Professional Documents
Culture Documents
Table 3.1 EPD’s TSP Monitoring Data at Yuen Long Station, 1998 to 2000
Highest 2 Daily
Year Annual Average
Average
3.3.1.4 As shown by the monitoring results in Table 3.1 for the rooftop Yuen
Long station, it is observed that the TSP concentrations in the Yuen Long area
remained high during the last few years and exceedance of the annual average
AQO for TSP was recorded for the last three years. The reasons may be largely
due to dust emissions from the construction activities and traffic emissions
from road network.
3.3.1.5 As shown in Figure 1.8, the proposed Deep Bay Link will encroach upon
the southwestern corner of the existing San Wai STW in the form of a viaduct.
With reference to the Environmental Impact Assessment Report for Agreement No.
CE109/98 Deep Bay Link Investigation and Preliminary Design (July 2002), the
modelling results showed exceedance of the 24-hour average AQO for nitrogen
dioxide at 10m above ground at the existing San Wai STW under the worst-case
scenario. The predicted exceedance is at 10m above ground level and covers an
area within about 50m from the southwestern corner of the existing San Wai
STW. Since there is no sensitive use located at the area of exceedance within
the existing and the future San Wai STW, adverse air quality impact is
therefore not expected.
3.4 Air Sensitive Receivers
3.4.1.1 In accordance with the definition stipulated in Annex 12 of EIAO-TM,
air sensitive receiver (ASR) is defined as:
· Any domestic premises, hotel, hostel, hospital, clinic, nursery, temporary
housing accommodation, school, educational institution, office, factory, shop,
shopping centre, place of public worship, library, court of law, sports
stadium or performing arts centre; and
· Any other premises or place with which, in terms of duration or number of
people affected, has a similar sensitivity to the air pollutants as the above
listed premises and places.
3.4.1.2 The Assessment Area for air quality impact assessment includes an area
500m from the boundary of the works areas. Figures 3.1 and 3.2 show
respectively the Assessment Area around the proposed expanded San Wai STW and
Ha Tsuen Pumping Station. Existing land uses within the Assessment Area of San
Wai STW include mainly agricultural land, container storage areas, and
scattered village houses. Whereas the existing land uses around the Ha Tsuen
Pumping Station are mainly public and private residential housing estates with
a number of schools.
3.4.1.3 Future ASRs around the proposed expanded San Wai STW and Ha Tsuen
Pumping Station include the planned sensitive land uses of the HSKNDA and HSK
North NDA as shown in Figure 1.9. Immediately to the southwest of the proposed
San Wai STW is the proposed Deep Bay Link. The road users of the proposed Deep
Bay Link might be susceptible to the future odour impacts from the operation
of San Wai STW. For reference purpose, the closest point of San Wai STW to
Deep Bay Link is taken as an air quality assessment point (A41) of the
operational phase odour impact assessment for San Wai STW.
3.4.1.4 Existing and future representative ASRs within the Assessment Area
likely to be affected by the construction and/or operation of the San Wai STW,
Ha Tsuen Pumping Station, and emergency bypass culvert are identified as
assessment points for this assessment. The selected assessment points are
summarised in Tables 3.2 to 3.4 and are shown in Figures 3.1 to 3.3. With
reference to Section 1.2 of this report, the proposed emergency bypass will be
constructed in the form of box culvert and will only be used for conveying
treated effluent from San Wai STW. The major air quality impact of the
proposed emergency bypass culvert would be associated with the construction
activities.
