Professional Documents
Culture Documents
DECEMBER 2022
Lead Agency:
City of West Hollywood
Planning and Development Services Department
8300 Santa Monica Boulevard
West Hollywood, California 90069
2
1. Project Description 7
1.1 Context 7
1.1.1 Lead Agency 7
1.1.2 City of West Hollywood 7
1.1.2.1 Existing Setting 7
1.1.3 Zoning 7
1.2 Project Purpose 8
1.3 Project Location 11
1.4 Construction 12
1.4.1 Length of Construction Time 12
1.4.2 Construction Employees 13
1.4.3 Construction Equipment 13
1.5 Operations 14
1.5.1 Average Daily Trips 15
2. Air Quality 18
2.1 Environmental Setting 18
2.1.1 Existing Air Quality Conditions 18
2.1.2 Existing Sensitive Receptors 18
2.2 Construction Impacts 19
2.2.1 Overall Construction 19
2.3 Operation Impacts 20
2.3.1 Overall Operations 20
2.4 Mitigation 21
2.4.1 Ozone Mitigation 21
2.4.2 Commute Trip Reduction 22
2.4.3 Carbon Sequestration 22
3. Noise 24
3.1 Environmental Setting 24
3.2 Construction Impacts 27
3.2.1 Summary of Results 28
3.3 Operation Impacts 32
3.4 Mitigation 34
4. Transportation 37
4.1 Environmental Setting and Existing Conditions 37
4.1.1 Existing Street System 37
4.1.2 Existing Transit Service 37
4.1.3 Potentially Significant Impact 37
4.2 Construction Impacts 42
3
4.3 Operation Impacts 43
4.5 Mitigation 46
4.5.1 Mitigation Measures 46
4.5.2 Significance after Mitigation 46
Appendix B - Noise 48
Appendix B-1: Noise data taken approximately 11:30 am at 11/12/2022 by Kishann Rai 48
Appendix B-2: Image from FHWA Roadway Construction Noise Model User’s Guide p.3 49
Appendix B-3 (Exposition Corridor Transit Neighborhood Plan Draft EIR - 4.9 Noise) 50
Appendix B-4: Zoning of area surrounding the project
(https://www.weho.org/home/showpublisheddocument/36958/636692560718630000) 51
Appendix B-5: Results from the RCMN model Demolition Phase 52
Appendix B-6: Results from the RCMN model Site Preparation 53
Appendix B-7: Results from the RCMN model Grading 54
Appendix B-8: Results from the RCMN model Building Construction 55
Appendix B-9: Results from the RCMN model Paving 56
Appendix B-10: Results from the RCMN model Architectural Coating 57
Appendix B-11: Calculating change in noise level due to traffic 58
References 59
4
List of Figures
Figure 1: Existing Zoning
Figure 2: Regional Location
Figure 3: Project Location
Figure 4: Surrounding Uses
Figure 5: Proposed Site Plan
Figure 6: CalEnviroScreen 4.0 Indicator Map (Left) and PM2.5 (Right)
Figure 7: Sensitive Receptors
Figure 8: Architectural Coating Mitigation Measures
Figure 9: Commute Trip Mitigation Measures
Figure 10: Sequestration
Figure 11: Exhibit 2-9, Landscape Plan Ground Level, Initial Study
Figure 12: Exhibit 2-10, 8th Floor Landscape Plan, Initial Study
Figure 13: Map of Receptors
Figure 14: The Den, to the left, next to the project site
Figure 15: Non-Transportation Source Noise Standards Effective Noise Sensitive Land Uses
Figure 16: Noise and Land Use Compatibility Matrix
Figure 17: Average Daily Traffic Around the Site
Figure 18: Number of Vehicles vs. Time on Sunset Blvd
Figure 19: Level of Service Definitions
5
List of Tables
Table 1: Zoning
Table 2: Proposed Development Summary
Table 3: Construction Phase and Timeline
Table 4: Number of Trips per Day during Construction
Table 5: Proposed Parking Summary
Table 6: Mode Split - Commute to Work
Table 7: Trip Summary Information - Hotel
Table 8: Trip Summary Information - Other Commercial
Table 9: Trip Summary Information - Residential
Table 10: Number of Visitors to the Project by Mode and Day
Table 11: Construction Impacts on Air Quality
Table 12: Operation Impacts on Air Quality
Table 13: West Hollywood’s daytime and nighttime hours
Table 14: West Hollywood’s Noise Levels
Table 15: West Hollywood Construction Hours
Table 16: Project Receptors
Table 17: Construction Impacts from OffRoad Equipment
Table 18: Overview of L10s by Construction Phase
Table 19: L10s during Demolition by Receptor
Table 20: L10s during Site Preparation by Receptor
Table 21: L10s during Grading by Receptor
Table 22: L10s during Building Construction by Receptor
Table 23: L10s during Paving by Receptor
Table 24: L10s during Architectural Coating by Receptor
Table 25: New CNEL With Construction Impacts
Table 26: Daily Vehicular Volume
Table 27: New Vehicular Volumes With Construction
Table 28: Noise Level Increase with Increased Traffic Volume
Table 29: Mitigation measures For Equipment
Table 30: Capacity of Roadway Systems
Table 31: Road Access Points to the Harper Project Site and Roadway Capacity
Table 32: Average Traffic Counts on a Wednesday on Sunset Blvd
Table 33: Smart Growth Model Outputs
6
1. Project Description
1.1 Context
1.1.3 Zoning
The site’s existing general plan land use and zoning is as follows:
Table 1: Zoning (City of West Hollywood, & De Novo Planning Group, 2022)
5554-018-023 Sunset Specific Plan and SSP Sunset Specific Plan and
Residential Multi-Family R4B-PK Residential, MultiFamily High-Density/
High Density (R4B) Parking Overlay District
7
Figure 1: Existing Zoning (City of West Hollywood, & De Novo Planning Group, 2022)
The initial study, prepared by the City of West Hollywood with the help from De Novo Planning
Group, outlines project details, which informs the narrative and analysis completed in this report.
