You are on page 1of 16

COMPARISONAL ANALYSIS OF CONVENTIONAL AND TELESCOPIC CANOPY

COLUMN CONSTRUCTION METHODS ON THE CANOPY FOURCOURT PROJECT


SHELL SPBU GRAHA RAYA TANGERANG
Aditya Nurfajri
Civil Engineering Study Program, Faculty of Engineering, Mercubuana University
Email : adityanurfajri508

construction system with steel as the main element @gmail.com. standard wf that we usually
encounter in the market which is heavier than non prismatic which is then fabricated in the field.
This method has been widely applied in the implementation of steel construction. Along with the
development of technology and innovation in the field of construction, there are other alternative
construction methods that have been developed to produce cheaper steel construction, efficient
and fast implementation by minimizing the risk of errors (accuracy), as well as producing an
erection method that is carried out in stages, relatively easily and quickly. The method that can be
applied is called the steel construction system of the telescopic canopy column with the pre-
engineering building method. The aim is to compare conventional steel construction methods and
pre-engineering buildings with a telescopic canopy column system from the aspect of cost and
time. The project that is used as the object of research is the Construction of the Fourcourt
Canopy of Shell Graha Raya Taangerang gas stations. Each method will be calculated cost and
implementation time based on the technical implementation of the method. From the comparison
results, the cost and time required for conventional steel canopy construction methods and pre-
engineering building telescopic systems will be obtained.