Table 3.2 Identified Air Quality Assessment Points Around the San Wai STW
Distance
from the
Subject to
Boundary Subject to
Assessment operational
Location of construction
Point phase
Expanded phase impact
impact
San Wai
STW
Tseung
A15 443m ü ü
Kong Wai
Tseung
A16 450m ü ü
Kong Wai
Tseung
A17 368m ü ü
Kong Wai
Villa
A31 483m ü ü
Oasis
San Wai
A37 village 208m ü ü
house
San Wai
A38 village 190m ü ü
house
San Wai
A39 village 260m ü ü
house
house
Deep Bay
Link
(closest
A41 0m ü
point to
San Wai
STW)
Area 5a
of
A42 HSKNDA 213m ü
(future
ASR)
Table 3.3 Identified Air Quality Assessment Points Around the Ha Tsuen Pumping
Station
Distance
from the
Subject to
Boundary Subject to
Assessment operational
Location of construction
Point phase
Expanded phase impact
Impact
Ha Tsuen
PS
Ho Ming
A1 Primary 134m ü ü
School
Pui Shing
Catholic
A2 170m ü ü
Secondary
School
Ho Tak Sum
A3 Primary 173m ü ü
School
QE School
Old
Students'
A4 Association 344m ü ü
Branch
Primary
School
Secondary
School
Tin Shing
A6 99m ü ü
Court
Tin Shing
A7 126m ü ü
Court
Tin Shing
A8 153m ü ü
Court
Tin Oi
A9 470m ü ü
Court
Home for
Aged at Sha
A11 183m ü ü
Chau Lei
Road
Sha Chau
A12 225m ü ü
Lei Tsuen
HSK North
NDA
Residential
A43 124m ü
Area
(future
ASR)
HSK North
NDA
Residential
A44 57m ü
Area
(future
ASR)
HSK North
NDA
Residential
A45 56m ü
Area
(future
ASR)
A46 HSK North 55m ü
NDA
Educational
Land Use
https://www.epd.gov.hk/eia/register/report/eiareport/eia_0862002/EIA main report/section3.htm#3. AIR QUALITY IMPACT 5/29
12/29/22, 2:13 AM 3
(future
ASR)
HSK North
NDA
Educational
A47 57m ü
Land Use
(future
ASR)
HSK North
NDA
Residential
A48 32m ü
Area
(future
ASR)
HSK North
NDA
Residential
A49 36m ü
Area
(future
ASR)
HSK North
NDA
Residential
A50 56m ü
Area
(future
ASR)
HSK North
NDA
Commercial
A51 128m ü
Area
(future
ASR)
Table 3.4 Identified Air Quality Assessment Points Around the Emergency Bypass
Culvert
Assessment
Location
Point Alternative
1 2 3 4
Home for
Aged at Sha
A11 >500m >500m 322m >500m
Chau Lei
Road
Sha Chau
A12 476m >500m 274m >500m
Lei Tsuen
Sik Kong
A14 462m >500m 445m >500m
Wai
Tseung Kong
A15 >500m >500m 423m 92m
Wai
Tseung Kong
A16 466m >500m 386m 159m
Wai
Tseung Kong
A17 415m >500m 328m 132m
Wai
San Sang
A21 249m 148m 455m >500m
Tsuen
San Lee Uk
A22 >500m 123m >500m >500m
Tsuen
San Lee Uk
A23 >500m 238m >500m >500m
Tsuen
San Uk
A24 139m 409m 110m >500m
Tsuen
San Uk
A25 228m 478m 147m >500m
Tsuen
Shek Po
A26 349m 420m 235m >500m
Tsuen
Shek Po
A27 340m 402m 268m >500m
Tsuen
Kau Lee Uk
A28 25m 32m 245m >500m
Tsuen
Kau Lee Uk
A29 14m 147m 121m >500m
Tsuen
Kau Lee Uk
A30 8m 238m 38m >500m
Tsuen
Sunny
A33 >500m >500m >500m 255m
Villas
Sunny
A34 >500m >500m >500m 187m
Villas
King's
A35 >500m >500m 491m 270m
Garden
King's
A36 >500m >500m 471m 278m
Garden
San Wai
A37 village 335m >500m 263m 181m
house
San Wai
A38 village 287m >500m 212m 163m
house
San Wai
A39 village 322m >500m 236m 193m
house
San Wai
A40 village 441m >500m 401m 37m
house
3.5.1 General
3.5.1.1 With reference to Section 1.2 of this report, in order to reduce the
chance of discharging raw sewage into Tin Shui Wai Drainage Channel and hence
Deep Bay, an emergency bypass culvert will be constructed in the form of box
culvert from San Wai STW to nearby drainage channel as part of this project.
3.5.1.2 Four alternative alignments of the proposed emergency bypass culvert
were considered and are shown in Figure 3.4. Figure 3.4 also indicates the
extent of the construction works areas associated with the four alternative
alignments.
3.5.2 Construction Phase Impact
3.5.2.1 In general, the construction works areas for the emergency bypass
culverts would be a 10m wide strip along the culvert alignment from the
expanded San Wai STW up to the connection point with the existing Ting Shui
Wai Drainage Channel for Alternatives 1, 2, and 3, and with the existing Lo Uk
Tsuen Drainage Channel for Alternative 4. A summary of the length and the
total construction works areas for the four alternatives is shown in Table
3.5.
Table 3.5 Length and Total Construction Works Area for the Four Alternatives
of the Proposed Emergency Bypass Culvert
1 1300m 13,000m2
2 1600m 16,000m2
3 1350m 13,500m2
4 600m * 6,000m2
3.5.3.1 All the four alternatives of the emergency bypass culvert will be
constructed in the form of box culvert up to the connection point with the
existing Ting Shui Wai Drainage Channel for Alternatives 1, 2, and 3, and with
the existing Lo Uk Tsuen Drainage Channel for Alternative 4. The existing
drainage channels will then convey the effluent to the Deep Bay.