The newly-proposed Harper Project proposes to replace the existing land uses on the project
site, developing a mixed-use development. The Harper Project will include a hotel, restaurants,
retail, and residential uses as well as a wrap-around digital billboard display on the corner of
Sunset Boulevard and North Harper Avenue (City of West Hollywood, & De Novo Planning Group,
2022). As seen in Figure 1 of this report, the Project will be split by residential uses and
commercial uses. The residential uses include 45 apartments, totalling 66,307 square feet, and
7,400 square feet of residential open space. The Project includes 9 low-income units and 36 units
at market-rate. The commercial uses include a 167-room hotel, a hotel spa and gym, a pool deck,
8
restaurants, a bakery, outside seating on the 8th floor, and a meeting area on the 9th floor. There
will also be two levels of subterranean parking, providing 172 total spaces (City of West
Hollywood, & De Novo Planning Group, 2022).
Table 2: Proposed Development Summary (City of West Hollywood, & De Novo Planning Group, 2022)
The main goal of this project is to complement the existing uses along the Sunset Strip, providing
pedestrian-oriented, walkable spaces within the Sunset community. According to their website,
“The Harper on Sunset is testimony to the strength and vitality of West Hollywood. A pedestrian
oriented project, it will provide the community with a place to walk, eat, and relax on the world
famous Sunset Strip” (The Harper on Sunset). The Project will also increase the economic
conditions in the area, creating employment opportunities and increasing foot traffic to local
businesses in the surrounding areas. For example, the developers estimate that the Harper
Project will generate approximately “150 full-time jobs over the next 50 years” (The Harper on
Sunset). The restaurants and bakery, which are along the Sunset Boulevard frontage, give the
building a “strong connection between the project and the street” (The Harper on Sunset).
The Project also includes an extensive landscaping plan, making outdoor gathering pleasurable
to residents of the Project and visitors to the area, as seen in Figure 3. Harper on Sunset
describes the Project’s priority as incorporating “an abundant use of greenery, to create an
organic appearance that is visually appealing to the public” (The Harper on Sunset).
The Harper Project is also unique because it proposes the development of the first hotel on the
eastern section of Sunset Boulevard, which will increase visitors to the area and, subsequently,
economic vitality of local businesses that surround the Project.
9
Figure 2: Regional Location (Source: City of West Hollywood, & De Novo Planning Group, 2022)
10
1.3 Project Location
The Harper Project is designated Sunset Specific Plan, with a portion of the land also designated
R4B-PK, or Residential Multi-Family High Density with a Parking Overlay District. There are various
surrounding uses to this project, as explained in Figure 4, sourced from the Initial Study for this
Project:
Figure 4: Surrounding Uses (City of West Hollywood, & De Novo Planning Group, 2022).
Appendix A items A-1 show the project site within a local context, respectively. The Project is
located along the Sunset Strip, a heavily visited, well-known commercial area. The strip includes a
mix of building typologies, ranging from high- to low-rise structures, and has a lot of pedestrian
activity. It contains a mix of low- and high-rise buildings, most of which directly front onto Sunset
Boulevard (City of West Hollywood, & De Novo Planning Group, 2022).
Figure 5 shows a detailed ground-floor site plan of the Harper Project in a neighborhood, local
context, including the surrounding structures in the background. Many of the commercial uses,
such as the restaurants, bars, outdoor patios, and hotel amenities are located on the first-floor of
the project.
11
Figure 5: Proposed Site Plan (City of West Hollywood, & De Novo Planning Group, 2022)
1.4 Construction
Table 3: Construction Phase and Timeline (California emissions estimator model ® soft release)
Construction Phase
Phase Name Phase Type Start Date End Date Days/Week Total Days
Demolition Demolition 1/1/2023 1/13/2023 5 Days/Week 10
Site Preparation Site Preparation 1/14/2023 1/16/2023 5 Days/Week 1
12
Grading Grading 1/17/2023 1/18/2023 5 Days/Week 2
Building Building
Construction Construction 1/19/2023 6/7/2023 5 Days/Week 100
Paving Paving 6/8/2023 6/14/2023 5 Days/Week 5
Architectural Architectural
Coating Coating 6/15/2023 6/21/2023 5 Days/Week 5
Table 4: Number of Trips per Day during Construction (California emissions estimator model ® soft
release)
Phase Name # Trips Worker (/day) # Trips Vendor (/day) Total # Trips Hauling
Demolition 10 0 118
Site Preparation 5 0 0
Grading 8 0 0
Building Construction 95 29 0
Paving 18 0 0
Architectural Coating 19 0 0
We are acting on the assumption that each number of trips per worker is one way. Thus, we
estimate that demolition requires 10 workers per day and approximately 20 people hauling per
day over the 10 day demolition period. During site preparation, 5 construction workers per day
will be required, and during the grading process, there will be 8 necessary workers per day.
