Contract and related to the Work.
H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with
submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Contractor's construction schedule.
4. List of Contractor's staff assignments.
I. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial
Completion, submit an Application for Payment showing 100 percent completion for portion of the Work
claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement
showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner
occupancy of designated portions of the Work.
J. Final Payment Application: After completing Project closeout requirements, submit final Application for
Payment with releases and supporting documentation not previously submitted and accepted, including, but
not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Updated final statement, accounting for final changes to the Contract Sum.
3. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."
4. AIA Document G706A, "Contractor's Affidavit of Release of Liens."
5. Evidence that claims have been settled.
6. Final liquidated damages settlement statement.
K. Payments to the Contractor will be made in accordance with the schedule outlined in the Contract for
Construction. Payments by cities, counties, school boards, and agencies governed by a board of directors
will be paid within 15 days of the date of the next legal board meeting provided that the board of directors
agrees to make payment on the Contract. Should the board of directors have issue with the amount
END OF SECTION
PART 1-GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications
for Payment.
B. Related Requirements:
1. Division 1 Section "Contract Modification Procedures" for administrative procedures for handling
changes to the Contract.
2. Division 1 Section "Unit Prices" for administrative requirements governing the use of unit prices.
3. Division 1 Section "Construction Progress Documentation" for administrative requirements
governing the preparation and submittal of Contractor's construction schedule.
4. Provide separate line items in the schedule of values for initial cost of materials, for each
subsequent stage of completion, and for total installed value of that part of the Work.
5. Each item in the schedule of values and Application for Payment shall be complete. Include
total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual
work-in- place may be shown either as separate line items in the schedule of
values or distributed as general overhead expense, at Contractor's option.
6. Schedule Updating: Update and resubmit the Schedule of Values before the next
Application for Payment when Change Orders or Construction Change Directives result in a
change in the Contract Sum.
B. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's
construction schedule.
1. Coordinate line items in the Schedule of Values with other required administrative forms and
schedules, including the following:
a. Application for Payment forms with continuation sheets.
b. Submittal schedule.
c. Items required to be indicated as separate activities in Contractor's construction
schedule.
2. Submit the initial schedule of values to Architect at earliest possible date, but no later than
seven days after notification of the award of the contract.
3. Sub-schedules for Separate Elements of Work: Where the Contractor's construction
schedule defines separate elements of the work, provide sub-schedules showing values
coordinated with each element.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but
not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. Requests for Information (RFIs).
4. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to
a specific contractor.
C. Related Requirements:
1. Section 011200 "Multiple Contract Summary" for a description of the division of work among separate
contracts and responsibility for coordination activities not in this Section.
2. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's
construction schedule.
3. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering
services, including establishment of benchmarks and control points.
4. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. RFI: Request from Owner, Architect, or Contractor seeking information required by or clarifications of the
Contract Documents.
2. Coordinate installation of different components to ensure maximum performance and accessibility for
required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and
entities to ensure efficient and orderly installation of each part of the Work. Each contractor shall coordinate
its operations with operations, included in different Sections, that depend on each other for proper installation,
connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of
one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum performance
and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for
coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is
required.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other
construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative
activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
E. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration
given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the
Work. See other Sections for disposition of salvaged materials that are designated as Owner's
property.
2. Architect's action may include a request for additional information, in which case Architect's time for
response will date from time of receipt of additional information.
3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be
eligible for Contractor to submit Change Proposal according to Section 012600 "Contract
Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract
Sum, notify Architect in writing within 10 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected
parties. Review response and notify Architect within seven days if Contractor disagrees with response.
1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal
Request, as appropriate.
2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for
acceptance.
c. Submittal of written warranties.
d. Requirements for preparing operations and maintenance data.
e. Preparation of Contractor's punch list.
f. Procedures for processing Applications for Payment at Substantial Completion and for final
payment.
g. Submittal procedures.
h. Coordination of separate contracts.
i. Responsibility for removing temporary facilities and controls.
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
E. Progress Meetings: Conduct] progress meetings at monthly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor,
supplier, and other entity concerned with current progress or involved in planning, coordination, or
performance of future activities shall be represented at these meetings. All participants at the meeting
shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of
significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether
each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's
construction schedule. Determine how construction behind schedule will be expedited; secure
commitments from parties involved to do so. Discuss whether schedule revisions are required to
ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Status of submittals.
4) Deliveries.
5) Off-site fabrication.
6) Access.
7) Site utilization.
8) Temporary facilities and controls.
9) Progress cleaning.
10) Quality and work standards.
11) Status of correction of deficient items.
12) Field observations.
13) Status of RFIs.
14) Status of proposal requests.
15) Pending changes.
16) Status of Change Orders.
17) Pending claims and disputes.
18) Documentation of information for payment requests.
4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes
to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting
where revisions to the schedule have been made or recognized. Issue revised schedule
concurrently with the report of each meeting.
F. Coordination Meetings: Conduct Project coordination meetings at regular intervals. Project coordination
meetings are in addition to specific meetings held for other purposes, such as progress meetings and
preinstallation conferences.
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction
during performance of the Work, including the following:
1. Startup construction schedule.
2. Contractor's construction schedule.
3. Construction schedule updating reports.
4. Daily construction reports.
5. Material location reports.
6. Site condition reports.
7. Special reports.
B. Related Requirements:
1. Section 013300 "Submittal Procedures" for submitting schedules and reports.
2. Section 014000 "Quality Requirements" for submitting a schedule of tests and inspections.
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling
the construction project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and
finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the schedule of values for the completion of an activity as scheduled. The sum
of costs for all activities must equal the total Contract Sum unless otherwise approved by Architect.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where
activities are arranged based on activity relationships. Network calculations determine when activities can be
performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that
establishes the minimum overall Project duration and contains no float.
E. Event: The starting or ending point of an activity.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as
scheduled.
1.6 COORDINATION
A. Coordinate Contractor's construction schedule with the schedule of values, list of multiple contracts, submittal
schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper
sequence.
PART 2 - PRODUCTS
3. Work by Owner: Include a separate activity for each portion of the Work performed by Owner.
4. Products Ordered in Advance: Include a separate activity for each product. Include delivery date
indicated in Section 011000 "Summary." Delivery dates indicated stipulate the earliest possible
delivery date.
5. Owner-Furnished Products: Include a separate activity for each product. Include delivery date indicated
in Section 011000 "Summary." Delivery dates indicated stipulate the earliest possible delivery date.
6. Work Restrictions: Show the effect of the following items on the schedule:
a. Coordination with existing construction.
b. Limitations of continued occupancies.
c. Uninterruptible services.
d. Partial occupancy before Substantial Completion.
e. Use of premises restrictions.
f. Provisions for future construction.
g. Seasonal variations.
h. Environmental control.