Keywords: Steel construction, Pre-engineering Building Telescopic Canopy Column,


Conventional,

1. INTRODUCTION

Background
The latest innovations in steel construction Fourcourt gas stations. The Telescopic
are needed along with the development of Canopy Column work method uses a
technology in the construction world. This Hydrolic Jacking system with the main
innovation is better known as the Telescopic column material using hollow steel plates
Canopy Column steel construction with the which are made to reduce work execution
Pre-Engineering Building method. Steel time, costs and increase work safety factors
construction generally uses a conventional for workers involved in the construction of
steel construction system, namely H-Beam the construction.
profile steel as a column structure material By using the Telescopic Canopy Column
and other profile steels such as WF and steel construction, time and cost control
Canal C as beams and horses. - horses on the becomes significant because the design is
roof. The construction is usually applied to made to minimize structural weight
office buildings, factories, warehouses, efficiency and relatively faster execution
stadiums, four-court gas stations and so on. time and reduce the duration of use of heavy
In this era, conventional steel buildings have equipment, especially mobile cranes, it
been gradually abandoned due to efficiency becomes a differentiator from conventional
in time, cost and work safety when steel construction which tends to
compared to using Telescopic Canopy maximizing the weight of the structure and
Column steel structures in general for the relatively longer use of heavy equipment,
1
so that from the total workload incurred it canopy column and conventional systems at
can reduce the cost of steel per kilogram the Shell Graha Raya Tangerang gas station
which is currently relatively high due to the fourcourt building.
unstable global economic market. At the 3. Knowing the comparison of each
time of erection the structure also gives an method of construction implementation on
impact that is relatively faster than the safety factor of workers and the tools and
conventional steel construction, because the materials used.
fabrication has been carried out at the
manufacturer, so that the steel material can Scope and Limitation of Problems
be erected immediately upon arrival at the Based on the above scope, there are several
project site. problems that are reviewed & can be
Compared with conventional steel formulated as follows:
construction systems with universal 1. Job analysis data is job analysis data
architectural designs, using Telescopic belonging to PT. Prima Sukses Bersama As
Canopy Column steel construction, the the contractor implementing the project.
desired use of steel materials can be realized 2. Calculation of the analysis of the
in such a way, because fabrication is carried steel structure of the fourcourt canopy is
out using the Pre-Engineering Building carried out with manual calculations and
system, namely the building has been application assistance
engineered before the work is carried out. . 3. Calculation of the analysis of the
steel structure only counts up to the stage of
Problem Formulation the roof work.
From the above background, the problems 4. The review is only carried out from
that will be discussed in this final project can the pedestal structure of the column to the
be formulated, namely: roof.
1. How much time is needed for each 5. Does not calculate the volume of
method of implementing the telescopic excavation and foundation piles.
canopy column and conventional systems in
the fourcourt building of the Shell Graha 2. LITERATURE REVIEW
Raya Tangerang gas station?
2. Calculate the costs required for each Overview
method of implementing the telescopic The definition of steel construction Pre-
canopy column and conventional systems at Engineering Building System especially
the Shell Graha Raya Tangerang gas station Telescopic Canopy Column is an
fourcourt building? engineering concept in the world of steel
3. Comparing each implementation construction where the fabrication work is
method to the safety factor of the workers carried out in a workshop with adequate
involved and the tools and materials used? production machine technology in terms of
quality and time. The main structural
Research Objectives components are also
Based on the formulation of the problem, the
objectives of this research are as follows:
1. To determine the time required for
each method of implementing the
conventional and telescopic canopy column
systems in the fourcourt building of the Shell
Graha Raya Gas Station Tangerang.
2. Knowing the costs required for each
method of implementing the telescopic
1
designed as efficiently as possible according Look at Figure 2.1, the bottom end of the
to the load and function requirements of a column is smaller than the top end because
building. the bottom moment is smaller, thus saving
This Pre-Engineering Building system was steel material and of course it will be lighter.
developed to produce steel construction that Such a profile is called a Tempered Profile.
is cheaper, efficient and fast implementation This tempered profile is not produced hot
with minimal risk of error (accuracy), and rolled like the standard hot rolled material
produces an erection method that is carried that we usually find in the market. This
out in stages, relatively easily and quickly. tempered profile is formed by combining 3
The connection of components during plate materials that are assembled into
erection is carried out without welding and tempered components.
does not require experienced experts, Whereas in conventional steel construction
because the Pre-Engineering Building systems, the fabrication work is carried out
system is equipped with an erection guide in the field with the main material used in
manual. So that costs can be known more the form of hot rolled material or commonly
accurately and economically. In general, this called the WF profile. This is something we
method can save 10%-15% of development usually encounter in steel construction
costs. buildings that already exist in general.
In the manufacture of steel construction Pre-
Engineering Building Systems, Pre- Differences in Pre-Engineering Building
Engineering Building System steel System Steel Construction Design with
construction manufacturers play an Conventional Systems
important role in steel construction
engineering which includes design with
reference to design standards (AISC,
MBMA, AWS, AISI, & JIS), drawings,
fabrication, and erection guide manual.
So the understanding of steel construction
Pre-Engineering Building is the pre-
fabrication of the building where the overall Figure 2.2. Differences in Pre-Engineering
design requirements of the building have Construction System Design with
been prepared in advance in the form of a Conventional Systems
Standard building. Then designed with a
complete building standards and the most Pre-Engineering Building Method
economical. The steel material in this 1. Look at Figure 2.2, the main element
concept is designed based on the need for uses non-prismic rods so that its own weight
moment distribution (BMD) on the rigid is 30% lighter.
frame frame due to the working loads. 2. Secondary elements use mild steel in
the form of Z-Section or Lip-Channel.
3. The foundation design is simpler and
lighter and easier to implement.
4. The construction weight is relatively
light so that the cost of steel is cheaper.
5. Seismic Resistance The structure of
the portal is more flexible to withstand
earthquake loads.
Figure 2.1. Moment distribution on the rigid
frame frame due to working loads.