Building construction requires the largest amount of construction workers and is the only
construction phase requiring vendors. 78 construction workers and 22 vendor workers per day
are required during the building construction phase. Paving requires 18 workers per day, and
architectural coating requires 16 workers per day (California emissions estimator model ® soft
release).
13
2. The second phase, site preparation, requires
a. 1 grader
b. 1 tractor/loader/backhoe
3. The third phase, grading, requires
a. 1 grader
b. 1 rubber tired dozer
c. 1 tractor/loader/backhoe
4. Building construction, the fourth and longest construction phase, requires
a. 1 crane
b. 2 forklifts
c. 2 tractors/loaders/backhoes
5. The fifth phase, paving, requires
a. 4 cement and mortar mixers
b. 1 paver
c. 1 roller
d. 1 tractor/loader/backhoe
6. Finally, the last phase, architectural coating, requires
a. 1 air compressor
1.5 Operations
The Harper Project is a mixed-use development including residential and commercial uses. As
can be seen in Figure 1, the Proposed Development Summary, the residential uses include one-
and two-bedroom apartment units as well as open space split between common open space and
private open space. The commercial units include 167 rooms in a hotel, a hotel spa and gym, a
pool deck, restaurants, a bakery, outdoor seating and a meeting area. There are 45 total
apartment units with 33 one-bedroom units and 12 two-bedroom units. Assuming a maximum
occupancy of 2 people per one-bedroom unit and 4 people per two-bedroom unit, there would
be a maximum occupancy of 114 individuals residing in the apartment complex. In addition, the
hotel will have 167 rooms, and assuming a maximum occupancy per room of 4 people, a total
maximum occupancy of 668 hotel guests. However, we will assume a reasonable worst case
scenario of 80% occupancy in the hotel, or 535 guests. Once completed, the Harper Project will
be comprised of 12 levels reaching approximately 111 feet and eight inches in total height:
● Two floors of subterranean parking (Basement 1 and Basement 2)
● Lower ground level for vehicular circulation
● Ground level with commercial uses and restaurants
● Eight residential floors for apartment and hotel uses
(City of West Hollywood, & De Novo Planning Group, 2022)
According to the initial study, the Harper Project will ‘generate additional average daily trips
(ADT)’ compared to the existing uses. Some of these additional ADT will likely be due to the
approximately “150 full-time jobs over the next 50 years” that the Harper Project will result in (The
14
Harper on Sunset). The project also adds various commercial uses that attract pedestrians and
visitors. Whereas the prior land uses only included office spaces, the Harper Project includes a
variety of land uses, as shown in Table 2. These uses, as well as the residential and hotel units, are trip
generators that will attract additional people and, thus, additional VMT.
In addition, the Harper Project offers 172 parking spaces, as seen in Table 5. It is likely that, due
to parking demand in West Hollywood and particularly along the Sunset Strip, the commercial
parking reasonable worst case scenario is 100% occupancy. The parking along Sunset Boulevard
is limited to 2 hours in many places and completely restricted in others, leaving few on street
parking options.
Table 5: Proposed Parking Summary (City of West Hollywood, & De Novo Planning Group, 2022)
15
Walked 2.2%
Although these numbers refer to commuting to and from work, they will be applied to general
mode split patterns for our purposes as well. Average daily trips are defined as round-trip trips by
motor vehicles over a 24 hour period.
Table 7: Trip Summary Information - Hotel (California emissions estimator model ® soft release)
Table 8: Trip Summary Information - Other Commercial (California emissions estimator model ® soft
release)
Table 9: Trip Summary Information - Residential (California emissions estimator model ® soft release)
The number of average daily trips can be found in Table 7, Table 8, and Table 9. Applying the
mode split principles listed in Table 6, the number of individuals expected to go to the Project are
calculated in Table 10.
16
Table 10: Number of Visitors to the Project by Mode and Day (California emissions estimator model ® soft
release)
Hotel Other Commercial Residential
Overall, it is estimated that the total people to go to the project, between commercial and
residential uses, on an average weekday are approximately 2,264 across various modes, with
1,867 individuals driving alone and 215 carpooling. It can be assumed, then, that there will be
approximately 2,000 vehicles over a 24-hour weekday period. On an average Saturday, the total
number of people going to the project is approximately 2,156 across modes, with 1,778 individuals
driving alone and 205 carpooling, leading to approximately 2,000 cars. Last, on Sunday, it is
estimated that there would be an average of 1,955 visitors to the project, with 1,613 driving alone
and 186 carpooling, totalling approximately 1,800 vehicles.
17
2. Air Quality
This section examines the degree to which the proposed project's short-term construction and
ongoing operations may result in significant environmental impacts regarding air quality. As used
in this study, “emissions” refers to the quantity of pollutants measured in pounds per day (ppd).
Figure 6: CalEnviroScreen 4.0 Indicator Map (Left) and PM2.5 (Right) (California Office of Environmental
Health and Hazard Assessment)
18
Figure 7: Sensitive Receptors (ArcGIS Pro)
We address short-term construction emissions from demolition, site grading, and haul truck trips.