3.5.3.2 With reference to the discussion in Section 1.2, the proposed
emergency bypass culvert will only be used for conveying treated effluent from
San Wai STW under the emergency event when the NWNT effluent tunnel or the
Urmston Road outfall is out of operation. Since the residual sulphide content
in the treated effluent would be minimal if any. Hydrogen sulphide emission
from treated effluent flowing along the proposed emergency bypass culvert and
the existing open drainage channels would thus not be expected. Odour impact
at the nearby existing and future ASRs (including Tin Shui Wai New Town,
HKSNDA and HSK Norht NDA) from the operation of the proposed emergency bypass
culvert is therefore not anticipated.
3.5.3.3 Other than the scenario described above with the break down of the
NWNT effluent tunnel or the Urmston Road outfall, the other emergency
discharge scenarios for the existing and the future arrangements are the same
and would result in the discharge of raw sewage. Nonetheless, the chance of
discharging raw sewage into the Tin Shui Wai Drainage Channel is in fact very
remote and has not happened since the commissioning of the existing San Wai
STW, the Ha Tsuen Pumping Station, and the NWNT effluent tunnel and Urmston
Road outfall for more than 10 years. Besides routine monitoring, inspection,
and maintenance to ensure satisfactory working condition of the system, the
following have been and will be applied to the Ha Tsuen Pumping Station to
further reduce the chance of system failure:
Standby pumps and screens to facilitate maintenance and repair of
equipment;
Back-up power in the form of dual power supply;
24-hour manned pumping station; and
Hand-cleaned bar screen at overflow bypass to prevent discharge of
floating solids.
3.5.3.4 A contingency plan would also be developed at the detailed design
stage to deal with the emergency discharges that may occur during the
operational stage of the project. It is recommended to include the following
items in the contingency plan:
Locations of the sensitive receivers in the vicinity of the emergency
discharges at Deep Bay and Urmston Road;
A list of relevant government bodies to be informed and to provide
assistance in the event of emergency discharges. Information on key
contact persons and telephone numbers should be included;
Reporting procedures required in the event of emergency discharges; and
Procedures listing the most effective means in rectifying the breakdown of
San Wai STW, Urmston Road Tunnel or Ha Tsuen Pumping Station in order to
minimise the discharge duration.
3.6 Assessment Methodology
3.6.1 Construction Phase Assessment
3.6.1.1 Construction dust impacts are assessed by determining dust-generating
activities and recommending corresponding dust control and suppression
measures. Details of dust-generating construction activities, including the
site area and the construction program were reviewed.
3.6.1.2 The construction works involved in this project include works
associated with the construction of the proposed expanded San Wai STW, the
expanded Ha Tsuen Pumping Station, and the emergency bypass culvert.
Emission Inventories
3.6.1.3 The major potential air quality impacts during the construction phase
of the proposed expanded San Wai STW and the expanded Ha Tsuen Pumping Station
would result from dust arising from construction activities including:
· Site clearance and preparation;
· Excavation and filling;
· Open site erosion;
· Construction of foundation and superstructure; and
· Handling and transportation of construction and demolition material.
3.6.1.4 With reference to Section 1.3 of this report, apart from the
construction of this project, there are a number of major projects planned in
the vicinity of the study area which might cause cumulative construction phase
impacts to the environment. These projects include YLKTSSD Stage 1, YLKTSSD
Stage 2, Deep Bay Link, and the HSKNDA. Concurrent construction activities
identified within 500m from the San Wai STW and the Ha Tsuen Pumping Station
are shown in Figures 3A.1 and 3A.2 in Appendix 3A. For the purpose of this
assessment, it was assumed that all these construction activities, together
with the construction of preferred Alternative 4 of the proposed emergency
bypass culvert, would occur at the same time. All these construction
activities were included in the dust modelling to predict the worst-case
cumulative dust impacts at the assessment points. Details of the construction
dust emissions calculation are presented in Appendix 3A.
3.6.1.5 The prediction of dust emissions was based on typical values and
emission factors from United States Environmental Protection Agency (USEPA)
Compilation of Air Pollution Emission Factors (AP-42), 5th Edition. A ten-hour
working day was assumed during construction phase of the Project. References
of the calculations of dust emission factors for different dust generating
activities are listed in Table 3.6.
with relatively warm climate such as Hong Kong. Sulphide generation would be
promoted under anaerobic conditions in sewage conveyance system. H2S is often
detectable when all odour components have been diluted to below their
detection thresholds. H2S is therefore adopted as the main parameter for
assessing odour impact in this study.
3.6.2.3 The odour impact assessment for this study is carried out by first
estimating the H2S emission rates using well-recognised equations and then
predicting the worst-case H2S concentrations at the assessment points using
computer dispersion modelling. As discussed in Section 3.2 above, the EIAO-TM
stipulates an odour nuisance limit of 5 odour units (OU) based on an averaging
time of 5 seconds. An OU is defined as the dilution factor required for
samples of odorous gases to be diluted with clean odour-free air to the
detection threshold.
3.6.2.4 Therefore, in order to convert the predicted H2S concentration at the
assessment points to OU for compliance checking with the EIAO-TM odour
nuisance limit, it is required to correlate the H2S concentration with OU, or
in simple term, to determine the detection threshold (i.e. one OU) of H2S for
those potential odour sources of concern in this assessment. For the purpose
of this assessment, a conservative detection threshold for H2S of 0.0005ppm or
0.00076 mgm-3 is adopted (Source: Woodfield M. and Hall D. (1994). Odour
Measurement and Control - An Update. AEA Technology and National Environmental
Technology Centre).
Odour Emission Estimation
3.6.2.5 The generation of sulphide in sewerage systems is predominantly an
anaerobic microbiological reaction involving sulphate and sulphate-reducing
bacteria. The bacteria are concentrated in slimes that form on the walls of
sewers and associated facilities. Although sulphide is also produced in the
wastewater, these slimes are generally responsible for the majority of
sulphide generated in sewerage systems. Apart from the need to have anaerobic
conditions, the following factors may also influence the rate of sulphide
generation:
Ø Liquid velocity
Ø Soluble electron donor concentration (which effectively is the soluble
biochemical oxygen demand concentration)
Ø Sulphate concentration
Ø Temperature
3.6.2.6 Several predictive equations (e.g. Pomeroy, Thistlethwayte) are
available for estimating the build-up of sulphide in sewerage systems. These
equations were derived empirically from measurements taken on a large number
of operating systems. Although different equations and different coefficients
adopted in these equations may result in different predictions, in most cases,
these equations should provide a reasonable basis for developing sulphide
control strategies.
3.6.2.7 Having said that, Thistlethwayte equation has been reported to
overestimate the sulphide flux when excess sulphate was available in sewage
(USEPA, 1985). The use of the Thistlethwayte equation is also not recommended
for low sewage velocity (say less than 0.5m/s) (Technological Standing
Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989a). It is
recommended in the Hydrogen Sulphide Control Manual (Technological Standing
Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989a), one of the
most comprehensive guidelines available today, that the Pomeroy equation be
used because of its simplicity and reliability in predicting sulphide flux
over a wider range of velocities.
Prediction of Sulphide Build-up in Pumping Mains
3.6.2.8 The equation suggested by Pomeroy to predict the sulphide flux from
wall slimes (Technological Standing Committee on Hydrogen Sulphide Corrosion
in Sewage Works, 1989a) is:
G = M[BOD5]1.07T-20
T temperature, oC
M coefficient, m/h
3.6.2.9 A value of 1x10-3 m/h for M was recommended by Pomeroy for normal pressure mains. High
values of M (around 2.9x10-3) were obtained by Pomeroy from two systems where the wastewater
contained a significant proportion of seawater and where anaerobic corrosion of iron produced a very
rough inside surface of the pipe, which promote slime growth.
3.6.2.10 The sulphide generated in the wastewater itself may also form a portion of the total sulphide build-
up. The build-up in sulphide concentration by bacteria activity in both slime and wastewater is given by the
following equation which was derived by performing a mass balance over the length of the pipeline
(Technological Standing Committee on Hydrogen Sulphide Corrosion in Sewage Works, 1989a):
Cs = 4G(1 + 0.4D)t / D
3.6.2.11 With reference to the Hydrogen Sulphide Control Manual (Technological Standing Committee on
Hydrogen Sulphide Corrosion in Sewage Works, 1989), one of the most comprehensive guidelines
available today, the equation below presented by Pomeroy and Parkurst is taken to estimate the sulphide
concentration for the gravity sewers:
S2 = {(aS1 – b)e-at + b} / a
a = N(SV)3/8 / dm
b = M’[BOD5]1.07T-20/r
T temperature, oC
r hydraulic radius, m
3.6.2.12 A value of 0.32x10-3 m/h for M' and 0.96 for N recommended by Pomeroy and Parkurst for
median or "average" sulphide generation condition are adopted in this assessment in the above equation.
3.6.2.13 Details of the hydrogen sulphide build-up calculations for this assessment are presented in
Appendix 3B.
3.6.2.14 The odour problem associated with hydrogen sulphide is caused by the release of molecular
hydrogen sulphide gas. The rate of release is dependent on many factors, including pH, temperature,
turbulence, ventilation conditions, etc.
3.6.2.15 The concentration of molecular hydrogen sulphide in wastewater is dependent on the pH value
and the temperature. Figure 3.5 shows this relationship and indicates that pH is more important than
temperature in the release of molecular hydrogen sulphide in wastewater, particularly when the pH drops
below 8 (towards a more acidic condition). When pH is constant, the release of molecular hydrogen
sulphide would increase with decreasing temperature.
3.6.2.16 The major potential odour emission sources within the proposed expanded San Wai STW are
shown in Figure 3.6 which include:
· the inlet chamber;
· the fine screen;
· the detritors;
· the sludge holding tanks;
· the solid handling house;
· the sludge dewatering house;
· the rapid mix and flocculation tank;
· the primary sedimentation tanks; and
· the connection channels.
