Document No: LOCL/BSVIQC/001
Indio
Rev. 0, November 5, 2015
Page 1 of 2
QUALITY DEFICIENCY REPORT
Project Location: —] Contractor: Date: Final Inprocess | Report No
OCL Paradip/BS-VI_| M/S Tuaman Engg. Ltd (Composite) 22.05.2020 Qo & zSvnrE)
Inspection Checklist, Specification, Or Drawing Used As Reference: _ Specification N
PDRP-8440-SP-0018 Rev. F2,and_Method Statement AG Piping
Location: Piping Fabrication Yard
" Description Of Discrepancy: _Noted welding electrode E7018 used without backing /
temperature not maintained for Line no. 400-WCR-058-2001P-A2AW-NI, Joint no. 19, Spool
10.3
" Surveillance/Deficiency: Non completion of the quality
‘See attached pictures —Photo-0 page
‘TEIS Surveillance Personnel: Mr. Abdul Waheedu, Manager Quality
‘Name Tile
Person Notified Of Deficiency: _Mr. Rajeev / Kaustay Samanta 22.05.2020
Tuaman Staff Date
™ Recommended Corrective Action by KIS _ Gouging and re filling shall be performed and RT shall
be taken for above joints / Proper function / Calibration of Portable oven& mother oven shall
Checked by Tuaman on regular basis
'Y Comrective Actions Implemented Accepted:
HIS Quality Personnel/Date Contractor Quality Control / Date:
TIS Site Construction Manager/DateDocument No: LOCLIBSVI/QC/001
Rev. 0, November 5, 2015
Page 2 of 2
QUALITY DEFICIENCY REPORT
Project Locat Contractor: Date: Final Inprocess | Report Nox
1OCL ParatipiBS-V1_[ M/S Twaman EagesLid (Compesitey | 22.05.2000 _| Ul BS VUTELION