7. Work Stages: Indicate important stages of construction for each major portion of the Work, including,
but not limited to, the following:
a. Subcontract awards.
b. Submittals.
c. Purchases.
d. Sample testing.
e. Deliveries.
f. Tests and inspections.
D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to,
the Notice to Proceed, Substantial Completion, and final completion, and the following interim milestones:
1. Temporary enclosure and space conditioning.
E. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence
prior to submittal of next schedule update. Summarize the following issues:
1. Unresolved issues.
2. Unanswered Requests for Information.
3. Rejected or unreturned submittals.
4. Notations on returned submittals.
5. Pending modifications affecting the Work and Contract Time.
F. Recovery Schedule: When periodic update indicates the Work is 14 or more calendar days behind the current
approved schedule, submit a separate recovery schedule indicating means by which Contractor intends to
regain compliance with the schedule. Indicate changes to working hours, working days, crew sizes, and
equipment required to achieve compliance, and date by which recovery will be accomplished.
G. Computer Scheduling Software: Prepare schedules using current version of a program that has been developed
specifically to manage construction schedules.
B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with
a continuous vertical line.
1. For construction activities that require three months or longer to complete, indicate an estimated
completion percentage in 10 percent increments within time bar.
2.4 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning
events at Project site:
1. List of subcontractors at Project site.
2. List of separate contractors at Project site.
3. Approximate count of personnel at Project site.
4. Equipment at Project site.
5. Material deliveries.
6. High and low temperatures and general weather conditions, including presence of rain or snow.
7. Accidents.
8. Meetings and significant decisions.
9. Unusual events (see special reports).
10. Stoppages, delays, shortages, and losses.
11. Meter readings and similar recordings.
12. Emergency procedures.
13. Orders and requests of authorities having jurisdiction.
14. Change Orders received and implemented.
15. Construction Change Directives received and implemented.
16. Services connected and disconnected.
17. Equipment or system tests and startups.
18. Partial completions and occupancies.
19. Substantial Completions authorized.
B. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract
Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed
description of the differing conditions, together with recommendations for changing the Contract Documents.
PART 3 - EXECUTION
END OF SECTION
PART 1 – GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for the following:
1. Preconstruction photographs.
2. Periodic construction photographs.
3. Final completion construction photographs.
4. Photographs to document additional work.
5. Photographs to document quantities for unit pricing.
6. Photographs to document quantities for allowances
B. Related Requirements:
1. Division 1 Section "Submittal Procedures" for submitting photographic documentation.
2. Division 1 Section "Closeout Procedures" for submitting photographic documentation as project
record documents at Project closeout.
3. Division 1 Section "Demonstration and Training" for submitting video recordings of demonstration of
equipment and training of Owner's personnel.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes requirements for the submittal schedule and administrative and procedural requirements for
submitting Shop Drawings, Product Data, Samples, and other submittals.
B. Related Requirements:
1. Section 012900 "Payment Procedures" for submitting Applications for Payment and the schedule of
values.
2. Section 013200 "Construction Progress Documentation" for submitting schedules and reports,
including Contractor's construction schedule.
3. Section 017823 "Operation and Maintenance Data" for submitting operation and maintenance
manuals.
4. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications,
and record Product Data.
5. Section 017900 "Demonstration and Training" for submitting video recordings of demonstration of
equipment and training of Owner's personnel.
1.3 DEFINITIONS
A. Action Submittals: Written and graphic information and physical samples that require Architect's responsive
action. Action submittals are those submittals indicated in individual Specification Sections as "action
submittals."
B. Informational Submittals: Written and graphic information and physical samples that do not require Architect's
responsive action. Submittals may be rejected for not complying with requirements. Informational submittals
are those submittals indicated in individual Specification Sections as "informational submittals."
C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another
computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion
of a network located outside of network firewalls within which internal and external users are able to access
files.
D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for
representing documents in a device-independent and display resolution-independent fixed-layout document
format.
c. Name of Architect.
d. Name of Contractor.
e. Name of subcontractor.
f. Name of supplier.
g. Name of manufacturer.
h. Submittal number or other unique identifier, including revision identifier. Submittal number shall
use Specification Section number followed by a decimal point and then a sequential number
(e.g., 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point
(e.g., 061000.01.A).
i. Number and title of appropriate Specification Section.
j. Drawing number and detail references, as appropriate.
k. Location(s) where product is to be installed, as appropriate.
l. Other necessary identification.
4. Additional Paper Copies: Unless additional copies are required for final submittal, and unless Architect
observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final
submittal. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies
to Architect.
5. Transmittal for Paper Submittals: Assemble each submittal individually and appropriately for transmittal
and handling. Transmit each submittal using a separate transmittal form. Architect will return without
review submittals received from sources other than Contractor.
a. Transmittal Form for Paper Submittals: Provide the following information where applicable
1) Project name.
2) Date.
3) Destination (To:).
4) Source (From:).
5) Name and address of Architect.
6) Name of Contractor.
7) Name of firm or entity that prepared submittal along with name, telephone and email
contact information of the preparer.
8) Names of subcontractor, manufacturer, and supplier.
9) Category and type of submittal.
10) Submittal purpose and description.
11) Specification Section number and title.
12) Specification paragraph number or drawing designation and generic name for each of
multiple items.
13) Drawing number and detail references, as appropriate.
14) Indication of full or partial submittal.
15) Remarks.
16) Signature of transmitter.
E. Electronic Submittals: Electronic submittals are the preferred means of delivery for most items for this project,
unless noted otherwise in the individual submittal requirements sections. Contractors Identify and incorporate
information in each electronic submittal file as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements
of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier. File name shall
use project identifier and Specification Section number followed by a decimal point and then a
sequential number (e.g., LNHS-061000.01). Resubmittals shall include an alphabetic suffix after
another decimal point (e.g., LNHS-061000.01.A).
3. Provide means for insertion to permanently record Contractor's review and approval markings and
action taken by Architect.
4. Transmittal for Electronic Submittals: Assemble each submittal individually and appropriately for
transmittal and handling. Transmit each submittal using a separate transmittal form. Architect will return
without review submittals received from sources other than Contractor.
a. Transmittal Form for Paper Submittals: Provide the following information where applicable
1) Project name.
2) Date.
3) Destination (To:).
4) Source (From:).
5) Name and address of Architect.
6) Name of Contractor.
7) Name of firm or entity that prepared submittal along with name, telephone and email
contact information of the preparer.
8) Names of subcontractor, manufacturer, and supplier.
9) Category and type of submittal.
10) Submittal purpose and description.
11) Specification Section number and title.