3.6.2.17 For the proposed expanded Ha Tsuen Pumping Station, the major odour sources would be the
existing and future wet wells of the pumping station.
3.6.2.18 The H2S emission flux from potential odour sources was estimated as a free surface sewage flow
with the following equation (Design Manual on Odor and Corrosion Control in Sanitary Sewerage Systems
and Treatment Plants, 1985):
3.6.2.19 The H2S emission flux from the wet wells of the proposed expanded Ha Tsuen Pumping Station
was calculated in accordance with Chapter 4.3 (Waste Water Collection, Treatment and Storage) of
USEPA Compilation of Air Pollution Emission Factors (AP-42), 5th Edition for wastewater sump tank.
3.6.2.20 Details of the H2S emission flux calculations for the major odour sources are presented in
Appendix 3B.
3.6.2.21 The USEPA approved ISCST3 model was used to simulate odour dispersion. Mixing height of
500m and ambient temperature of 298K were taken in the model.
3.6.2.22 To ascertain the worst-case condition, the dispersion modelling considered 5940 predefined
separate meteorological conditions. The resolution on the wind direction is set to 2-degree increments.
The following stability class and wind speed taken by USEPA for screening purpose were taken in this
assessment:
C : 1,2,3,4,5,8,10 m/s
D : 1,2,3,4,5,8,10,15,20 m/s
E : 1,2,3,4,5 m/s
F : 1,2,3,4 m/s
3.6.2.23 Odour assessment was based on a 5-second averaging time due to the short exposure period
tolerable by human receptors. However, the shortest averaging time for ISCST3 is one hour, which is also
the limitation of most other dispersion models. Conversion of model-computed hourly average results to 5-
second values is therefore necessary. The hourly concentration was first converted to a 3-minute average
value according to a power law relationship that is stability dependent (Duffee, O'Brien and Ostojic, 1991).
Another conversion factor (10 for unstable conditions and 5 for neutral to stable conditions) was then
applied to convert the 3-minute average to 5-second average (Keddie, 1980). The odour threshold of
hydrogen sulphide was taken as 0.5ppb or 0.76mgm-3. The conversion factors for different stability
classes are summarised in Table 3.7.
Table 3.7 Factors for Converting Hourly Average Odour Values to 5-second Average Odour Values
Factors to Convert
1-hr average
Concentration
3
concentration
Stability (m g/m ) from Concentration (m g/m3)
Class 1-hr average
(m g/m3) to directly to
to
Odour Unit 5-second
5-second
(B) Odour Unit
average
(OU)
(A)
(A x B)
Unmitigated
Mitigated Scenario
Scenario
% AQO /
Guideline 115% 104% 83% 86%
level
Unmitigated
Mitigated Scenario
Scenario
% AQO /
Guideline 68% 70% 60% 57%
level
3.8.1.7 As shown by the modelling results, in view of the low intensity of the
construction activities involved, exceedance of the guideline level and AQO
for TSP would not be expected without any dust suppression measures.
3.8.1.8 With the implementation of dust suppression measures, the modelling
results showed that the worst-case dust impacts at the assessment points are
on average reduced by about 22% and 14% respectively for the 1-hour average
TSP level and the 24-hour average TSP level.
3.8.1.9 The predicted worst-case hourly and daily average TSP concentration
contours at 1.5m above ground around the proposed expanded Ha Tsuen Pumping
Station for the unmitigated and mitigated scenarios are shown in Figures 3.11
to 3.14. No air sensitive use is identified within the areas with predicted
exceedance of the hourly and daily TSP guideline level / AQO during the
construction period under the mitigated scenario.
3.8.1.10 With the implementation of proper dust control and suppression
measures stipulated in the Air Pollution Control (Construction Dust)
Regulation and described in Section 3.9 below, adverse dust impact from the
construction activities of the proposed expanded Ha Tsuen Pumping Station is
not expected.