3
6. Erection is easy, fast and done
gradually. The connection of components Cranes
during erection is carried out without Cranes are heavy equipment for vertical
welding and does not require experienced transport or lifting equipment commonly
experts, because the PRE-ENGINEERED used in construction projects. The crane
BUILDING is equipped with an erection works by lifting the material to be moved
guide manual. So that costs can be known vertically, moving it horizontally, then
more accurately, in general it can save 10%- lowering the material to the desired place.
15% of development costs. Cranes have several types which in operation
7. The volume of the foundation is are selected according to the conditions of a
lighter (5% to 10%). because the weight of project. The types of cranes commonly used
the superstructure is accurate according to are:
the design. a) Crawler wheeled cranes
b) Truck cranes
Conventional Method c) Truck cranes for limited locations
1. Look at Figure 2.2, the main element d) Truck cranes for all types of
is the hot roller wf which is heavier than non locations
prismatic. e) Tower cranes
2. Secondary elements use I or Lip- .
Channel profile steel which is relatively
heavier. Productivity of Heavy Equipment
3. Foundations are expensive and Productivity or equipment capacity is the
required to use a deeper foundation. amount of output (output) of a certain
4. The construction weight is relatively volume of work produced by the tool per
heavy so that the cost of steel is more unit time. To estimate the productivity of the
expensive. tool, it takes the performance of the tool
5. Seismic Resistance The structure of provided by the tool manufacturer and the
the portal is heavier and stiffer and behaves efficiency factor of the tool, operator, field
poorly in earthquake areas. conditions and materials (Rostiyanti 2008).
6. A lot of erection labor is required and Tool productivity is calculated based on the
expensive. Time and cost are required to volume per cycle time and the number of
obtain accuracy and uniformity in erection. cycles in one hour.
A lot of time consuming so that it can Q = qx N x E ..........................pers. (1)
exceed the time schedule of work and costs. Where :
7. Requires a heavier foundation. Q = production of tools per hour
(m³/hour)
Heavy Equipment in Steel Construction q = production of tools per cycle
Work (m³/cycle)
Heavy equipment has an important role in E = efficiency of working time
the implementation of construction projects, (effective working time/60)
especially large-scale projects. The purpose N = number of cycles per hour, namely:
of using these heavy equipment is to .. .................................................pers . (2)
simplify the work process so that the Ws = cycle time (minutes)
expected results can be achieved more easily Thus, tool productivity can be calculated by:
in a relatively shorter time. Q = .......................... ..........pers. (3)
Heavy equipment that is generally used in
steel construction work is erection tools
(cranes), trucks or loaders for transportation
equipment (Rostiyanti 2008).
4
The definition of cycle time is the time used actualization of work in the field. By
by a machine (vehicle) to undergo a cycle of knowing the volume of work, it will be
work. For example, a crane has a working known how much cost is required in the
mechanism cycle as follows: lifting implementation of the construction.
mechanism - rotary mechanism - walking
mechanism (to put or lower the load. Work Unit Price The work
The cycle time consists of: unit price is the sum of prices, materials and
Fixed time: It is the time for lifting, turning, labor wages based on analytical calculations.
walking, putting or lowering the load, and so The price of materials obtained in the
on - other things, of course. So fixed time is market, collected in a list called the unit
not affected by the distance of the haul. price list of materials. Wages for labor
Variable time : Represents the time it takes obtained at the location are collected and
to walk and rotate in an empty state. recorded in a list called the unit price list of
Variable time = wages. The unit prices of materials and labor
Where : wages vary in each region. So in calculating
V = Speed when walking carrying loads and compiling the budget for a project, it
So cycle time = fixed time + variable time must be guided by the unit price of materials
Each heavy equipment has a specific and labor wages on the market and at the job
productivity according to its production site. Usually the executor or contractor
capacity makes a separate unit price of work that is
adjusted to the market price where the
Cost Analysis project is carried out.
Before a construction project begins, it is
necessary to carefully estimate the costs to Direct Costs
be incurred for the project, hereinafter According to Asiyanto (2003) direct costs in
referred to as the Cost Budget Plan, project costs are costs incurred for activities
according to Ibrahim (2001) the plan Cost that are directly related to the project in
budget is a calculation of the amount of costs question which results in permanent physical
a required for materials and wages, as well construction. This direct cost is dominant to
as other costs associated with the the total cost. The main components of direct
implementation of the building or project. costs are material, labor, and equipment
The cost budget plan is calculated based on costs.
the volume of each type of work multiplied a) Material costs The
by the unit price of each work, and
calculated for all types of work carried out
on a construction project, so that the total
cost of the overall budget plan can be
obtained. The unit price of work consists of
material costs, labor costs, and equipment
costs where these costs include direct costs
in a project.

Work Volume
Calculation of work volume is the most
important part in the planning stage of a
construction project. Calculation of the
volume of construction work is a process of
measuring/calculation of the quantity of
work items based on drawings or
5
price or materials used for the construction To get worker productivity, it is usually
implementation process, which includes obtained by dividing the worker coefficient
packing costs, transportation costs and contained in the unit price analysis by the
temporary storage costs in the warehouse. volume of work. Meanwhile, to find tool
b) Labor productivity, each tool has its own
Costs Costs paid to workers in completing a productivity according to the type of heavy
type of work in accordance with their skills equipment.
and expertise
c) Equipment 3. LITERATURE REVIEW
Costs The costs required for rental,
transportation, installation of equipment, and Research Design
operating costs can also be included in In this research design, the researcher wants
wages from machine operators. to know and analyze the comparison of the
size and dimensions of WF steel with the
Scheduling effect of the same load on the work of the
Scheduling in construction projects is a tool Fourcourt Canopy structure of telescopic
to determine the activities needed to columns and WF Steel horses at Shell Graha
complete a project in a certain sequence and Raya Tangerang. The data collection method
time frame, in which each activity must be is by analyzing the Shell Graha Raya
carried out so that the project is completed Tangerang Work Project Data. The data
on time at an economical cost (Irika & analyzed in the form of AsBuilt Drawing
Lenggogeni 2013). documents, RAB and Material
From the scheduling we will get an overview Specifications obtained from the Shell Graha
of the length of work that can be completed, Raya Tangerang NTI Work Project. What
as well as the parts of the work that are will be reviewed is the main part of the
interrelated with one another. Scheduling is telescopic column steel canopy structure, the
done by determining the sequence in which WF canopy roof structure includes gording,
activities are started, postponed, and fascia, beams, horse connections and the cost
completed so that the cost and resource of working on the WF steel canopy structure.
usage requirements are adjusted according to
the needs and implementation time. Research Steps
In this research methodology chapter, the
Time and Activity Duration steps that will be taken during the
In scheduling there are two differences, preparation of the Final Project on
namely time and duration. If the time shows "Comparative Analysis of Costs & Time for
day/night, while the duration shows the Steel Construction Buildings Using Pre-
length of time working in one day, for Engineering Building Systems and
example one working day is 8 hours. Conventional Systems in the Shell Graha
Determining the duration of the activity is Raya Gas Station Fourcourt Project" are
usually based on the volume of work and the described. used as a frame of reference
productivity of workers/tools in completing during conducting research.
a job. For example, the productivity of a
group of workers to do brick wall work is 10
m2/day, while the volume of brick wall work
is 320 m2.
Duration of brick wall work = work
volume / productivity = 320 m2/10 m2/day =
32 days

6
Research Analysis of implementation costs for each
Data Primary method is calculated by analyzing the costs
Data Data obtained from the results of direct incurred from:
observations and observations in the field in A. Pre-Engineering Building Method:
the form of location, location conditions, 1. Fabrication process outside the
building conditions around the location. project
2. Erection process
Secondary B. Conventional Method
Data Supporting data used in the preparation 1. Fabrication process inside project
and preparation of the Final Project both 2. Erection process The
from the field and from the existing requirements for calculating the required
literature. This data cannot be used directly cost are: Work Cost : material volume x
as a source but must go through a data volume unit price (manufacturing + erection)
processing process to be used. The the cost is obtained from the offer of the
secondary data used in the preparation of work price from the bidding contractor.
this Final Project report are: Cost analysis is needed to prepare a budget
a. Drawings of plans for steel plan in order to find out the amount of costs
construction buildings using the pre- required for each method and to determine
engineering building method and the amount of budget needed in
conventional methods for the telescopic implementing the project.
canopy column fourcourt project at the Shell
Graha Raya gas station Analysis of Implementation Time
b. Unit price of work Analysis of the execution time of each work
c. Project Scheduling activity for both methods is calculated by
analyzing the amount of time required from
Data Analysis the following activity stages:
Analysis of Implementation Methods A. Pre-Engineering Building Method:
Prepare an outline of the stages of 1. Fabrication process outside the
implementing steel construction works for project
pre-engineering building systems and 2. Erection process
conventional systems as well as analyzing B. Method Conventional
the activities of each work. The analysis of 1. Fabrication process in the project
implementation methods becomes the basis 2. Erection process
for calculating the cost and implementation The amount of time required can be
time for each method. calculated by dividing the volume of work
For the pre-engineering building system by the value of the productivity level of
because the steel construction work begins workers/tools.
with the fabrication of the building where
the overall design requirements of the 4. RESULTS AND ANALYSIS OF
building have been prepared in advance in
the form of a Standard Building. Then it is Building Data
designed with complete building standards. In this Shell Graha Raya Tangerang gas
The steel material in this concept is designed station construction project, with a building
based on the need for moment distribution dimension of 21.6 mx 18 m, data analysis of
(BMD) on the rigid frame frame due to implementation methods, costs and time
working loads. Steel profiles like this are
commonly called tempered steel profiles.

Analysis of Implementation Costs


7
for steel construction buildings was carried the stages of steel construction work using
out using the pre-engineering building tcc conventional systems are described. The
system and conventional systems. stages of the work can be seen in the flow
The steel construction design for the pre- chart of Figure 4.20 below.
engineering building system starts from the
drawing proposal along with the building
concept submitted by the owner to the
contractor to be forwarded to the pre- Figure 4.20. Flowchart of Stages of Steel
engineering building system steel Construction Work Conventional System
construction manufacturer who has been
appointed or recommended by the owner or Cost Analysis
contractor for detailed design using software In this cost analysis, the calculation of costs
design assistance. computer programs such is obtained after calculating the volume per
as the 2016 ETABS program, Tekla and work item. To calculate this, data such as
STAADIII. plan drawings of work items are needed.