Our findings show there to be a high concentration of ROG/VOC emissions also referred to as
Ozone. We identified the source to be the paint, also classified as architectural coating, used for
the exterior, interior, and parking.
19
Table 11: Construction Impacts on Air Quality (California emissions estimator model ® soft release)
ROG/VOC2 NOX CO SO2 PM10 Total PM2.5 Total
Measurement lbs/day
2023 675.67 10.19 10.96 2.62 5.8 2.97
Threshold1 75 100 550 150 150 55
Max 675.63 10.19 10.96 2.62 5.8 2.97
1
Threshold is based on the South Coast AQMD Air Quality Significance Thresholds used to assist the CEQA practitioner in
conducting an air quality analysis.
2
ROG and VOC are both precursors to ozone and are summed in the CalEEMod report under the header ROG. For the purposes of
comparing the ROG value to a VOC significance threshold, the terms can be used interchangeably.
3
Red text indicates that this emission type has exceeded the AQMD threshold for pounds per day (ppd).
From our assessment, mobile sources exceed SCAQMD thresholds. The high concentration of
mobile emissions were specifically a result of daily commute trips. The breakdown of commute
trips and mode split for project operations can be found under section 1.5.1 Average Daily Trips in
tables 6 - 9.
Table 12: Operation Impacts on Air Quality (California emissions estimator model ® soft release)
ROG/VOC NOX CO SO2 PM10 Total PM2.5 Total
Measurement lbs/day
Area 16.09 0.97 26.63 0.05 3.45 3.45
Energy 0.14 1.3 1.03 7.86 0.09 0.09
Mobile 412.13 373.58 3717.57 7.98 860.39 233.01
Water 0 0 0 0 0 0
Solid Waste 0 0 0 0 0 0
Threshold 75 100 550 150 150 55
Total 428.37 375.85 3745.23 8.04 863.95 236.57
20
2.4 Mitigation
Figure 8: Architectural Coating Mitigation Measures (California emissions estimator model ® soft release)
21
2.4.2 Commute Trip Reduction
The mobile operations of the project have shown to have a high concentration of emissions.
Fortunately, there are commute trip reduction programs that encourage workers to take
alternative modes such as transit, vanpool, carpool, biking, walking and even telecommuting.
One of the most effective ways to change commuter behavior is through transportation subsidies
and incentives provided by employers. Studies have also shown “Employee commute behavior is
most easily influenced at the start of a new job and/or work site relocation (City of Seattle).”
Implementing a commute trip reduction program at the beginning of operations will provide a
successful reduction in drive-alone trips to the project site. The program will be offered to all
full-time employees working at the hotel, restaurants, and apartments. Benefits include a $1.49
daily transit subsidy, parking cash-out for those who chose not to use their space, vanpool
services, and telecommuting for non customer-facing and staff management employees (i.e.
accounting).
Figure 9: Commute Trip Mitigation Measures (California emissions estimator model ® soft release)
22
Figure 11: Exhibit 2-9, Landscape Plan Ground Level, Initial Study (City of West Hollywood, & De Novo
Planning Group)
Figure 12: Exhibit 2-10, 8th Floor Landscape Plan, Initial Study (City of West Hollywood, & De Novo Planning
Group)
23
3. Noise
Table 13: West Hollywood’s daytime and nighttime hours (City of West Hollywood, 2011)
Table 14: West Hollywood’s Noise Levels (City of Los Angeles Department of City Planning, 2017; Kishann
Rai, 2022)
Nighttime 40 dBA
The City of West Hollywood did not have the ambient noise level data for the day or night, so
LAMC data was used as a substitute for the night and was obtained from a previous EIR, see City
of West Hollywood, 2018 in the references for the full document. The noise levels were deemed
appropriate to use due to the city’s close proximity to LA. The site itself is zoned as SSP and
residential as are surrounding areas (City of West Hollywood, 2018). Therefore, the project would
have an ambient noise level 40 dBA at nighttime (City of Los Angeles Department of City
Planning, 2017). The daytime ambient noise was measured to be 57.4 dBA on 11/12/2022 at 11:30
am. Note that this measurement did not span a whole hour and was extrapolated, see Appendix
B-1 for data.
24
Figure 13: Map of Receptors (made with Google’s My Maps)
Figure 14: The Den, to the left, next to the project site (Google Earth)
West Hollywood did not provide criteria as to how to classify a receptor when analyzing noise
impacts. CalTrans recommends analyzing receptors within 500 ft of a project so major
businesses and residences within a .1 mile radius of the project were chosen (Caltrans, 2020).
The distance of the receptors was measured with the measure tool on Google Maps from the
closest point on the receptor to the middle of the site (see Table 16).
25
3. The Pink Taco
4. Andalusia Apartments
5. The Body Shop.
The Andalusia apartments were especially important as they were noted to be a Los Angeles
Historic-Cultural Monument in the initial study. The Andalusia and Harper House are both
residential areas making them receptors of interest.The Body Shop has been used in various
music videos and has hosted some celebrities according to its website. Ambience is a large part
of The Body Shop’s business, and construction noise may affect said ambience making the club a
sensitive receptor. However, the Body Shop will not be affected during some of its hours as the
shop is open from noon to 12 am which is partially outside of construction hours, see the table
below (The Body Shop, n.d.). The Den was also of particular concern due to its close proximity to
the construction site however, its hours are 5 p.m. - 2 a.m. and 5 p.m. - 3 a.m. on Saturday so
construction will not be present for the whole business day (The Den on Sunset, n.d.). The Pink
Taco, a restaurant, was also deemed a sensitive receptor as patrons may be disturbed by the
noise.