12) Specification paragraph number or drawing designation and generic name for each of
multiple items.
13) Drawing number and detail references, as appropriate.
14) Indication of full or partial submittal.
15) Remarks.
16) Signature of transmitter.
F. Options: Identify options requiring selection by Architect.
G. Deviations and Additional Information: On an attached separate sheet, prepared on Contractor's letterhead,
record relevant information, requests for data, revisions other than those requested by Architect on previous
submittals, and deviations from requirements in the Contract Documents, including minor variations and
limitations. Include same identification information as related submittal.
H. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked with approval notation from Architect's action stamp.
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators,
installers, authorities having jurisdiction, and others as necessary for performance of construction activities.
Show distribution on transmittal forms.
J. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that
are marked with approval notation from Architect's action stamp.
PART 2 - PRODUCTS
a. Provide a digital signature with digital certificate on electronically submitted certificates and
certifications where indicated.
b. Provide a notarized statement on original paper copy certificates and certifications where
indicated.
B. Product Data: Collect information into a single submittal for each element of construction and type of product
or equipment.
1. If information must be specially prepared for submittal because standard published data are not
suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's catalog cuts.
b. Manufacturer's product specifications.
c. Standard color charts.
d. Statement of compliance with specified referenced standards.
e. Testing by recognized testing agency.
f. Application of testing agency labels and seals.
g. Notation of coordination requirements.
h. Availability and delivery time information.
4. For equipment, include the following in addition to the above, as applicable:
a. Wiring diagrams showing factory-installed wiring where requested.
b. Printed performance curves where requested..
c. Operational range diagrams where requested.
d. Clearances required to other construction, if not indicated on accompanying Shop Drawings.
5. Submit Product Data before or concurrent with Samples.
6. Submit Product Data in the following format:
a. PDF electronic file.
b. Paper Copy: 5 paper copies of Product Data unless otherwise indicated. Architect will return 4
copies unless Concurrent review by Consultants is required. For each Consultant to review the
document, provide one additional copy.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings
on reproductions of the Contract Documents or standard printed data, unless submittal based on Architect's
digital data drawing files is otherwise permitted.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information,
as applicable:
a. Identification of products.
b. Schedules.
c. Compliance with specified standards.
d. Notation of coordination requirements.
e. Notation of dimensions established by field measurement.
f. Relationship and attachment to adjoining construction clearly indicated.
g. Seal and signature of professional engineer if specified.
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on
sheets at least [8-1/2 by 11 inches (215 by 280 mm), but no larger than 36 by 48 inches (750 by
1067 mm).
3. Submit Shop Drawings in the following format:
a. PDF electronic file.
b. Paper Copy: 5 paper copies of Product Data unless otherwise indicated. Architect will return 4
copies unless Concurrent review by Consultants is required. For each Consultant to review the
document, provide one additional copy.
D. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics
with other elements and for a comparison of these characteristics between submittal and actual component as
delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one
submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Number and title of applicable Specification Section.
e. Specification paragraph number and generic name of each item.
3. For projects where electronic submittals are required, a physical color and material samples must also
be submitted. Provide corresponding electronic submittal of Sample transmittal, digital image file
illustrating Sample characteristics, and identification information for record.
4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons
throughout the course of construction activity. Sample sets may be used to determine final acceptance
of construction associated with each set.
a. Samples that may be incorporated into the Work are indicated in individual Specification
Sections. Such Samples must be in an undamaged condition at time of use.
b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the
property of Contractor.
5. Samples for Initial Selection: Initial Selection includes materials specified under an allowance where a
final specific material has not be chosen. In consultation with the Architect submit manufacturer's color
charts consisting of units or sections of units showing the full range of colors, textures, and patterns
available for products for consideration.
a. Number of Samples: Submit 1 full set(s) of available choices where color, pattern, texture, or
similar characteristics are required to be selected from manufacturer's product line. Architect
will return submittal with options selected.
6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same
material to be used for the Work, cured and finished in manner specified, and physically identical with
material or product proposed for use, and that show full range of color and texture variations expected.
Samples include, but are not limited to, the following: partial sections of manufactured or fabricated
components; small cuts or containers of materials; complete units of repetitively used materials;
swatches showing color, texture, and pattern; color range sets; and components used for independent
testing and inspection.
a. Number of Samples: Submit 3 sets of Samples. Architect will retain. The Architect will return 2
Sample sets; remainder will be returned
1) Submit a single Sample where assembly details, workmanship, fabrication techniques,
connections, operation, and other similar characteristics are to be demonstrated.
2) If variation in color, pattern, texture, or other characteristic is inherent in material or
product represented by a Sample, submit at least 3 sets of paired units that show
approximate limits of variations.
E. Product Schedule: As required in individual Specification Sections or where multiple colors of the same product
are used in the same area, prepare a written summary indicating types of products required for the Work and
their intended location. Include the following information in tabular form:
1. Type of product. Include unique identifier for each product indicated in the Contract Documents or
assigned by Contractor if none is indicated.
2. Manufacturer and product name, and model number if applicable.
3. Number and name of room or space.
4. Location within room or space.
5. Submit product schedule in the following format:
a. PDF electronic file.
b. Paper Submission: 3 paper copies of product schedule or list unless otherwise indicated.
Architect] will return 2 copies.
F. Coordination Drawing Submittals: Comply with requirements specified in Section 013100 "Project
Management and Coordination."
G. Contractor's Construction Schedule: Comply with requirements specified in Section 013200 "Construction
Progress Documentation."
H. Application for Payment and Schedule of Values: Comply with requirements specified in Section 012900
"Payment Procedures."
I. Test and Inspection Reports and Schedule of Tests and Inspections Submittals: Comply with requirements
specified in Section 014000 "Quality Requirements."
J. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in
Section 017700 "Closeout Procedures."
K. Maintenance Data: Comply with requirements specified in Section 017823 "Operation and Maintenance
Data."
L. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or
person. Include lists of completed projects with project names and addresses, contact information of architects
and owners, and other information specified.
M. Welding Certificates: Prepare written certification that welding procedures and personnel comply with
requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure
Qualification Record on AWS forms. Include names of firms and personnel certified.
N. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies
with requirements in the Contract Documents and, where required, is authorized by manufacturer for this
specific Project.
O. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer
complies with requirements in the Contract Documents. Include evidence of manufacturing experience where
required.
P. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies
with requirements in the Contract Documents.
Q. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies
with requirements in the Contract Documents.
R. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form,
indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
S. Product Test Reports: Submit written reports indicating that current product produced by manufacturer complies
with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer
and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing
agency.
T. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having
jurisdiction, that product complies with building code in effect for Project. Include the following information:
1. Name of evaluation organization.
2. Date of evaluation.
3. Time period when report is in effect.
4. Product and manufacturers' names.
5. Description of product.
6. Test procedures and results.
7. Limitations of use.
U. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard
form, indicating and interpreting results of tests performed before installation of product, for compliance with
performance requirements in the Contract Documents.
V. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard
form, indicating and interpreting results of compatibility tests performed before installation of product. Include
written recommendations for primers and substrate preparation needed for adhesion.
W. Field Test Reports: Submit written reports indicating and interpreting results of field tests performed either during
installation of product or after product is installed in its final location, for compliance with requirements in the
Contract Documents.
X. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance
and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and
other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide
name and version of software, if any, used for calculations. Include page numbers.
PART 3 - EXECUTION
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated.
These services do not relieve Contractor of responsibility for compliance with the Contract Document
requirements.
1. Specific quality-assurance and -control requirements for individual construction activities are specified
in the Sections that specify those activities. Requirements in those Sections may also cover production
of standard products.
2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -
control procedures that facilitate compliance with the Contract Document requirements.
3. Requirements for Contractor to provide quality-assurance and -control services required by Architect,
Owner, or authorities having jurisdiction are not limited by provisions of this Section.
4. Specific test and inspection requirements are not specified in this Section.
C. Related Requirements:
1. Section 012100 "Allowances" for testing and inspecting allowances.
1.3 DEFINITIONS
A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the
Work to guard against defects and deficiencies and substantiate that proposed construction will comply with
requirements.
B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the
Work to evaluate that actual products incorporated into the Work and completed construction comply with
requirements. Services do not include contract enforcement activities performed by Architect.
C. Preconstruction Testing: Tests and inspections performed specifically for Project before products and materials
are incorporated into the Work, to verify performance or compliance with specified criteria.
D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified
to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance
and compliance with specified requirements.
E. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and
for completed Work.
F. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall
mean the same as testing agency.
G. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee,
Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation,
erection, application, and similar operations.
1. Use of trade-specific terminology in referring to a trade or entity does not require that certain
construction activities be performed by accredited or unionized individuals, or that requirements
specified apply exclusively to specific trade(s).
H. Experienced: When used with an entity or individual, "experienced" means having successfully completed a
minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special
requirements indicated; and having complied with requirements of authorities having jurisdiction. See
individual specification sections for modifications to this experience requirement.
D. Continuous Inspection of Workmanship: All work is to be under continuous inspection during construction to
identify and correct deficiencies in workmanship in addition to testing and inspection specified. Corrective
actions are to be required to bring work into compliance with standards of workmanship established by
Contract requirements and approved mockups.
E. Monitoring and Documentation: Maintain testing and inspection reports including log of approved and
rejected results. Include work Architect has indicated as nonconforming or defective. Indicate corrective actions
taken to bring nonconforming work into compliance with requirements. Comply with requirements of authorities
having jurisdiction.
PART 3 - EXECUTION
END OF SECTION
PART 1 - GENERAL
1.2 DEFINITIONS
A. General: Basic Contract definitions are included in the Conditions of the Contract.
B. "Approved": When used to convey Architect's action on Contractor's submittals, applications, and requests,
"approved" is limited to Architect's duties and responsibilities as stated in the Conditions of the Contract.
C. "Directed": A command or instruction by Architect. Other terms including "requested," "authorized,"
"selected," "required," and "permitted" have the same meaning as "directed."
D. "Indicated": Requirements expressed by graphic representations or in written form on Drawings, in
Specifications, and in other Contract Documents. Other terms including "shown," "noted," "scheduled," and
"specified" have the same meaning as "indicated."
E. "Regulations": Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and
rules, conventions, and agreements within the construction industry that control performance of the Work.
F. "Furnish": Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and
similar operations.
G. "Install": Unload, temporarily store, unpack, assemble, erect, place, anchor, apply, work to dimension,
finish, cure, protect, clean, and similar operations at Project site.
H. "Provide": Furnish and install, complete and ready for the intended use.
I. "Project Site": Space available for performing construction activities. The extent of Project site is shown on
Drawings and may or may not be identical with the description of the land on which Project is to be built.
F. State Government Agencies: Where abbreviations and acronyms are used in Specifications or other
Contract Documents, they shall mean the recognized name of the entities in the following list. This
information is subject to change and is believed to be accurate as of the date of the Contract Documents.
1. CBHF; State of California; Department of Consumer Affairs; Bureau of Electronic and Appliance
Repair, Home Furnishings and Thermal Insulation; www.bearhfti.ca.gov.
2. CCR; California Code of Regulations; Office of Administrative Law; California Title 24 Energy Code;
www.calregs.com.
3. CDHS; California Department of Health Services; (See CDPH).
4. CDPH; California Department of Public Health; Indoor Air Quality Program; www.cal-iaq.org.
5. CPUC; California Public Utilities Commission; www.cpuc.ca.gov.
6. SCAQMD; South Coast Air Quality Management District; www.aqmd.gov.
7. TFS; Texas A&M Forest Service; Sustainable Forestry and Economic Development;
www.txforestservice.tamu.edu.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.
B. Related Requirements:
1. Section 011000 "Summary" for work restrictions and limitations on utility interruptions.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Polyethylene Sheet: Reinforced, fire-resistive sheet, 10-mil (0.25-mm) minimum thickness, with flame-
spread rating of 15 or less per ASTM E 84 and passing NFPA 701 Test Method 2.
B. Orange or Green Plastic Snow Fence
2.3 EQUIPMENT
A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations
and classes of fire exposures.
PART 3 - EXECUTION
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for selection of products for use in Project;
product delivery, storage, and handling; manufacturers' standard warranties on products; special
warranties; and comparable products.
B. Related Requirements:
1. Section 012300 "Alternates" for products selected under an alternate.
2. Section 012500 "Substitution Procedures" for requests for substitutions.
3. Section 014200 "References" for applicable industry standards for products specified.
1.3 DEFINITIONS
A. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from
previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and
terms of similar intent.
1. Named Products: Items identified by manufacturer's product name, including make or model number
or other designation shown or listed in manufacturer's published product literature, which is current
as of date of the Contract Documents.
2. New Products: Items that have not previously been incorporated into another project or facility.
Products salvaged or recycled from other projects are not considered new products.
3. Comparable Product: Product that is demonstrated and approved through submittal process to have
the indicated qualities related to type, function, dimension, in-service performance, physical
properties, appearance, and other characteristics that equal or exceed those of specified product.
B. Basis-of-Design Product Specification: A specification in which a specific manufacturer's product is named
and accompanied by the words "basis-of-design product," including make or model number or other
designation, to establish the significant qualities related to type, function, dimension, in-service performance,
physical properties, appearance, and other characteristics for purposes of evaluating comparable products
of additional manufacturers named in the specification.