1.5m 2.5m 5m 7.5m 10m 12.5m 15m 17.5m 20m 22.5m 25m 27.5m 30m
A15 28.5 27.9 25.2 21.3 16.9 12.5 10.9 10.6 10.3 9.9 9.5 9.2 8.7
A16 28.5 27.9 25.3 21.5 17.0 12.7 11.2 10.9 10.5 10.2 9.8 9.4 9.0
A17 35.1 34.2 30.1 24.4 18.3 14.0 13.6 13.1 12.6 12.1 11.5 10.8 10.2
A31 27.7 27.2 24.8 21.3 17.3 13.2 10.3 10.0 9.7 9.4 9.1 8.8 8.4
A32 27.3 26.8 24.6 21.3 17.4 13.5 10.1 9.9 9.6 9.3 9.0 8.7 8.3
A37 53.7 51.1 40.6 27.8 21.3 20.3 19.2 18.0 16.6 16.0 15.4 14.7 14.0
A38 63.7 60.2 46.2 30.2 25.3 24.0 22.4 20.8 19.2 18.4 17.5 16.6 15.6
A39 46.7 44.9 37.3 27.5 20.4 19.6 18.7 17.7 16.6 15.5 14.3 13.7 13.2
A40 25.3 24.4 20.9 16.3 13.9 13.5 12.9 12.7 12.4 12.1 11.7 11.4 11.0
A41 NA NA NA NA NA NA 41.5 NA NA NA NA NA NA
A42 57.9 54.6 41.7 27.1 25.9 24.5 22.9 21.2 20.1 19.1 18.2 17.2 16.1
Max 63.7 60.2 46.2 30.2 25.9 24.5 41.5 21.2 20.1 19.1 18.2 17.2 16.1
% Criteria 1274% 1204% 924% 604% 518% 490% 830% 424% 402% 382% 364% 344% 322%
Note: Assessment point A41 is representing the section of Deep Bay Link at 15m
above ground level adjacent to the proposed San Wai STW.
Table 3.11 Predicted Worst-case 5-second Average Odour Levels at Assessment
Points Around the Expanded San Wai STW for the Mitigated Scenario
1.5m 2.5m 5m 7.5m 10m 12.5m 15m 17.5m 20m 22.5m 25m 27.5m 30m
A15 0.5 0.5 0.6 0.7 0.8 1.0 1.1 1.1 1.1 1.0 0.9 0.7 0.5
A16 0.5 0.5 0.6 0.7 0.8 1.0 1.1 1.1 1.1 1.0 0.9 0.7 0.5
A17 0.5 0.5 0.5 0.7 1.0 1.2 1.3 1.4 1.4 1.2 1.0 0.8 0.6
A31 0.5 0.5 0.6 0.7 0.8 0.9 1.0 1.1 1.0 1.0 0.8 0.7 0.5
A32 0.5 0.5 0.6 0.7 0.8 0.9 1.0 1.0 1.0 1.0 0.8 0.7 0.6
A37 0.8 0.8 0.8 0.8 1.3 1.8 2.2 2.4 2.3 2.0 1.5 1.0 0.8
A38 0.9 0.9 0.9 0.9 1.4 2.0 2.5 2.8 2.7 2.2 1.7 1.1 1.0
A39 0.7 0.7 0.7 0.9 1.3 1.7 2.0 2.2 2.1 1.8 1.4 1.0 0.7
A40 0.7 0.7 0.7 0.8 1.1 1.5 1.7 1.8 1.8 1.6 1.3 0.9 0.7
A41 NA NA NA NA NA NA 4.6 NA NA NA NA NA NA
A42 0.9 0.9 0.9 0.9 1.5 2.1 2.6 2.9 2.8 2.4 1.7 1.1 1.0
Max 0.9 0.9 0.9 0.9 1.5 2.1 4.6 2.9 2.8 2.4 1.7 1.1 1.0
% Criteria 18% 18% 18% 18% 30% 42% 92% 58% 56% 48% 34% 22% 20%
Note: Assessment point A41 is representing the section of Deep Bay Link at 15m
above ground level adjacent to the proposed San Wai STW.
3.8.2.4 The predicted worst-case 5-second average odour levels in the vicinity
of the proposed expanded San Wai STW for the unmitigated scenario are shown in
Figure 3.15. Since the emission heights of the odour sources were taken as
ground level for the unmitigated scenario, the odour levels presented in
Figure 3.15 at a receiver height of 1.5m above ground level would represent
the worst-case impacts. 1.5m is the average height of human breathing zone. As
shown in Figure 3.15 and in Table 3.10, very high odour impacts would be
expected in the area even at a large distance from the STW. Exceedances of the
5 OU criteria level are expected at most part of San Wai. More than 60 OU are
predicted at an existing village house in San Wai (assessment point A38).
3.8.2.5 For the mitigated scenario, as shown by the modelling results in Table
3.11, the worst affected height around the San Wai STW would be at 17.5m above
ground level. Figure 3.16 shows the predicted worst-case 5-second average
odour levels in the vicinity of the proposed expanded San Wai STW at the worst
affected height of 17.5m above ground level. No air sensitive use is
identified within the areas with predicted exceedance of the 5 OU criteria
during the operational period under the mitigated scenario. As shown in the
figure, higher odour levels are predicted around the exhaust point of the
deodorization unit. The highest odour impact of about 3 OU is predicted at
Area 5a of the future HSKNDA. With the implementation of the proposed odour
control measures, exceedance of the 5 OU criteria is not predicted at the
existing and future ASRs in the area.
