You are on page 1of 1

COMPLETION FOR WORK FROM HOME

APRIL 16 SATURDAY

CONTACT JEBREN FOR THE SCHEDULE OF ARENAS TEAM DMCI MATERIALS , DMCI
FABRICATION ALSO JACKS TEAM FOR THE AEROPACK FABRICATION AT MATERIALS UPDATE AND
MONITOR THE TURRET,SHEARING AND BENDING FOR THE DMCI AND AEROPACK MATERIALS.
ANSWER THE QUESTION OF JEBREN FOR THE CUTTING LIST OF A7 AND THE JAMB
PROFILE FOR THE FIX AND LOUVER DOOR FOR A7 DEMOUNTABLE FIX LOUVER.
CONTACT KUYA JACK IF HE HAS MATERIALS FOR A7 DEMOUNTABLE LOUVER AND
ANSWER HIS QUESTION FOR THE PROFILE IF THE JAMB IS SINGLE RABBET OR DOUBLE RABBET JAMB.
CHECK AND APPROVED ALL REQUEST FOR THE VISITA APPLICATION.

APRIL 17 SUNDAY

MESSAGE JEBREN FOR THE UPDATE OF ARENAS AND MACHINE OPERATOR OUTPUT
AND IF JACK TEAM HAS ALREADY A MATERIALS FOR AEROPACK ALSO UPDATE JEBREN TO FINISH THE
JAMB OF AEROPACK METAL DOOR SO THAT MONDAY MORNING GENERAL ASSEMBLY ALREADY HAS
THE JAMB.
UPDATE JEBREN THAT WE HAVE SCHEDULE FOR PARTIAL DELIVERY ON WEDNESDAY
FOR AEROPACK DEMOUNTABLE LOUVER (JACKS TEAM) AND PARTIAL DELIVERY FOR METAL DOOR
(GENERAL ASSEMBLY).
REVIEW ALL SHOPDRAWING BEFORE MAKING A CUTTING LIST BEFORE SENDING IT
JEBREN (PREMIUM AND NATURA,AEROPACK A3 AND DMCI ASTON).
WENT TO OUR MUNICIPAL COUNCILOR TO HAVE A SCHEDULE MEETING FOR THE
PROPOSED ROLL UP AND METAL DOOR IF INCASE HE WILL HAVE PROJECT.

APRIL 18 MONDAY

UPDATE BOSS REYNARD FOR AEROPACK PROJECT.


CHECK EMAIL FOR NEW PROJECT MAKE CUTTING LIST FOR AEROPACK A3 METAL
DOOR AND DMCI ASTON AND SEND IT TO JEBREN VIA MESSENGER .
I REQUEST SIR MIKE TO RESEND AEROPACK A1 LO2 FIX LOUVER VIA MESSENGER
AND MAKE CUTTING LIST TOMMOROW I WILL SEND IT TO JEBREN.
ANSWER JEBREN QUESTION FOR THE CHINA DOOR .915M ANSWER BOSS RUDOLF
CALL FOR THE PICK UP OF ARCH GERALD ROMAN METAL DOOR AND UPDATE JEBREN FOR THE SAID
PROJECT FPOR HIM TO BE NOTIFIED.
ASK JEBREN TO SEND THE PRODUCTION REPORT FOR ME TO MAKE A REPORT AND
SEND TO HR MAAM RAZZEL EMAIL.
CHECK THE FBI REPORT OF SIR MIKE ABOUT THE ERROR OF METAL DOOR
AEROPACK B3 PROJECT.
HOLD THE A1 (LO1,LO2) FIX LOUVER AS PER ADVISE OF SIR MIKE AND NOTIFIED
JEBREN TO HOLD THE SAID PROJECT.
ANSWER SIR MIKE ABOUT THE ERROR OF B3 THAT HE IS THE ONE WHO CHANGE
THE MEASUREMENT OF THE DOOR AND THAT IS NOT OUR FAULT.
ANSWER ALL QUESTION OF SIR MIKE VIA MESSENGER.
HAVE A MEETING TO OUR MUNICIPAL COUNCILOR AND PROPOSED TO HIM OUR
PRODUCT (CITY SHUTTER) FOR HIS FUTURE PROJECTS.
CHECK AND APPROVED ALL REQUEST FOR THE VISITA APPLICATION.

BENZAR E. MISLANG