PART 2 - PRODUCTS
select color, gloss, pattern, density, or texture from manufacturer's product line that includes both standard
and premium items.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes general administrative and procedural requirements governing execution of the Work
including, but not limited to, the following:
1. Construction layout.
2. Field engineering and surveying.
3. Installation of the Work.
4. Progress cleaning.
5. Protection of installed construction.
B. Related Requirements:
1. Section 011000 "Summary" for limits on use of Project site.
2. Section 013300 "Submittal Procedures" for submitting surveys.
3. Section 017700 "Closeout Procedures" for submitting final property survey with Project Record
Documents, recording of Owner-accepted deviations from indicated lines and levels, and final
cleaning.
PART 2 - PRODUCTS
2.1 MATERIALS
A. General: Comply with requirements specified in other Sections.
B. In-Place Materials: Use materials for patching identical to in-place materials. For exposed surfaces, use
materials that visually match in-place adjacent surfaces to the fullest extent possible.
1. If identical materials are unavailable or cannot be used, use materials that, when installed, will provide
a match acceptable to Architect for the visual and functional performance of in-place materials.
2.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Existing Conditions: The existence and location of underground and other utilities and construction indicated
as existing are not guaranteed. Before beginning site work, investigate and verify the existence and location
of underground utilities, mechanical and electrical systems, and other construction affecting the Work.
1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer,
storm sewer, and water-service piping; underground electrical services, and other utilities.
2. Furnish location data for work related to Project that must be performed by public utilities serving Project
site.
B. Examination and Acceptance of Conditions: Before proceeding with each component of the Work, examine
substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with
requirements for installation tolerances and other conditions affecting performance. Record observations.
1. Examine roughing-in for mechanical and electrical systems to verify actual locations of connections
before equipment and fixture installation.
2. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.
3. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or
primers.
C. Written Report: Where a written report listing conditions detrimental to performance of the Work is required
by other Sections, include the following:
1. Description of the Work.
2. List of detrimental conditions, including substrates.
3. List of unacceptable installation tolerances.
4. Recommended corrections.
D. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work
indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Existing Utility Information: Furnish information to Architect or Engineer that is necessary to adjust, move, or
relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or
affected by construction. Coordinate with authorities having jurisdiction.
B. Field Measurements: Take field measurements as required to fit the Work properly. Recheck measurements
before installing each product. Where portions of the Work are indicated to fit to other construction, verify
dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule
with construction progress to avoid delaying the Work.
C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on
Drawings.
D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of
the Contract Documents caused by differing field conditions outside the control of Contractor, submit a request
for information to Architect according to requirements in Section 013100 "Project Management and
Coordination."
3.3 INSTALLATION
A. General: Locate the Work and components of the Work accurately, in correct elevation, as indicated.
B. Comply with manufacturer's written instructions and recommendations for installing products in applications
indicated.
C. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions
required for product performance until Substantial Completion.
D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in
excess of that expected during normal conditions of occupancy.
E. Sequence the Work and allow adequate clearances to accommodate movement of construction items on site
and placement in permanent locations.
F. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.
3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers
appropriately and dispose of legally, according to regulations.
a. Use containers intended for holding waste materials of type to be stored.
4. Coordinate progress cleaning for joint-use areas where Contractor and other contractors are working
concurrently. For this project joint use areas will be limited to exterior spaces.
B. Site: Maintain Project site free of waste materials and debris.
C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution
of the Work.
1. Remove liquid spills promptly.
2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area,
as appropriate.
D. Waste Disposal: Do not bury or burn waste materials on-site. Do not wash waste materials down sewers or
into waterways. Comply with waste disposal requirements in Section 015000 "Temporary Facilities and
Controls."
E. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or
in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the
construction period.
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited
to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
5. Repair of the Work.
B. Related Requirements:
1. Section 013233 "Photographic Documentation" for submitting final completion construction
photographic documentation.
2. Section 017300 "Execution" for progress cleaning of Project site.
3. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual
requirements.
4. Section 017839 "Project Record Documents" for submitting record Drawings, record Specifications,
and record Product Data.
5. Section 017900 "Demonstration and Training" for requirements for instructing Owner's personnel.
e. Page number.
2. Submit list of incomplete items in the following format:
a. PDF electronic file. Architect will return annotated file.
PART 3 - EXECUTION
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section includes administrative and procedural requirements for project record documents, including the
following:
1. Record Drawings.
2. Record Specifications.
3. Record Product Data.
4. Miscellaneous record submittals.
B. Related Requirements:
1. Section 017300 "Execution" for final property survey.
2. Section 017700 "Closeout Procedures" for general closeout procedures.
3. Section 017823 "Operation and Maintenance Data" for operation and maintenance manual
requirements.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION
PART 1 - GENERAL
1.2 SUMMARY
A. Section Includes:
1. Demolition and removal of buildings and site improvements.
2. Removing below-grade construction.
3. Disconnecting, capping or sealing, and abandoning in-place site utilities.
B. Related Requirements:
1. Section 011000 "Summary" for use of the premises and phasing requirements.
2. Section 013200 "Construction Progress Documentation" for preconstruction photographs taken before
building demolition.
3. Section 311000 "Site Clearing" for site clearing and removal of above- and below-grade site
improvements not part of building demolition.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged.
B. The existing pole building and pole yard immediately adjacent to demolition area will be occupied during
demolition. The adjacent houses will also be occupied during demolition. Conduct building demolition so that
disruption of activities is minimized.
1. Provide not less than 24 hours' notice of activities that will affect operations of on site adjacent occupied
buildings. Notice regarding the adjacent houses should be made at least 72 hours in advance of the
activity.
2. For on-site areas maintain access to the pole yard and pole building through the use of a temporary
driveway. Maintain access to existing walkways, exits, and other facilities used by occupants of
adjacent buildings.
3. Do not block the west driveway to the property which is shared with the house to the west.
C. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
D. Hazardous Materials: Present in buildings and structures to be demolished.
1. A report of the presence of hazardous materials is on file for review and use at the office of the
superintendent.
2. The existing facility has been completely abated of all asbestos containing materials.
E. On-site storage or sale of removed items or materials is not permitted.
1.8 COORDINATION
A. Arrange demolition schedule so as not to interfere with operations of adjacent occupied buildings.
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting demolition operations.
B. No construction plans for the existing building are available for this project. Review Project Record Documents
of existing construction or other existing condition and hazardous material information provided by Owner.
Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.
C. Verify that hazardous materials have been remediated before proceeding with building demolition operations.
D. No items of salvage are requested by the Owner at this time. Owner will remove all items from the building
prior to demolition. Inventory and record the condition of items which might be removed and salvaged.