Analysis of Implementation Methods Calculation of Steel Construction Volume


Analysis of Steel Construction of Pre-Engineering Building System.
Implementation Methods with Pre- Volume calculation is carried out on each
Engineering Building Systems Steel item of steel construction building
construction of pre-engineering building components. The result of calculating the
systems found in the Shell Graha Raya volume of all material items will be a
Tangerang gas station construction project, variable in the calculation of the budget plan.
the implementing contractors use steel From the tcc design of the pre-engineering
construction with pre-engineering building building system, the volume that will be
systems by appointing construction calculated is the volume of the weight of the
engineering project consultants companies steel material from each component item,
steel pre-engineering system as a consultant which will then know the total weight of the
who is a consultant for steel construction material from the design produced by the
planners using the Pre-engineering Building pre-engineering building system. From each
System. The steel engineering consultant component item produced, the volume
company is called Akanksha Promoters (I) weight calculation will be carried out as
Pvt.Ltd, which has its address at MP Nagar below.
Bhopal, India. The stages of steel
construction work using the pre-engineering
building system can be seen in the flow chart
of Figure 4.5 below.

Figure 4.5. Flowchart of Steel Construction


Work Stages Pre-engineering Building
System

Analysis of Steel Construction


Implementation Methods With
Conventional Systems
In the analysis of the conventional system
steel construction implementation methods,

8
Table 4.1. Total Volume of TCC Steel
Construction Materials Pre-engineering
building system

Budget Plan The


Budget Plan (RAB) is a recapitulation of the
Calculation of Conventional System Steel costs of all work. This RAB is calculated by
Construction Volume multiplying the volume of each work item
In the conventional system steel construction with the work unit price that has been
design, steel construction materials use determined based on the reference unit price
profile steel or commonly called hot rolled of wages and materials from the steel
WF steel as shown in Figures 4.27 and 4.28. construction work offer document by the
produced conventional system steel contractor implementing the Shell Graha
construction buildings. Raya Tangerang TCC Development Project.
The price offer includes the cost of erection
of the steel construction.
The Budget Plan for each method can be
seen in Table 4.5 for the pre-engineering
building system and Table 4.6 for the
conventional system.

Figure 4.27. Hot rolled steel profile on Table 4.5. TCC Pre-Engineering Building
conventional system steel construction System Budget Plan
building components

Figure 4.28. Standard Structure of Fourcourt


Gas Station Shell

Table 4.4. Total Volume of Conventional Table 4.6. Budget Plan Conventional System
Steel Construction Materials Fourcourt Gas
Station

9
- Production capacity per day = 840
tons / 365 hr
= 2.3 tons / hr
= 2300 kg/hr
Volume requirements for steel construction
systems for pre-engineering building
systems.
- Volume = 14300 kg
- Time of fabrication work = Vol. /
Production capacity/hr
Time Analysis = 14300 kg / 2300 kg/hr
of TCC Steel Construction Pre- = 6.21 hr 7 hr
Engineering Building System b) Material Delivery Work
Implementation In this material delivery job, the material
time analysis of TCC steel construction pre- delivery time is calculated starting from the
engineering building system is divided into material that has been fabricated in the
the following stages of work. workshop and sent until it arrives at the
a) Pre-Fabrication project location , the procurement of steel
Work In this work, steel construction is construction materials for the pre-
fabricated in the workshop using tempered engineering building system is carried out by
steel production machines. The contractors using locally produced steel
manufacturing process is carried out by a materials that are sent in standard factory
steel construction manufacturer with a pre- shapes and sizes to be sent to the contractor's
engineering building system with an workshop for fabrication.
engineering service center that provides Based on the analysis of the implementation
standard product components for steel time of material work in the field, the
structure standards. By using machines and following table 4.7 stages and calculation of
production equipment to support steel material delivery work time.
forming, the workshops are carried out as
follows: Table 4.7. Analysis of Delivery Time for
1. Cutting Steel Construction Materials for Pre-
2. Befalling Engineering Building Systems
3. Notching
4. Drilling
5. Bending
6. Assembling
7. Finishing
8. Welding
9. Shot blasting
10. Paint (painting)
From a series of pre-fabricated works, it was From the analysis of delivery times for steel
found that the production capacity in the construction materials for pre-engineering
steel construction manufacture is 840 tons building systems in table 4.7, it is found that
per year. The following is the calculation of the total time for material delivery work is 5
the pre-engineering building system steel days.
construction work time. c) Erection Work
- Production capacity = 840 Time analysis on erection work is carried out
tons/year to determine the value of productivity and