Table 15: West Hollywood Construction Hours (City of West Hollywood, n.d.a)
Mon-Fri 8am-7pm
Sunday No construction
Andalusia 69 ft Residential
Apartments
26
3.2 Construction Impacts
Table 17: Construction Impacts from OffRoad Equipment (California emissions estimator model ® soft
release)
CalEEMod was used to estimate the noise impacts of off road vehicles, and construction phases
were broken into 6 phases. It was determined that the longest phase would be “Building
Construction” at 100 days; the shortest phase is Site Preparation at one day.
To determine the construction impacts that the Harper Project will have on the environment and
surrounding community the RCNM model was used. The RCNM model is limited as only a total of
20 machines can be entered into the model. Hence, construction impacts were broken up by its
phases: demolition, site preparation, grading, building construction, paving, and architectural
coating. This also allowed for a more in depth analysis of each phase. The RCNM standards for
each piece of equipment’s dBA were kept. The RCNM model did not have the noise levels for
forklifts, so in Building Construction “All other equipment” was used as a substitute. See
Appendix B-2 for the RCNM model’s set measurements for construction equipment as stated in
the FHWA User Hand Book.
The RCNM model did not allow for different pieces of equipment to be used for various amounts
of time. Yet, this was not an issue as in a worst case scenario, all pieces of equipment are being
used simultaneously. Moreover, a worse case scenario assumes all pieces of equipment are
being used for 8 hours a day, beyond what CalEEMod stated, for the full workday. Equipment is
27
likely to be used for 8 hours if 1) a mistake was made and needs to be redone or 2) work was
damaged and needs to be redone.
Note West Hollywood’s construction hours are 8am-7pm (City of West Hollywood, n.d.a). Sundays
no construction is permitted along with holidays and on Saturdays interior construction can take
place. However, an extended hours construction may be applied to (City of West Hollywood,
n.d.a). However, for a reasonable worst case scenario such a permit is not likely as the city only
has six active extended noise permits as of 11/30/2022 evincing their rarity (note not all 6 permits
are for 6 separate projects) (City of West Hollywood, n.d.b).
Any construction that exceeds 55 dBA during the night or 50 dBA must be considered for
mitigation according to Figure 15 below, as these are the city’s noise thresholds for construction
(City of West Hollywood. 2011). Note that the ambient environment already exceeds the noise
threshold of 55 dBA at 57.4 dBA.
Figure 15: Non-Transportation Source Noise Standards Effective Noise Sensitive Land Uses (City
of West Hollywood, The City of West Hollywood 2035 General Plan, 2011).
The charts below affirm that the daytime noise thresholds of 55 dBA, during which construction
would take place, is exceeded in every phase of construction for all receptors. The L10 was used
in the RCNM model to determine a reasonable worst case scenario since the L10 is the noise
level that is exceeded 10% of the time.
28
*all L10s measured in dBA
Table 18: Overview of L10s by Construction Phase
Receptor L10
Receptor L10
Receptor L10
29
The Den 91.6
Receptor L10
Receptor L10
Receptor L10
30
Figure 16: Noise and Land Use Compatibility Matrix (City of West Hollywood, The City of West
Hollywood 2035 General Plan, 2011).
31
Table 25: New CNEL With Construction Impacts
Figure 16 confirms that any West Hollywood
project within a residential area, which all
receptors and the project are, will need mitigation
if the CNEL is above 60. The new CNEL to
represent the impacts of construction was
calculated to be 67.78. Hourly data could not be
found for the city of West Hollywood so
substitutions had to be made when calculating
the new CNEL. The measured daytime ambient
noise was used for some daytime hours. Note,
that the daytime ambient noise calculation was
extrapled and the original measurement did not
span a whole hour. To replicate a worse case
scenario, the highest L10 during the construction
phase was used for the span of 8 daytime hours.
8 hours is the workday length CalEEMod
predicted and is considered a typical workday. 40
dBA for nighttime hours was used because hourly
nighttime data could not be found (City of Los
Angeles Department of City Planning, 2017).
Hence, the L10 was deemed more appropriate to
use in this case for the construction and daytime
hours as the nighttime hours are an
underestimate and the L10 would help
compensate for this.
The new CNEL of 67.78 would categorize the noise level as “ZONE B-Conditionally Acceptable”
according to Figure 16. Such a noise level requires mitigation to be undertaken if construction is
to proceed. Mitigation measures are detailed in the mitigation section of the report.
32
Table 26: Daily Vehicular Volume (West Hollywood Mobility Plan 2035, see Figure 16)
There will be 2,000 vehicles over a 24-hour weekday period after the completion of the project
as the project description stated. On Saturday, approximately 2,000 cars and on Sunday it is
estimated that there would be approximately 1,800 vehicles. To see the full calculations, please
refer to the project description.
