You are on page 1of 2

BRIDGE & ROOF CO.

(INDIA) LTD EIL STANDARD SPECIFICATION NO


A GOVERNMENT OF INDIA 6-82-1100 Rev 1
ENTERPRISE

FORMAT NO: 1110 REV 1 : BR/70909/MECH/F19 REV-0

PIPING HYDRO TEST RELEASE / ACCEPTANCE RECORD (A/G PIPING)

Project: Report No:


Plan Date:
Contractor: Area:
Loop No: REP P & ID No.
INCH MTR:
From To

Sl. No Line No. (s) Sl No. Isometric No. (s) P&ID No. (s) Sl. No.

Test Medium: Test Duration: Design/Test Pressure:


Test Pressure Gauge No. Range Calibration Certificate No: Gauge Calibration Date:

Item to Check Accepted Witness


B&R EIL
Field Installation Checklist Prior to Hydrotest Signed
Punch list Prepared Yes No
Pre-Hydrotest Punch items Cleared
Accessibility to Inspection / Witness Locations
Capacity of pressurizing pump checked
Cordon off area for high pressure testing, as required
Pre-hydrotest flushing carried out
IBR/Others test Witnessing Required Yes No
System Released for Pressure Testing:

B&R: EIL:

Sign: Sign:

Name: Name:

Date: Date:

Page 1 of 2
BRIDGE & ROOF CO. (INDIA) LTD EIL STANDARD SPECIFICATION NO
A GOVERNMENT OF INDIA 6-82-1100 Rev 1
ENTERPRISE

FORMAT NO: 1110 REV 1 : BR/70909/MECH/F19 REV-0

PIPING HYDRO TEST RELEASE / ACCEPTANCE RECORD (A/G PIPING)

Designation: Designation:
ACTIVITY Date Time
Water Filling and Venting started at
Water Filling Completed
Vents Closed
Isolation of Pressurizing pump
Test completed at:
- Water drained
- Air
- Temp Blinds Removed
- Checked for reinstallation of
a. Control & Safety vales
b. On line Instruments
c. Rupture disks
d. Deblinding
e. Others
- Cold setting of spring supports carried out

B&R: EIL:

Sign: Sign:

Name: Name:

Date: Date:

Designation: Designation:

Page 2 of 2