You are on page 1of 2

Stage 1

Catchment A
235640 sq.m.

Drainage A1

Catchment D Drainage A2
39000 sq.m.

Drainage B2
Basin A Drainage C1
(12 x 6 x 2m)
Catchment B
Drainage B1
77450 sq.m.
Legends

existing/ proposed channel


Catchment C
direction of surface runoff 233230 sq.m.
Basin B
temporary bund (12 x 6 x 2m)

temporary/ permenent
runoff collection basin Drainage C2

catchment area
Basin C
(12 x 6 x 2m)
Stage 2

Drainage D1 Catchment A
Drainage A1
163000 sq.m.

Area 0-B1 completed,


permenent surface water
Catchment D
management design is
56300 sq.m. considered seperately
Drainage A2

Drainage B2
Basin A Drainage C1
(12 x 6 x 2m) permenant basin to be Catchment B
considered separately 77450 sq.m. Drainage B1

Legends

existing/ proposed channel


Catchment C
direction of surface runoff 233230 sq.m.
Basin B
temporary bund (10 x 5 x 2m)

temporary/ permenent
runoff collection basin Drainage C2

catchment area
Basin C
(12 x 6 x 2m)