Professional Documents
Culture Documents
The construction has been developed from the point of view of costs. For this purpose,
CAPEX and OPEX have been determined, and assuming mine costs, a cash flow has also
You can see the capex in chapter 2.0 MAIN PLANT, subtitle 2.4. CAPEX AND
CAPEX evaluates the net cost of equipment, direct and indirect construction and
installation costs. Within these, we estimate the cost of assembly, pipelines, land
management, civil works and electrical installations through factors. Likewise, CAPEX
evaluates the indirect costs of the project that represent EPCM, spare parts, commissions,
startup, freight and transport. A contingency of 35% is also evaluated. All these costs were
gladly provided us with this information. In this case, part of the CONSTRUCTIBILITY
All equipment costs were taken from InfoMine USA. (2014). We consider these equipment
costs as FOB costs, CIF cost was considered as 8% of equitment cost. In order to obtain
equipment cost values, the M&S Index extracted from Chemical Engineering magazine
were used. For the year 2019 the factor is 1716.2 while for the year 2014 is 1566.9. We
chosed 2014 like the first year because the edition of the InfoMine USA.
You can see the OPEX in chapter 2.0 MAIN PLANT, subtitle 2.4. CAPEX AND
OPEX
The calculation of the energy consumed per month, the value given in HP was multiplied
by 0.745 to convert it to kw, the it was multiplied by the number of hours worked per day.
It was considered 28 days per month to calculate the monthly energy. In the cost of this
project, the salaries of people directly and indirectly involved with the production process
of the concentrate (engineers, technicians, operators, etc.) have been considered acording to
Direct and indirect materials have been considered within the supply group, such as
reagents, spare parts and maintenance materials. Spare parts and maintenance were
considered as 1% of the cost of equipment. Within the service group, the energy
consumption of each equipment was mainly considered. The cost of energy is 0.065 kw -
hr. It was obtained through an average of the energy costs in which some Peruvian
companies work.
We have a representation of the plants in two dimensions in plans which are in the annexes
of the report. You can see the PLANS in chapter 4.0 ANNEX, subtitle 4.1. MAIN
PLANT, section 4.1.2. PFD MAIN PLANT; subtitle 4.2. REAGENT PLANT section
4.2.2. PFD REAGENT PLANT and subtitle 4.3. DISALINATION PLANT, section
For cash flow we could not work only with plant costs, so mine costs were estimated by
benchmarking, with data from Peruvian companies with close capabilities and approximate
mineralogy, for example the “Toromocho” and “Cerro Lindo” mines. Expert criteria were
also consulted for engineers who work in operation and have current data. Also for mine
data according to Lightning. J (2012) in his work "VALUATION OF CAPEX AND OPEX