Proposed Expanded Ha Tsuen Pumping Station
3.8.2.6 Under the current design, most of the sewage surface within the wet
wells would not be exposed to the atmosphere under normal operation. Odour
emissions from the sewage surface within the wet wells should thus be minimal
during normal operation. However, the wet wells would be force-ventilated
during man entry for inspection or maintenance and would result in potential
odour emissions.
3.8.2.7 For the purpose of this assessment, two operation scenarios namely the
unmitigated and the mitigated scenarios were considered and assessed with the
odour dispersion model. In the unmitigated scenario, it was assumed that all
major odour sources within the proposed expanded Ha Tsuen Pumping Station
namely the existing and the new wet wells would be open to the atmosphere. All
H2S emissions would be dispersed directly from the sources at ground level.
3.8.2.8 In the mitigated scenario, it was assumed that the existing and the
new wet wells would be contained within building structures. All the odour
emissions from the wet wells would be ventilated to a deodoriser located at
the rooftop of the existing and the new pumping stations. In this assessment,
it is estimated that an H2S removal efficiency of up to 97% would be required
for the deodorisers so as to achieve the 5 OU criteria at all the ASRs. All
the treated air would be emitted from the exhaust vent of the deodorisers with
exhaust heights of 4m and 8m above ground for the existing and new wet wells,
respectively, and with an exit velocity of 8m/s.
3.8.2.9 The worst-case 5-second average odour levels were calculated at the
assessment points in the vicinity of the proposed expanded Ha Tsuen Pumping
Station as shown in Figure 3.2. The assessment heights were taken as 1.5m to
30m above local ground level to represent the worst affected heights. The
modelling results for the unmitigated and mitigated scenarios at the
assessment points are shown in Tables 3.12 and 3.13 respectively.
A1 90.7 84.4 60.5 47.5 40.0 32.0 26.5 23.7 21.1 19.6 18.2 16.7 15.2
A2 67.4 63.0 46.9 40.5 34.8 28.7 23.5 21.3 19.0 17.6 16.5 15.3 14.2
A3 73.4 66.7 42.6 32.6 28.5 27.0 25.3 23.4 21.4 19.4 17.3 15.3 13.3
A4 31.5 30.2 24.9 18.8 17.0 15.0 13.5 12.8 11.9 11.1 10.7 10.2 9.8
A5 54.0 50.3 36.2 26.0 22.0 20.4 19.6 18.6 17.6 16.5 15.3 14.1 12.9
A6 105.6 90.3 68.3 52.5 46.1 41.7 37.8 33.8 29.7 25.6 21.8 18.3 15.1
A7 119.8 100.5 64.0 46.5 43.1 39.1 34.8 30.3 25.9 21.6 17.8 15.9 14.1
A8 88.7 78.8 47.3 38.1 33.4 31.2 28.6 25.8 22.9 20.1 17.3 14.7 13.0
A9 27.2 26.7 24.3 20.8 16.7 13.0 12.1 11.1 10.1 9.0 8.0 7.0 6.4
A11 53.6 50.0 36.3 31.0 26.6 22.4 20.6 18.7 17.5 16.6 15.5 14.5 13.4
A12 40.8 38.6 29.9 25.8 22.8 19.5 17.3 16.0 14.7 13.9 13.2 12.5 11.7
A43 95.5 88.6 62.4 48.7 40.8 32.5 27.0 24.0 21.4 19.9 18.4 16.9 15.3
A44 114.9 103.0 85.2 64.7 55.0 49.6 43.9 38.0 32.3 26.9 22.1 17.8 15.5
A45 193.8 156.6 98.8 77.2 63.0 48.7 37.0 30.6 24.7 19.5 15.3 11.9 9.2
A46 174.1 129.2 90.7 62.5 51.6 42.3 33.2 26.7 21.9 17.6 13.7 10.5 7.8
A47 129.2 106.7 69.3 50.0 45.9 41.3 36.2 31.0 26.1 21.5 18.2 16.1 14.1
A48 164.1 123.2 88.7 75.3 66.4 56.5 46.8 37.6 29.4 23.9 20.2 16.8 13.8
A49 298.1 266.6 170.8 133.8 105.8 79.4 57.1 39.9 31.0 23.7 18.0 13.6 10.3
A50 165.3 141.5 101.3 88.8 76.6 63.6 51.1 39.8 30.1 24.7 20.3 16.4 13.2