10
duration. This analysis is carried out through - Mobile crane speed = 50 km/h
field observations. (travelling)

Another consideration that underlies the use


of field observations is that the data obtained
is more accurate in accordance with field
conditions.
In this erection work, the heavy equipment
used is 1 unit of rough terrain crane. The
following is the plan for the heaviest and
tallest building materials to determine the
specifications of mobile mobile cranes in Figure 4.30. Dimensions of Mobile Crane
erection work. Tadano Type GR-500XL
Building data:
- Column height= 5.25 m From the calculation of erection work time,
- Rafter length = 9 m the total duration of erection work for steel
- Rafter weight (1frame) = 603.4 construction materials tcc pre-engineering
kg building system using mobile cranes in the
- Weight of 1 column = 636.7 kg lifting zone is as follows.
Mobile crane specifications: Total duration of the zone = 857.327 min
- Brand/Type = TADANO = 14.28 hours
- Model = GR-500XL After knowing the total duration of the
- Max Lifting Capacity = 50 Ton x 3.5 erection cycle with mobile mobile cranes in
m the lifting zone, a recapitulation of the
- Boom angle change motion = 0°- effective use of mobile cranes with mobile
80° crane operating hours of 6 hours/day will be
- Change movement time = 51 obtained. as follows:
sec (0°-80°) Total minutes = 857.327 min
boom angle = 1° = Total hours = 14.28 hours
0.011min Total days = 2.38 days
- Time movement change length = 133 Rounding = 3 days
sec/17.42 m The total duration of steel construction work
(telescopic) boom = 7.85 for pre-engineering building systems is as
m/min follows.
- Speed of main hoist line (6 part line): d) Hydraulic Jacking Up Work
Time analysis on hydraulic jacking up work
is carried out to determine the value of
productivity and duration. This analysis is
carried out through field observations.
Another consideration that underlies the use
of field observations is that the data obtained
is more accurate in accordance with field
conditions.
Figure 4.29. Hoisting Specification In this hydraulic jacking up work, the tools
used are 1 set of hydraulic jack tcc machines
- Max boom length = 33.3 owned by the implementing contractor.
m
- Swing speed = 2.7 rpm =
972°/min
10
From the calculation of hydraulic jack
capacity, it can be seen the composition and
the working mechanism of hydraulic jacks
and followed by observations of work time
in the field as the basis for calculating the
hydraulic jack cycle time in steel
construction work with pre-engineering
building systems.
The following is an example of calculating
the hydraulic jack work time on the TCC
Figure 4.37. Hydrolic Jack Specifications Shell Graha Raya Tangerang Project.
Hydraulic Jacking Up Fourcourt Gas Station
Time analysis on hydraulic jacking up work Shell
is done to determine the value of - Setting the engine position
productivity and duration. This analysis is (t1) = 60 minutes
carried out through field observations. - Installing the hydraulic tube into the
Another consideration that underlies the use column (t2) = 15 minutes/ column
of field observations is that the data obtained
is more accurate in accordance with field = 75 minutes for 5 columns
conditions. - Setting Hose and Safety Valve
Building data: (t3) = 5 minutes/ column
1 Hydraulics can be jacked up in 4 stages
with the maximum load of each jack listed in = 25 minutes for 5 columns
the Max Thrust (kg) table above. - Hydraulic Jack Up process
The Hydraulic Jack can open 5000 mm (t4) = 8 cm/minute
above the lowest pipe which is 6540 mm in
total open length. But in the field it will use = max height of fourcort
a maximum of 4500 mm (69%) of the 3.55m
maximum potential thus, the jack will only
open up to stage 3. Maximum thrust of stage = 355/8
3 = 12,591 kg.
The total weight of the fourcourt = 44.4 minutes / column
construction: 21215.46 kg (with the For hydraulic jack process it can be done by
distribution as below). jacking up 3 columns simultaneously So,
• Weight of steel structure = assuming a total of 5 columns in the project,
14345.46 kg the hydraulic jack process can be carried out
• Roof weight = 1983 kg in 2 alternating cycles, i.e. 44.4 minutes
• Ceiling weight = 4887 kg multiplied by 2 cycles = 88.8 minutes
From the above data we can analyze the
safety factor for hydraulic jacks, in this Release of hydraulic jack tube
project 5 hydraulic jacks are used which lift (t5) = 15 minutes / column
the canopy with each each jack has a
capacity of 12,591 kg. So, the total lifting = 75 minutes for 5 columns
capacity of 5 jacks = 5 x 12,591 = 62,955 kg , the results obtained are the duration of
SWL = 62,955 x 80% = 50,364 kg usage as follows:
Weight of structure < Carrying Total minutes = (t1) + (t2) + (t3) +
capacity of hydraulic jack (t4) + (t5)
21215.46 kg < 50364 kg (OK) = 60 + 75 + 25 + 88.8 + 75
= 323.8 minutes
12
Total hours = 5.39 hours
Total days = 1 day