Provide photographs or video of conditions that might be misconstrued as damage caused by salvage
operations. Comply with Section 013233 "Photographic Documentation.
3.2 PREPARATION
A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to
40 CFR 82 and regulations of authorities having jurisdiction.
B. Salvaged Items: Comply with the following:
1. Clean salvaged items of dirt and demolition debris.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area until delivery to Owner.
3.4 PROTECTION
A. Existing Facilities: Protect adjacent walkways, loading docks, building entries, and other building facilities
during demolition operations. Maintain exits from existing buildings.
B. Temporary Shoring: Provide and maintain interior and exterior shoring, bracing, or structural support to
preserve stability and prevent unexpected movement or collapse of construction being demolished.
1. Strengthen or add new supports when required during progress of demolition.
C. Existing Utilities to Remain: Maintain utility services to remain and protect from damage during demolition
operations.
1. Do not interrupt existing utilities serving adjacent occupied or operating facilities unless authorized in
writing by Owner and authorities having jurisdiction.
2. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and
authorities having jurisdiction.
a. Provide at least 72 hours' notice to occupants of affected buildings if shutdown of service is
required during changeover.
D. Temporary Protection: Erect temporary protection, such as walks, fences, railings, canopies, and covered
passageways, where required by authorities having jurisdiction and as indicated. Comply with requirements
in Section 015000 "Temporary Facilities and Controls."
1. Protect adjacent buildings and facilities from damage due to demolition activities.
2. Protect existing site improvements, appurtenances, and landscaping to remain.
3. Erect a plainly visible fence around drip line of individual trees or around perimeter drip line of groups
of trees to remain.
4. Provide temporary barricades and other protection required to prevent injury to people and damage
to adjacent buildings and facilities to remain.
5. Provide protection to ensure safe passage of people around building demolition area and to and from
occupied portions of adjacent buildings and structures.
6. Protect walls, windows, roofs, and other adjacent exterior construction that are to remain and that are
exposed to building demolition operations.
7. Erect and maintain dustproof partitions and temporary enclosures to limit dust, noise, and dirt migration
to occupied portions of adjacent buildings.
E. Remove temporary barriers and protections where hazards no longer exist. Where open excavations or other
hazardous conditions remain, leave temporary barriers and protections in place.
B. Site Access and Temporary Controls: Conduct building demolition and debris-removal operations to ensure
minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Driveways will need to be closed for construction and demolition operations. Provide alternate routes
around closed or obstructed trafficways as required for the Owner’s operations.
2. Use water mist and other suitable methods to limit spread of dust and dirt. Comply with governing
environmental-protection regulations. Do not use water when it may damage adjacent construction or
create hazardous or objectionable conditions, such as ice, flooding, and pollution.
C. Explosives: Use of explosives is not permitted.
3.8 REPAIRS
A. Promptly repair damage to adjacent buildings caused by demolition operations.
3.10 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by building demolition operations.
Return adjacent areas to condition existing before building demolition operations began.
1. Clean roadways of debris caused by debris transport.
conditions. At that time the general contractor shall inform the Owner and Architect of the conditions. The
Owner shall have the material tested and if it is hazardous will have the materials removed.
END OF SECTION
DIVISION 31 – EARTHWORK
PART 1 - GENERAL
1.2 SUMMARY
A. Section Includes:
1. Protecting existing vegetation to remain.
2. Removing existing vegetation.
3. Clearing and grubbing.
4. Stripping and stockpiling topsoil.
5. Stripping and stockpiling rock.
6. Removing above- and below-grade site improvements.
7. Disconnecting, capping or sealing, and removing site utilities.
8. Temporary erosion and sedimentation control.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for temporary erosion- and sedimentation-control
measures.
1.3 DEFINITIONS
A. Subsoil: Soil beneath the level of subgrade; soil beneath the topsoil layers of a naturally occurring soil profile,
typified by less than 1 percent organic matter and few soil organisms.
B. Surface Soil: Soil that is present at the top layer of the existing soil profile. In undisturbed areas, surface soil
is typically called "topsoil," but in disturbed areas such as urban environments, the surface soil can be subsoil.
C. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface
soil; the zone where plant roots grow.
D. Plant-Protection Zone: Area surrounding individual trees, groups of trees, shrubs, or other vegetation to be
protected during construction and indicated on Drawings.
E. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1. Sidewalks around the building site may be closed during construction. Coordinate with authorities
having jurisdiction. Do not close or obstruct streets, other sidewalks, or other adjacent occupied or
used facilities without permission from Owner and authorities having jurisdiction. Minimize closing of
the alley.
2. Provide alternate routes around closed or obstructed traffic ways if required by Owner or authorities
having jurisdiction.
B. Improvements on Adjoining Property: Authority for performing site clearing indicated on property adjoining
Owner's property will be obtained by Owner before award of Contract.
1. Do not proceed with work on adjoining property until directed by Architect.
C. Salvageable Improvements: No salvageable items on site are known of at this time.
D. Utility Locator Service: Notify One Call for area where Project is located before site clearing.
E. Soil Stripping, Handling, and Stockpiling: Perform only when the soil is dry or slightly moist.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Satisfactory Soil Material: Requirements for satisfactory soil material are specified in Section 312000 "Earth
Moving."
1. Obtain approved borrow soil material off-site when satisfactory soil material is not available on-site.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect and maintain benchmarks and survey control points from disturbance during construction.
B. Protect existing site improvements to remain from damage during construction.
1. Restore damaged improvements to their original condition, as acceptable to Owner.
END OF SECTION
PART 1 - GENERAL
B. Comply with local, state, and federal regulations to remove and properly dispose of
sidewalks, steps, driveways, and structures (including both above ground and below ground
elements).
C. Comply with local, state, and federal regulations to remove fuel tanks, septic tanks, cisterns,
and any other underground facilities; and to properly dispose of any liquids or products
contained within these items.
E. Place backfill material in holes and depressions, grade the site, and establish ground cover.
1.03 SUBMITTALS
Comply with Division 1 - General Provisions and Covenants, as well as the following:
Seventy-two hours prior to initiating demolition at each site, submit a plan to control erosion and
sediment from each site covered by the contract.
1.04 SUBSTITUTIONS
Comply with Division 1 - General Provisions and Covenants, as well as the following:
Comply with Division 1 - General Provisions and Covenants, as well as the following:
B. Coordinate with public and private utilities for timely disconnection of service prior to initiating
demolition.
C. Submit a traffic control plan to the Engineer 48 hours in advance of any lane or road closures
indicating the area of closure and the signs and traffic control devices to be used to set up the
closure.