A worst case scenario assumes that the number of vehicles coming to visit the project will all
travel along these new roads. Such a scenario is likely if one or more of the roads is closed for
repairs. The new numbers would be the following:
Street Name New Daily Vehicular Volume New Daily Vehicular Volume
Weekday and Saturday Sunday
Using the formula 10 log V2 - 10 log V1 the change in noise level due to the change in the
increased traffic volume was calculated, see appendix for more detailed calculations:
Street Name Noise Level Increase From Noise Level Increase From
Traffic on Saturday (dB) Traffic on Saturday (dB)
The project will not have a significant impact when it comes to operational noise as the increase
in traffic related noise increases by 5dB a day. The city did not have a threshold related to traffic
related noise generated by a project. No mitigation is needed for operational noise as the
impacts were not significant.
33
3.4 Mitigation
While operational noise does not need mitigation, construction noise does. CalEEMod could not
be run for noise mitigations, as calculating how mitigation measures would affect noise is beyond
the model’s capacity. In order to reduce noise pollution resulting from construction, the following
will be done:
1. Implementing noise barriers around the construction site (Echo Barrier, 2020)
2. Using mufflers on equipment as applicable (Nelson Global Products Aftermarket, n.d.)
3. Machinery is up to date and well cared for- being oiled or wet as necessary (Pav, 2019)
4. Using customized mitigation measures for each piece of equipment (see chart below)
5. Extending the “Building Construction” so the same amount of hours are worked in double
the time to reduce daily noise
Sound barriers around the construction site can help reduce noise significantly. Sound barriers
can be made with barriers themselves or by draping sound blankets around fencing. Depending
on the brand of the sound blanket, anywhere from 10 dB to a 30 dB decrease in noise can be
achieved (Echo Barrier, 2020). With the new CNEL being approximately 67.78, the minimum of a
10 dB decrease with a sound barrier would make the new CNEL 52.78 which brings noise to
“Zone A- Normally Acceptable.”
The second mitigation measure, “using mufflers,” would help to silence noise coming from the
engine. However, depending on the equipment’s brand and age, this may not be an option for all
pieces of construction equipment. According to the company Nelson Global Products
Aftermarket, their mufflers can reduce sound from 18 dB to 35 dB depending upon the muffler
type.
In addition to using mufflers and sound barriers, simply making sure all equipment is updated,
well oiled/wet as necessary can reduce the likelihood of unnecessary noise as the machines run
smoothly.
Table 29 below offers some mitigation measures for each piece of equipment being used to
construct The Harper Project. Note, that in addition to the sound barrier surrounding the
construction site, additional sound barriers can be set up within the site itself when work is
isolated in one part of the site or the machine being used is mostly stationary.
Finally, It is also recommended that the longest and loudest phase of construction, “Building
Construction,” is made longer so fewer pieces of equipment are used to decrease the amount of
noise output each day. Workers should work 4 hours a day for 200 days instead of 8 hours a day
for 100 days. Extending the construction may be more costly and it may be harder to find workers
to fill these hours. However, this mitigation is needed to reduce the CNEL during this construction
phase; which again is the loudest with its highest L10 being 95.3 dBA.
34
The phase is currently 100 days with 8 hour days:
Total hours for Building Construction Phase = 100 days* 8 hours/1 day = 800 hours
X= 200 days
Table 29: Mitigation measures For Equipment
35
2020)
* Sources used to compile the chart: Dongqi Group (n.d); Pav, N (2019); Echo Barrier (2020);
Nelson Global Products Aftermarket (n.d.); Construction Solutions (n.d.); Baart Industrial Group.
(n.d.).
36
4. Transportation
The following is a brief description of the streets that serve the site:
Sunset Boulevard – Sunset Boulevard is an east-west arterial that provides four travel
lanes during the peak periods, with two lanes in each direction. It is situated to the north
of the project site. Parking is prohibited during the AM and PM peak periods and limited
between the peak periods. The posted speed limit is 35 mph.
N Harper Avenue – N Harper Avenue is a north-south residential street that provides two
travel lanes during the peak periods, with one in each direction. It is situated to the west
of the project site. No parking from on Thursday from 9 AM to 11 AM and daily from 7PM -
7AM without a special permit. The posted speed limit is 25 mph.
37
Figure 17 shows the Project site (colored in yellow) in relation to the two streets that provide
access to the site, N Harper Avenue and Sunset Boulevard. These two streets were chosen,
since we assumed this is where most people would be causing traffic by entering and exiting
through the site. The daily traffic counts were taken from West Hollywood’s 2035 Mobility Plan
that provides guidance for the upcoming years regarding long-term strategies that addresses the
unique characteristics of West Hollywood’s transportation needs. Sunset Boulevard has a daily
traffic count of 52,231 vehicles while N Harper Avenue has a daily traffic count of 1,632 vehicles.
Figure 17: Average Daily Traffic Around the Site (West Hollywood Mobility Plan 2035)
For the traffic analysis, we looked at the impact the traffic flow will have on the level of service on
the selected streets of N Harper Avenue. From Table 30, we break down roadway capacity based
on the type of streets. In Table 31, we classified N Harper Avenue as a residential street with two
traffic lanes with a capacity of 600 vehicles/lane/hr. We chose to go with the lower part of the
range, since we wanted to assume a reasonable worst case scenario where the street would only
be able to handle a smaller amount of traffic, leading to a total roadway capacity of 1200
vehicles/hr. Sunset Boulevard was classified as an arterial street with four traffic lanes with a
capacity of 1600 vehicles/lane/hr, leading to a total roadway capacity of 6400 vehicles/hr.
38
Table 30: Capacity of Roadway Systems (Geraldine Knatz’s Traffic Lecture on 9/29/2022)
Residential 600-800
Arterial 1600
Freeway 2000
Table 31: Road Access Points to the Harper Project Site and Roadway Capacity
The data from Sunset Boulevard was collected from LA’s GeoHub Site which provided hourly
traffic rates from the arterial street that goes by the project site. The data was exported from the
site and can be found in Table 32. From Table 32, we can see that the Peak Hour Volume
occurred around 5 PM with 3254 vehicles. The overall average daily traffic on Sunset Boulevard
was found by summing every hour’s number of vehicles, resulting in a total of 52,231
vehicles/day. The average daily traffic on N Harper Avenue was taken from Figure 17 regarding
Average Daily Traffic Around the Site, which was 1632 vehicles/day.
There was no hourly traffic data found regarding N Harper Avenue. However, according to
Precision Traffic & Safety Systems, the peak hour volume (highest hour) is generally between 6
percent and 10 percent of the ADT. The lower part of the range is generally found on lower
volume roadways. The average value is approximately 8.4 percent of the ADT. Since we are
assuming a worst case scenario, we will go with the upper bound of 10 percent. This 10 percent
will be considered the PHV percentage. By applying this 10 percent rule to N Harper Avenue, we
found that the PHV is 163 vehicles.
39
Table 32: Average Traffic Counts on a Wednesday on Sunset Blvd (Geohub for LA County)
40
Figure 18: Number of Vehicles vs. Time on Sunset Blvd
Time: 5:00 PM
Number: 3254 vehicles
𝑃𝐻𝑉 𝑁𝑢𝑚𝑏𝑒𝑟 3254
PHV Percentage = 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐷𝑎𝑖𝑙𝑦 𝑇𝑟𝑎𝑓𝑓𝑖𝑐
= 52231
= 0. 0623 = 6. 23%
1632 vehicles/day
41
4.2 Construction Impacts
In terms of construction impacts, we used the assumptions outlined at the beginning of the
presentation to get the building construction outputs from CalEEMod. There were multiple
phases considered. However, the building construction phase had the most trips for the building.
In terms of the worst case scenario, we assumed that all of the workers/ vendors will be going
home during the peak hour at 5 PM, resulting in 124 additional vehicles on the road.
Since the building construction phase is the longest and has the most workers commuting to and
from the site, we assumed this would be the worst case scenario during the construction phase
as this is when the most people are filtering in and out of the project. Also, we assumed that
everyone would be going back home around the same time at 5 PM, which is considered the end
of the work day. We also assumed that the same amount of vehicles would be added to each
road, N Harper Avenue and Sunset Boulevard, surrounding the site. The total amount of
additional trips was added to the peak hour volume for N Harper Avenue. The new PHV for N
Harper Avenue is 287 vehicles while Sunset Boulevard’s PHV is now 3378 vehicles.
N Harper Avenue
New Traffic Volume = 163 Vehicles+124 Vehicles = 287 vehicles
Sunset Boulevard
New Traffic Volume = 3254 Vehicles + 124 Vehicles = 3378 vehicles
After finding the new PHV during construction, we used the new PHV numbers and the capacity
of each roadway to determine the level of service. The level of service definitions can be found in
Figure 19. After performing the analysis, we found that for Sunset Boulevard and N Harper
Avenue that there would be no significant impact as the level of service remained both in range
of excellent level of service during the construction phase.
42
Figure 19: Level of Service Definitions (Highway Capacity Manual)
N Harper Avenue
The volume to capacity ratio is within range of the excellent level of service
meaning there is no significant impact for traffic on this road.
Sunset Boulevard
The volume to capacity ratio is within range of the excellent level of service
meaning there is no significant impact for traffic on this road.
43
was taken from the PHV percentage used for N Harper Avenue. We take the larger number to
ensure we are emulating a worst case scenario condition during peak hours.
Information from Table 10: Number of Visitors to the Project by Mode and Day
Other
Hotel Commercial Residential
Total Amount of Vehicles Combined from Every Use (Except Residential): 2063 vehicles
To determine the PHV from added vehicles due to the residential component of the project, it
was assumed that around one-fifth of people will be commuting to and from the project site at 5
PM. The PHV for PM Peak Hour Vehicles inputted into the smart growth model was 40 vehicles.
However, after inputting this into the smart growth model. The number of added vehicles to traffic
was decreased to 18 vehicles. To get the additional vehicle trips from the hotel and other
commercial uses of the project site, the total number of vehicles combined from every use
(except residential): was 2063 vehicles. After applying the 10% PHV percentage, the number of
added vehicles from the other uses was found to be around 207 vehicles after rounding up to the
nearest whole number. 207 and 18 were added together to get the total of 225 additional
vehicles at peak hour from the use of the CalEEMod and the Smart Growth Models. This number
was then added to the original PHV to determine the new volume during the operational phase
of the project.