12
Total Time Duration = Pre Fabrication table 4.8 stages and calculation of work time
Time + Material Delivery + Erection Time + for delivery of conventional steel
TCC Hydrolic Jacking Up construction materials.
= 7 days + 5 h ari + 3 days + 1 day = 16 days
Table 4.8. Analysis of Delivery Time for
Conventional System Steel Construction Steel Construction Materials Conventional
Construction System
Time Analysis of the conventional system
steel construction construction time analysis
is divided into the following stages of work.
a) Fabrication Work
In this work, the main material for
conventional steel construction, which is
profile steel or WF steel, is carried out
directly in the field. Based on observations c) Erection Work
and field surveys. From the fabrication work Time analysis on erection work for
in the field, the time coefficient value of the conventional steel construction buildings is
fabrication work is obtained with the details carried out to determine the value of
of the workers as follows. productivity and duration of work. Similar to
Coefficient of work time = 33.4 kg/hour the erection work of steel construction
- 1 welder buildings with the pre-engineering building
- 1 blender system, the heavy equipment used is also 1
- 1 grinder unit of mobile crane of the Tadano brand
- 1 painter type GR-500XL with the same specifications
Total volume weight of conventional as the pre-engineering building system.
steel The following is the plan for the heaviest
= 17,928.23 kg. working time 8 hours/day. and tallest building materials to determine
Planned : the specifications of mobile mobile cranes in
Coefficient of work time = 187.4 kg/hr, erection work.
with Building data:
- 6 welders - Column height= 5.35 m
- 6 blenders - Rafter length = 8.6 m
- 6 grinders - Rafter weight (1frame) = 642.1
- 6 painters kg
Duration of work = 17.928.23 kg / 187.4 - Weight of 1 column = 767.2 kg
kg/hour Because column material is the heaviest
= 95.668 hours material item, namely with With a weight of
= 11 ,9 hr ≈ 12 hr 767.2 kg and an elevation of 5.35 m, it is
b) Material Delivery Work planned to position the mobile crane during
In the conventional system steel construction erection to optimize working time by
material delivery work, based on the results maximizing the capacity of the mobile crane,
of field surveys, the implementing contractor as well as lay out the mobility of the mobile
procures large volumes of profile steel crane for erection work.
material at steel manufacturers in Indonesia Planned :
such as PT. Krakatau Steel and PT. Mount - Length of boom = 25.8 m
Garuda. The location of the steel - Height of boom from floor = 16.7 m
manufacturer is in Cilegon Banten. Based on
the analysis of the implementation time of
material work in the field, the following
13
- Capacity of mobile crane = 3000 kg a) The working time of the pre-
(Table of mobile crane capacity) engineering building system obtained a total
- Radius of mobile crane = 22 m work time of 16 working days.
(Table of capacity of mobile crane) b) The work time of the conventional
Due to condition of implementation area and system is a total of 19 working days.
the area is relatively the same as the pre- From these results, the pre-engineering
engineering building system, it is assumed building construction method is more
that the placement of the mobile crane efficient in terms of time than conventional,
operation is in the same place. From the which is 3 days faster.
calculation of the erection work time, the 2. From the analysis of the calculation
total duration of erection work for of the cost of the steel construction
conventional steel TCC construction construction of the telescopic canopy
materials using a mobile crane in the lifting column system pre-engineering building
zone is as follows. with the conventional system, the following
Total duration of the zone = 1288.49 min results are obtained:
= 21.48 hours a) The total cost of the steel
After knowing the total duration of the construction work for the pre-engineering
erection cycle with mobile mobile cranes in building system is Rp. 526,428,123,-
the lifting zone, a recapitulation of the b) While the total cost of conventional
duration of effective use of mobile cranes steel construction works is Rp.
with mobile crane operating hours of 6 613,716.224,-
hours/day will be obtained. duration of use is So from these results, the cost of steel
as follows: construction for the pre-engineering building
Total minutes = 1288.49 min system is more efficient in terms of cost,
Total hours = 21.48 hours which is 14.2% cheaper or if it is translated
Total days = 3.58 days it is around Rp. 87,288,100,-
Rounding = 4 days 3. From the safety factor in the steel
The total duration of steel construction work construction work method, the pre-
in pre-engineering building systems is as engineering building method was chosen
follows. with several influencing factors as follows:
Total Duration of Time = a) implementation of the steel
Manufacturing Time + Material Delivery + construction pre-engineering building
Erection Time system was mostly carried out at a low
= 12 days + 3 days + 4 days = 19 days elevation of 2.6 m from the ground floor
b) Steel erection is carried out at an
5. CONCLUSION elevation of 2.6 m so as to reduce the risk of
work accidents
comparing c) There is no welding work in the
the cost and time of steel construction project area so as to reduce the risk of fire
buildings using pre-engineering building due to sparks in the welding process.
systems and conventional systems developed
analysis, the results of the cost and time Suggestion
approach are obtained as shown below. From the conclusion above, for steel
1. From the analysis of the calculation construction works, the pre-engineering
of the construction time of the steel building system is recommended to the
telescopic canopy column system pre- owner or investor and contractor as follows.
engineering building with the conventional
system, the following results were obtained:

14
1. Steel construction tcc pre- Tadano Product Catalog. 2015. Catalog of
engineering building systems have begun to mobile crane type GR-500XL
be widely developed by steel construction https://www.tadano.com/businesses/
manufacturers with pre-engineering building service/spec/index.html
systems in Indonesia. This can be a Zeng, Q., Li, Z., Wan, L., Ma, D., & Wang , J.
consideration to compare with importing (2022). Research on Dynamic Characteristics
steel construction materials with similar of Canopy and Column of Hydraulic Support
designs. under Impact Load.Energies,15(13), 4638.
2. The combination of hydraulic tcc Setiawan, A. (2008). Steel Structure Planning
system with pre-engineering building is an With LRF Method D.
innovation that seems quite new in steel Seo, J., Yoo, WS, Lee, UK, Kim, C., Kang, KI,
construction work in Indonesia. With this, it & Cho, H. (2010). Case study of a
synchronous hydraulic jack-up system for
makes business opportunities open for steel
constructing high-rise residential
applicators and contractors to innovate and buildings.Canadian Journal of Civil
increase competitiveness in the field of steel Engineering,37(6), 922-926.
construction in particular. Darmawan, MSD (2016). Mobile Crane
3. At the erection stage, experienced Productivity in High-rise Building
workers are needed in handling the erection Construction (Case Study of Parking Building
work of steel construction buildings with a "B" DPBCA Training Center & Hotel
pre-engineering building system. Development Project, Sentul City, Bogor
4. In the whole steel construction work Regency).Student Online Journal (JOM)
process, the combination of hydraulic tcc Civil Engineering,1(1).
with pre-engineering building systems has Aprilian, T. (2010). Labor productivity analysis
advantages in safety factors, especially on steel roof truss structure work (case study
construction workers, where the risk of work of dr. Moewardi hospital construction project,
accidents can be minimized because the Surakarta, Central Java).
majority of work areas are carried out at low
elevations of 2.5 m from the floor. basis, so
that it can be an important consideration for
owners who prioritize work safety to use the
design.

REFERENCES
Putra, RKE, Ekaputri, Y., & Nurcahyo, CB
(2015). Comparative Analysis of Cost and
Time of Steel Construction Buildings Using
Pre-Engineering Building Systems and
Conventional Systems at the Mojosari Fober
Cement Boards Plant Project.Journal of ITS
Engineering,4(1), D60-D64.
Buildings, PS (2011). Erection Manual Book and
Pre-Engineering Building System.
Saputra, R., Suraji, A., & Hakam, A. (2016).
CONSTRUCTION FAILURE ANALYSIS
FROM SOCIO–ENGINEERING SYSTEM
PERSPECTIVE.Journal of Civil Engineering
(JRS-Unand),12(1), 61-70.
Rostiyanti, SF (2002). Heavy equipment for
construction projects.

15

You might also like