A. The use of explosives is not allowed unless specified in the contract documents.
C. Obtain all local, state, and federal permits required for execution of the work, including
notification to the Iowa DNR according to 40 CFR 61.145. Pay all permit fees.
D. Property Ownership:
1. Title: The property address, legal description, and ownership will be included in the
contract documents. Upon execution of the contract for the work of demolition and site
clearance on all or any part of the demolition area, all rights, title, and interest of the
Jurisdiction in and to buildings, structures, and other property to be demolished and/or
removed by the Contractor on part or all of said project area as described in the contract
documents and contract addenda thereto, is vested with the Contractor.
2. Land: No property rights, title, or interest of any kind whatsoever, in or to the land or
premises upon which such buildings or structures stand, is created, assigned, conveyed,
granted, or transferred to the Contractor or any other person or persons, except only the
license and right of entry to remove such buildings and according to the contract
documents. Do not use the land or premises, or allow any other party to use the land or
premises, for any purpose other than activities in direct support of the demolition of the
building.
A. Demolition Work:
3. Includes: Unit price includes, but is not limited to, removal of trees, brush, vegetation,
buildings, building materials, contents of buildings, appliances, trash, rubbish, basement
walls, foundations, sidewalks, steps, and driveways from the site; disconnection of
utilities; furnishing and compaction of backfill material; furnishing and placing topsoil;
finish grading of disturbed areas; placing and removing safety fencing; removal of fuel
and septic tanks and cisterns; seeding; and payment of any permit or disposal fees.
2. Payment: Payment will be at the unit price for each plugged or abandoned well.
3. Includes: Unit price includes, but is not limited to, obtaining all permits; plug or abandon
private wells according to local, state, and federal regulations.
PART 2 - PRODUCTS
2.02 TOPSOIL
2.03 SEEDING
A. Sealing Materials:
3. Sand Cement Grout: Provide at a ratio of 1 sack of cement, equal volume of masonry
sand, and not more than 6 gallons of water.
4. Concrete: Provide a Class A, Class B, or Class C mix meeting the requirements of Iowa
DOT Materials I.M. 529.
B. Filling Materials: Provide filling materials free of foreign matter and any toxic residue.
1. Sand
2. Pea gravel
4. Agricultural lime
PART 3 - EXECUTION
3.01 GENERAL
A. Protect existing fire hydrants, street lights, traffic signals, utility poles, fire alarm boxes, wire
cables, underground utilities, and other appurtenances in the vicinity of the demolition site.
B. Provide correct type and class of fire extinguishers on site and in equipment. Provide fire
extinguishers adjacent to any areas where cutting torches are used.
C. Comply with noise pollution requirements and any working hour restrictions of the
Jurisdiction.
D. Prior to starting demolition, remove and properly dispose of all volatile or flammable materials
such as gasoline, kerosene, benzene, cleaning fluids, paints or paint thinners, household
hazardous wastes, or similar products.
E. Inspect the site for its character and the type of structures to be demolished. The Jurisdiction
assumes no responsibility for the condition of existing buildings, structures, and other
property within the demolition area, or the condition of the property before or after the
solicitation for proposals. No adjustment of proposal price or allowance for any change in
conditions that occur after the acceptance of the lowest responsible, responsive proposal will
be made.
F. Pay all disposal costs, including costs related to disposal of specialty items such as
household hazardous wastes, appliances, yard wastes, or electronics.
A. Sanitary Sewer: Disconnect and plug all sanitary sewer service lines according to Section
4010, 3.08 and the Jurisdiction’s Plumbing Code. Notify engineer for inspection of the
disconnection prior to placing backfill material.
B. Water Service: Disconnect all water services by a licensed plumber according to the
Jurisdiction’s Plumbing Code requirements. Notify engineer for inspection prior to placing
backfill material.
C. Storm Sewer: Disconnect all sump pump and area drain connections to the storm sewer
system according to the requirements of the Jurisdiction. Notify engineer for inspection prior
to placing backfill material.
D. Private Utility Services: Disconnect all natural gas or propane lines, electric services,
communication services, and any other services according to the requirements of the specific
utility involved.
E. Backfill: Place backfill material for all service disconnects according to Section 3010, 3.05.
F. Surface Restoration:
1. Within the Street: Restore the street surface according to Section 7040.
2. Public Right-of-way: Grade and seed according to Section 9010. Provide a 1 year
warranty for all seeded areas. If dates do not allow for seeding, complete fine grading
and apply mulch until seeding can be completed.
A. Temporary Fencing: Erect temporary fencing prior to any work around all excavations,
buildings, or other dangerous elements to prevent unauthorized access. Provide a fence 4
feet high minimum. Ensure the fence is consistently restrictive from top to grade and without
horizontal openings greater than 2 inches. Maintain fencing until all hazards are eliminated.
B. Adjacent Property: Protect structures, parking lots, driveways, sidewalks, utilities, lawns,
and other property elements from damage from the demolition activities. Provide sheeting or
shoring as necessary to protect adjacent property. Prevent the accumulation of debris and
litter on adjacent properties.
C. Sidewalks: If sidewalks are to be closed during demolition, submit a sidewalk closure plan
that meets the ADA requirements to the Engineer 48 hours prior to the scheduled closure.
Install necessary signing and barricades according to the approved closure plan. Sidewalks
designated to remain and damaged during the work will be replaced by the Contractor at no
cost to the Contracting Authority.
D. Streets: Promptly remove any demolition debris, litter, or mud from streets and rights-of-way
caused by the demolition work. Repair damage to the street and right-of-way caused by the
demolition at no additional cost to the Contracting Authority.
E. Vehicle Covering: Cover all open-bodied vehicles transporting demolition debris and trash.
F. Drainage Facilities: Maintain or re-establish all tiles, roadway subdrains, culverts, or other
drainage facilities not identified in the contract documents for removal.
A. Erosion and Sediment Control: Implement the approved erosion and sediment control plan
for each site prior to initiating demolition by placing all required devices; include measures to
prevent tracking of mud onto adjacent streets or alleys.
B. Dust Control: Comply with all applicable air pollution requirements of the Jurisdiction. Use
water or appropriate chemicals for control of dust in the demolition area, on hauling
equipment, on adjacent roadways, and when grading the site.
C. Litter: Take steps to prevent the generation of litter during demolition and collect all litter
from the demolition area at the end of each working day. Load trucks to prevent leakage or
blowing of debris.
D. Septic Tanks and Outdoor Toilets: Pump out all septic tanks and outdoor toilets using a
licensed company. Remove septic tanks and dispose of properly. Demolish outdoor toilet
building and remove from site.
E. Cisterns and Meter Pits: Pump out and remove all cisterns and meter pits.
F. Freon: Identify, handle, and dispose of all Freon containing appliances according to
applicable state and federal regulations.