44
Table 33: Smart Growth Model Outputs (Smart Growth Model)
Model Outputs10
Smart Growth Factor -0.01
Actual/ITE-Estimated AM Peak Hour Vehicle Trips 0.27
Actual/ITE-Estimated PM Peak Hour Vehicle Trips 0.45
Estimated AM Peak Hour Vehicle Trips 9
Estimated PM Peak Hour Vehicle Trips 18
N Harper Avenue
New Traffic Volume = 163 Vehicles+225 Vehicles = 388 vehicles/hr
Sunset Boulevard
New Traffic Volume = 3254 Vehicles + 225 Vehicles = 3479 vehicles/hr
After finding the new PHV during the operational phase, we used the new PHV numbers and the
capacity of each roadway to determine the level of service. The level of service definitions can be
found in Figure 19. After performing the analysis, we found that for Sunset Boulevard and N
Harper Avenue that there would be no significant impact as the level of service remained both in
range of excellent level of service during the operational phase.
N Harper Avenue
The volume to capacity ratio is within range of the excellent level of service
meaning there is no significant impact for traffic on this road.
45
Sunset Boulevard
The volume to capacity ratio is within range of the excellent level of service
meaning there is no significant impact for traffic on this road.
4.5 Mitigation
46
Appendix A - Additional Project Maps
Appendix A-1: Project Location (City of West Hollywood, & De Novo Planning Group, 2022)
47
Appendix B - Noise
Appendix B-1: Noise data taken approximately 11:30 am at 11/12/2022 by Kishann Rai
48
Appendix B-2: Image from FHWA Roadway Construction Noise Model User’s Guide p.3
49
Appendix B-3 (Exposition Corridor Transit Neighborhood Plan Draft EIR - 4.9 Noise)
50
Appendix B-4: Zoning of area surrounding the project
(https://www.weho.org/home/showpublisheddocument/36958/636692560718630000)
51
Results from the RCMN model
Demolition Phase
52
Site Preparation Phase
53
Grading
54
Building Construction Phase
55
Paving
Andalusia
56
Architectural Coating
57
*Equation in excel: =(10*LOG(V2))-(10*LOG(V1))
58
References
Baart Industrial Group. (n.d.). Excessive roller chain noise: Sources and solutions . Baart Industrial
Group. Retrieved from https://baartgroup.com/excessive-roller-chain-noise/
CAPCAO. (2021). California Emissions Estimator Model User’s Guide. Retrieved from
http://www.aqmd.gov/docs/default-source/caleemod/user-guide-2021/01_user-39-s-guide
2020-4-0.pdf
City of West Hollywood, & De Novo Planning Group. (2022). (rep.). 8228-8240, The Harper
Project Initial Study. West Hollywood, CA: De Novo Planning Group. Retrieved October 17,
2022, from https://ceqanet.opr.ca.gov/2022090073
California Office of Environmental Health and Hazard Assessment (n.d.). CalEnviroScreen 4.0.
Retrieved from https://oehha.ca.gov/calenviroscreen
City of Los Angeles Department of City Planning. (2017, April). Exposition Corridor Transit
Neighborhood Plan Draft EIR: 4.9 Noise. Retrieved from
https://planning.lacity.org/eir/ExpositionCorridor/Deir/ECTNP%20Index.html
City of Seattle. (2019). Commute Trip Reduction Strategic Plan 2019-2023. Retrieved from
https://www.seattle.gov/Documents/Departments/SDOT/TransportationOptionsProgram/C
TR_Final_Plan_20190822.pdf
City of West Hollywood. (2018, August). City of West Hollywood Zoning Map.
https://www.weho.org/home/showpublisheddocument/36958/636692560718630000
City of West Hollywood. (2011, September 19). City of West Hollywood Ch.10 Safety and Noise.
Retrieved from
https://www.weho.org/home/showpublisheddocument/7918/635229037960770000
59
City of West Hollywood Open Data. (n.d.). Citywide Traffic Volumes Map. Retrieved from
https://data.weho.org/Traffic/Citywide-Traffic-Volumes-Map/rnip-gr5e
Construction Solutions. (n.d.). Solution summary: Quieter motor graders. Retrieved from
https://www.cpwrconstructionsolutions.org/heavy_equipment/solution/832/quieter-motor-
graders.html
Echo Barrier. (2020, April 19). Reducing Heavy Machinery Noise. Retrieved from
https://blog.echobarrier.com/blog/reducing-heavy-machinery-noise
The Harper on Sunset. The Harper. (n.d.). Retrieved October 29, 2022, from
https://theharperonsunset.com/
Nelson Global Products Aftermarket. (n.d.). Small Engine Exhaust Solutions. Retrieved from
https://www.nelson-aftermarket.com/small-engine-exhaust-solutions/
Pav, N. (2019, June 28). Saw blade noise - how to reduce it is very important! NCcttingtools.
Retrieved from
https://www.nccuttingtools.com/saw-blade-noise.html#Chapter_4_10_Ways_To_Reduce_
The_Operating_Noise_Of_The_Saw_Blade
South Coast Air Quality Management District. (2019) South Coast AQMD Air Quality Significance
Thresholds. Retrieved from
http://www.aqmd.gov/docs/default-source/ceqa/handbook/scaqmd-air-quality-significance
-thresholds.pdf?sfvrsn=2
The Body Shop. (n.d.). Home - The Body Shop. Retrieved from
https://www.bodyshopgentlemensclub.com/
The Den On Sunset. (n.d.). Hours and Location. Retrieved November 30, 2022, from
https://www.thedenonsunset.com/location/the-den-on-sunset/
60