Project Logo Project Name : Marina Mix-50 @ Lusail District for Sh.

Hamad Bin Faisal Al Thani


Project No. : P-233 Form No.: P07-F06 /Rev. 0 / Nov. 2012
Client MEP SUB CONTRACTOR Consultant Contractor
Sh. Hamad Bin Faisal
Al Thani

COMMISSIONING FORM_Small Power Socket


Description:
Area / Location :
Work Inspection Request ( WIR ) Ref. No.
Reference / Drawing:
SI Report / Result Result Verified by: Remarks
Inspection / Check Point RCC/HR/AA
No. Date REDCO AEB
Preview WIR and check pre-commissioning
1 form ,ensure all comments have been addressed
Check pre-commissioning snag list is attached
2 and complete
Preview and check all electrical test form, ensure
3 all comments have been addressed
Functional Test: socket outlet, supply source 1&2,
4 confirm availability of power and polarity of each
socket outlet IAW section 8.2.6 subsection e.
Functional Test: socket outlet, supply source 1&2,
confirm and record earth loop impedance and
5 prospective short circuit test IAW section 8.2.6
subsection d.
Functional Test: Three phase socket , carry out
6 and verify the voltage of the power supply no.
1&2, phase to phase and phase to neutral.
Functional Test: Three phase socket, supply
source 1&2, confirm satisfactory completion of
7 prospective short circuit test IAW section 8.2.6
subsection d.
Functional Test: Three phase socket, confirm /
carry out and record the operation times of
8 residual current operated device IAW section
8.2.7 subsection e are satisfactory.
Check the labeling and tagging and descriptive
9 identification
10 Check all equipment for damage
Legend Accepted ( OK ) Rejected with remarks Not Applicable
Comments

Inspected by: Checked by Approved by


Name Name Name
Company Company Company
Signature Signature Signature
Date Date Date