G. Mercury and PCB: Handle and dispose of any fluorescent light fixtures and ballasts or
thermostats containing polychlorinated biphenyl (PCB) or mercury according to state and
federal regulations.
H. Electronic Wastes: Comply with local regulations to dispose of all electronic wastes,
including TVs, VCRs, DVD players, stereo equipment, cell phones, and computers.
Remove and dispose of all fuel tanks containing gasoline, benzene, kerosene oils, or similar
volatile materials, either above or below ground, according to the State Fire Marshal and Iowa
DNR regulations.
Pump out or empty all other tanks in a safe manner. Flush immediately with water, carbon
dioxide, or nitrogen until gas-free. Prior to tank removal, use appropriate metering equipment to
verify the tank is free of all volatile gases. Conduct the test by a competent individual in the
presence of the Engineer.
Plug and abandon all wells according to the Iowa Administrative Code, Section 567, Chapter 39.
File an Iowa DNR Abandoned Water Well Pugging Record upon completion of the well
abandonment.
2. Remove casing pipe, any curbing, frost pit, or pump house structure to a depth of 4 feet
below the ground surface.
3. Introduce sealing or filling material from the bottom of the well, or interval to be filled or
sealed, and place progressively upward to the top of the well or interval to be filled or
sealed.
4. For placement of neat cement, sand cement grout, or concrete, utilize grout pipe, tremie
pipe, cement bucket, or dump bailer to avoid segregation or dilution of the sealing
materials during placement.
5. Place bentonite pellets or graded bentonite for sealing by pouring in place and agitating
to avoid bridging.
6. Sealing materials may be substituted for filling materials to fill the entire well up to the
well cap. This procedure is preferred but not required.
1. Place filling or sealing materials from the bottom of the well to 1 foot below the static
water level.
2. Place sealing materials on top of the filling materials up to the static water level to act as
a cap.
3. Place filling or sealing materials up to top of 4 feet below the ground surface.
4. Place 1 foot of sealing material on top of filling materials, extending 6 inches beyond the
diameter of the well casing.
3.07 SALVAGE
A. Restrictions: Salvage is allowed only on property owned by the Jurisdiction. The ownership
of each site is included in the contract documents. Remove all salvaged materials from the
site by the end of each day’s work.
B. Authorized Workers: Only the Contractor’s authorized workers are allowed to salvage or
demolish the structure or its contents.
A. Structures:
1. Except for wood frame or non-rigid masonry buildings, start on the top floor and maintain
structural parts of buildings, such as columns, beams, and joists, supporting the floor of
any building story until the walls, flooring, and partitions of that story are removed.
2. No wall or part of a wall will be allowed to fall outward from any building except through
chutes or other controlled method that will ensure safety and minimize dust, noise, and
other nuisance.
B. Basements and Foundations: Completely remove and dispose of all basement floors,
footings, foundations, and walls unless specifically stated in the contract documents. Notify
engineer for inspection prior to filling the basement excavation.
C. Surface Slabs: Remove all concrete, asphalt, or masonry slabs and appurtenances.
D. Vegetation: Remove and dispose of all brush, shrubs, trees, logs, downed timber, and other
yard waste on the site unless otherwise specified in the contract documents. Do not mix with
demolition material. Remove stumps to a minimum of 2 feet below finish grade.
Protect any trees or other vegetation not designated for removal by placing a fence at the drip
line encompassing the entire tree and keeping all operations outside of the fenced in area,
including storage of equipment or materials. At no additional cost to the Contracting
Authority, replace any trees that are designated for protection but are damaged beyond
treatment. The Engineer will determine size and species of the replacement tree.
E. Retaining Walls: Remove all retaining walls unless otherwise specified in the contract
documents. Complete work without damage to adjacent public or private property. Following
removal, grade the adjacent slope to a 3:1 (horizontal to vertical) slope or flatter.
F. Fences: Remove all fences, guardrails, posts, and other appurtenances unless on a
property line with adjacent private property and designated for retention in the contract
documents. Fill and compact soil in all post holes.
G. Miscellaneous Objects: Remove all clotheslines, signs, piping, posts, or any other objects
protruding from the ground and fill any resulting hole.
3.09 DISPOSAL
B. Demolition Material: Deliver all demolition material to the disposal facility designated in the
contract documents according to the rules for that facility. Cover all vehicles used to
transport demolition material. The Contractor may submit an alternate disposal facility, fully
licensed by the state, for consideration by the Engineer. Submit all disposal tickets received
from the disposal facility clearly indicating the specific address of the origin of the demolition
debris. Pay all fees associated with disposal of the demolition material.
All asbestos or asbestos containing materials will be removed prior to the demolition by a
licensed asbestos contractor through a separate contract. Notify the Engineer if asbestos is
discovered in the demolition process. No further work will be allowed until the asbestos has been
removed by a licensed contractor.
3.11 RECYCLING
If specified in the contract documents, certain materials may be required to be recycled from the
demolition site. These include bricks, concrete, and recoverable metals. All costs related to
recycling and the value received from recycled materials are the Contractor’s.
A. Backfill: Place backfill material in all excavation areas and holes with material meeting
Section 2010, 2.03. Unless otherwise specified in the contract documents, compact using
Type A compaction as indicated in Section 2010, 3.04. If compaction with moisture and
density control is specified, use Section 2010, 3.09. Notify the Engineer 24 hours in advance
of compaction testing so a soil density sample can be obtained and analyzed. Provide
density testing as specified in the contract documents.
B. Topsoil: Strip and stockpile the top 12 inches of topsoil for use as a final topsoil and grading
material. If topsoil quality does not meet Section 2010, 2.01, supply additional material to
place a minimum of 8 inches over the site. The Engineer will approve the borrowed topsoil
material. No payment will be made for supplying additional topsoil material.
C. Borrow: If sufficient fill material is not available, supply additional material of equal quality to
the soil on the site. Supply suitable material meeting Section 2010. No payment will be
made for supplying additional fill material.
D. Grading: Grade site to conform with all surrounding areas with a uniform surface that will not
allow ponding and does not change drainage patterns that existed prior to demolition.
Remove excess excavation material from the site.
A. Clean Up: Remove all unused material and rubbish from the site. Remove all salvaged
materials and any materials recycled. Restore all areas occupied during the course of the
work, including the public right-of-way and any private property.
B. Seeding: Complete seedbed preparation, seeding, fertilizing, and mulching of the site
according to the requirements for permanent urban seeding in Section 9010, 2.02, A. If
unable to comply with permanent seeding dates, apply the urban temporary erosion control
mixture in Section 9010, 2.02, D.
END OF SECTION