https://www.epd.gov.hk/eia/register/report/eiareport/eia_0862002/EIA main report/section3.htm#3. AIR QUALITY IMPACT 24/29
12/29/22, 2:13 AM 3
A51 87.8 77.6 49.7 39.8 35.4 33.3 30.8 28.1 25.3 22.5 19.7 17.1 14.6
Highest 298.1 266.6 170.8 133.8 105.8 79.4 57.1 39.9 32.3 26.9 22.1 18.3 15.5
% Criteria 5962% 5332% 3416% 2676% 2116% 1588% 1142% 798% 646% 538% 442% 366% 310%
1.5m 2.5m 5m 7.5m 10m 12.5m 15m 17.5m 20m 22.5m 25m 27.5m 30m
A1 0.5 0.5 0.5 0.5 0.8 1.0 1.2 1.2 1.1 0.8 0.5 0.5 0.5
A2 0.5 0.5 0.5 0.5 0.6 0.8 0.9 0.9 0.8 0.6 0.5 0.5 0.5
A3 0.5 0.5 0.5 0.5 0.7 0.9 1.0 1.0 0.9 0.7 0.5 0.5 0.5
A4 0.3 0.3 0.3 0.3 0.4 0.4 0.4 0.5 0.4 0.4 0.3 0.3 0.3
A5 0.4 0.4 0.4 0.4 0.5 0.6 0.7 0.8 0.7 0.6 0.4 0.4 0.4
A6 0.6 0.6 0.6 0.6 0.9 1.3 1.5 1.3 1.0 0.8 0.8 0.8 0.8
A7 0.5 0.5 0.5 0.5 0.9 1.4 1.6 1.4 1.2 0.9 0.7 0.7 0.7
A8 0.5 0.5 0.5 0.5 0.7 1.1 1.2 1.2 1.2 0.9 0.6 0.6 0.5
A9 0.2 0.3 0.3 0.3 0.4 0.4 0.4 0.4 0.4 0.3 0.3 0.2 0.2
A11 0.4 0.4 0.4 0.4 0.5 0.6 0.7 0.8 0.7 0.6 0.4 0.4 0.4
A12 0.4 0.4 0.4 0.4 0.4 0.5 0.5 0.6 0.6 0.5 0.4 0.3 0.3
A43 0.5 0.5 0.5 0.5 0.8 1.2 1.3 1.3 1.1 0.8 0.5 0.5 0.5
A44 0.6 0.6 0.7 0.7 0.9 1.5 1.7 1.4 1.2 1.0 1.0 1.0 1.0
A45 0.6 0.6 0.6 0.8 1.2 2.1 2.6 2.1 1.9 1.3 1.3 1.3 1.2
A46 0.5 0.5 0.5 0.7 1.1 1.9 2.3 2.4 2.2 1.4 1.1 1.1 1.1
https://www.epd.gov.hk/eia/register/report/eiareport/eia_0862002/EIA main report/section3.htm#3. AIR QUALITY IMPACT 25/29
12/29/22, 2:13 AM 3
A47 0.5 0.5 0.5 0.5 0.8 1.2 1.3 1.8 1.7 1.2 0.8 0.8 0.8
A48 0.6 0.6 0.6 0.6 0.9 1.4 1.7 2.3 2.2 1.4 1.2 1.2 1.2
A49 0.7 0.7 0.8 1.0 1.1 2.1 3.3 4.0 3.4 2.1 2.4 2.5 2.4
A50 0.6 0.7 0.7 0.7 0.9 1.4 1.7 2.5 2.3 1.4 1.4 1.5 1.4
A51 0.5 0.5 0.5 0.6 0.7 0.9 1.0 1.2 1.2 0.9 0.6 0.6 0.6
Highest 0.7 0.7 0.8 1.0 1.2 2.1 3.3 4.0 3.4 2.1 2.4 2.5 2.4
% Criteria 14% 14% 16% 20% 24% 42% 66% 80% 68% 42% 48% 50% 48%
or better. The exhaust height and exit velocity of the treated air should not
be less than 5m and 10m/s respectively.
3.9.2.3 For the proposed expanded Ha Tsuen Pumping Station, it is recommended
that the air ventilated from the existing and the new wet wells should be
treated by deodorisers with a H2S removal efficiency of 97% or better before
discharge to the atmosphere. The exhaust of the deodorisers should be located
on the rooftop of the pumping station and the exit velocity of the treated air
should not be less than 8m/s.
3.9.2.4 The two likely technologies for deodorization to be adopted for this
project would be adsorption of odorous chemicals by granulated activated
carbon (GAC) and scrubbing of odorous air stream with chemical oxidants in a
chemical scrubber. For example, chemicals such as sodium hydroxide, chlorine
solution, and sodium hypochlorite etc are commonly used in scrubbers to
oxidise odorous chemicals such as hydrogen sulphide and mercaptans.
3.9.2.5 A simple comparison of the operational characteristics of the two
technologies, based on some manufacturers' information, are summarised in
Table 3.14 below.
Granular Chemical
Activated Scrubber
Carbon
Absorb +
Adsorb odorous neutralise
Approach
compounds odorous
compounds
Single / multi
Mode of Single / multi stage; packed
operation stage bed / sieve
tray
Preferably low
Large (ranged
range for each
Air flow range from 0.05 to 30
unit (0.1 to 1
m3/s)
m3/s)
Typical H2S
>99.7% (minimum >99.5% (minimum
removal of 99%) of 98%)
efficiency
space
requirement