This hot work proposal outlines the necessary safety procedures and authorizations for hot work to be conducted aboard the vessel Glow Shipping Lines L. L. C. The proposal specifies the vessel and intended work date, as well as the location, reason, and estimated duration of the work. It details the procedures to ensure integrity of the work location, ventilation of the area, and effective fire protection. The hot work equipment to be used is also specified. Authorizations from the Master, Chief Engineer, and Superintendent/Technical Manager are required before office approval can be granted.
This hot work proposal outlines the necessary safety procedures and authorizations for hot work to be conducted aboard the vessel Glow Shipping Lines L. L. C. The proposal specifies the vessel and intended work date, as well as the location, reason, and estimated duration of the work. It details the procedures to ensure integrity of the work location, ventilation of the area, and effective fire protection. The hot work equipment to be used is also specified. Authorizations from the Master, Chief Engineer, and Superintendent/Technical Manager are required before office approval can be granted.
This hot work proposal outlines the necessary safety procedures and authorizations for hot work to be conducted aboard the vessel Glow Shipping Lines L. L. C. The proposal specifies the vessel and intended work date, as well as the location, reason, and estimated duration of the work. It details the procedures to ensure integrity of the work location, ventilation of the area, and effective fire protection. The hot work equipment to be used is also specified. Authorizations from the Master, Chief Engineer, and Superintendent/Technical Manager are required before office approval can be granted.
Vessel: Proposal No. Date Issued: Vessel ‘s Condition : Ballast Laden Intended Work Date: Location and access arrangements (including staging if appropriate):
Reason for doing the work at the requested position and not in the Engine Workshop:
Work to be carried out including estimated duration:
Detail the procedures to ensure the integrity of the Hot Work location with respect to: a) Valves/plugs/blanks/spades, etc; 1 b) Pipelines and their contents including heating coils, c) Atmosphere. d) No cargo/ballast/IG/gas freeing/bunker operations to be carried out during the validity of the work permit.
Detail the method of ensuring continuous ventilation of the work location and where appropriate, the method of extracting toxic 2 fumes:
3 Detail the procedures in place to ensure effective fire protection at the work site and adjacent spaces:
4 Specify the Hot Work equipment to be used for the work under consideration and confirm its availability:
Master Chief Engineer Shipboard Authorisation: Name Date Name Date
Office Authorisation: Yes No Name Date Superintendent/Technical Manager* DPA * Cross Out as applicable
Form: SF105 Rev. MAY 2015 Issued/Approved by: DPA/GM Page 1 of 1 MS – M6