Innovative Contractors for Advanced Dimensions

Main Contractor: Saudi Bin Ladin Group


Project Name: King Abdullaziz International Airport Development Project -KAIADP-JEDDAH, K.S.A

J-10-421-PF-0 (Terminal Complex, Control Tower & Supporting Facilities)


Contract Title /No.:
J-10-422-PF-0 (Aprons,Taxiways,Roads,Tunnels,Bridges,Load Centers & Infrastructure,
Transportation Center & Supporting Facilities)

Electric Generator Inspection Checklist


Site entry Number:
Identification Number: Make:
Owner's Id: Model:
Third Party Sticker Validity: Year:

Electric Generator N/A OK Fail Remarks


1 Silencer/Exhaust Noise/Fumes
2 Fuel Leakage
3 Oil Leakage
4 Spill containment tray installed
5 Untidy Wiring
6 Controls access secured. Area Fenced
7 Access limitation and safety warning signs installed
8 Rotating component protected by screen/guard
9 Connector Terminal Covered/Access Secured
10 Distribution cables protected/location marked
11 AC Power Outlet ELCB Protected
12 Power Outlet Individual Switch/Breaker protected
13 Battery Cables connection clean/secure
14 Battery Properly Secured
15 Frame, ground connection point/cable/stake
16 Doors close and secure in open position
17 Ohm rating of grounding
18 Exhaust and Noise emissions
19 Danger Signs & Poster
20 Physical barricade around the generator
21 Fire extinguisher (Type & Capacity)

Inspected by:
Name Position Signature

Accept for Work To be re-tested


Approved by:
Name Position Signature

Remarks: