You are on page 1of 25

Presenter

Amr Mohamed Gad


Senior Machinery Engineer with RasGas company since 2007

• 13 years of experience in maintenance, retrofits, and upgrades


of Gas Turbines, Compressors and Pumps in natural gas facilities.

• Previous publications at 5 major worldwide conferences


Boiler Feed Water Pumps Performance Loss

Amr Mohamed Gad– RasGas


Dr.Nicholas White – RasGas
Arbain Bin Mahmood– RasGas

2nd Middle East Turbo Machinery Symposium


17th – 21st March 2013

1 / Boiler Feed Water Pumps Performance Loss | March13


Index

• RGX2 Steam Condensate System


• Problem Summary
• Troubleshooting History
• Unit 92-A261A –Failure
• Performance Deterioration
• RCFA-Unit 92-P261A
• Operational Risk Mitigation
• Recommendations Results
• Lessons Learned

2 / Boiler Feed Water Pumps Performance Loss | March13


RGX2 Steam Condensate System

Steam condensate system set up at RGX2


• Total of x6 Boiler Feed Water Pumps (x4 steam driven pumps and
x2 motor driven pumps).

Operating philosophy N+2:


• x4 in service and x2 Stand by operation.

x6 No. BFW

3 / Boiler Feed Water Pumps Performance Loss | March13


RGX2 Steam Condensate System

Pump specifications:
• Rated capacity 750 M3/hr
• Rated power 1.7 MW
• Differential head 680m
• Horizontally split casing
• 4 stage with double inlet impeller

4 / Boiler Feed Water Pumps Performance Loss | March13


RGX2 Steam Condensate System

New pump before installation Old pump at skid in RGX2

5 / Boiler Feed Water Pumps Performance Loss | March13


Problem Summary

• One pump experienced high thrust bearing temperature alarm


after 16 months of operation

• The thrust bearing was replaced twice during the following 6


months without identifying the root cause
• System operation indicated low pump performance (flow rate
and head rise)
• During the 25 months of operation, thrust bearing temperature
again reached high alarm level and pump was found seized
upon inspection

6 / Boiler Feed Water Pumps Performance Loss | March13


Troubleshooting History

Historical Records
Unit 92-P261A historical events shown on a timeline
pump’s thrust bearing temperature
increase due to bearing degradation over
one year – alarm level reach xx deg C
Plot-0

120 92TI6864AA.PV
32.137
92TI6864AB.PV
100
28.376
92TI6864BA.PV
65.055
80
92TI6864BB.PV
58.462
60 92TI6865AA.PV
32.43
92TI6865AB.PV
40 29.695
92TI6865BA.PV
74.042
20 92TI6865BB.PV
75.849
92PI6802A.PV
0 7.4481E-02
10/6/2009 8:20:59.518 AM 372.00 days 10/13/2010 8:20:59.518 AM 92PI6517.PV
92P261A PMP NDE BRG TEMP 61.984
92P261A PMP NDE BRG TEMP 92PI6518.PV
92P261B PMP NDE BRG TEMP 61.994
92P261B PMP NDE BRG TEMP
92P261A PMP NDE BRG TEMP
92P261A PMP NDE BRG TEMP
92P261B PMP NDE BRG TEMP
92P261B PMP NDE BRG TEMP
OIL TO PMP & TURB 92P261A
WB FR 92P261ABCD
WB FR 92P261ABCD

7 / Boiler Feed Water Pumps Performance Loss | March13


Troubleshooting History

Unit 92-P261A -Vibration readings


Plot-0 11.624 11.624

28
10.842
18.608
Pump D.E/N.D.E VAH&VAHH is 50/70 Mm PK-PK 11.233
21.319 \\RTIS67\92VI6808AA.P
25.592 26.349 12.015
8.1319 8.1319 UM PP
8.1319 7.7411 \\RTIS67\92VI6808AB.P
Pump D.E 6.2027 5.0305 11.233
24 8.9133 8.9133 UM PP
radial vibration 7.3748 7.3748 \\RTIS67\92VI6809AA.P
20.928
UM PP
\\RTIS67\92VI6809AB.P
25.958
19 UM PP
\\RTIS67\92VI6810AA.P
8.1319
UM PP
\\RTIS67\92VI6810AB.P
8.1319
UM PP
14 \\RTIS67\92VI6810BA.P
Pump N.D.E 6.2027
UM PP
radial vibration \\RTIS67\92VI6811AA.P
8.9133
UM PP
9 \\RTIS67\92VI6811AB.P
Turbine D.E & N.D.E 7.7411
UM PP

radial vibration

4
2/1/2012 7:45:40.602
4:39:46 PM AM 7.00 days 2/7/2012
2/8/20125:34:00
7:45:30.806
PM AM
92P261A PMP NDE VIB X
92P261A PMP NDE VIB Y
92P261A PMP DE VIB X
Turbine D.E/N.D.E VAH&VAHH is 25/37 Mm PK-PK
92P261A PMP DE VIB Y
92P261A TURB DE VIB X
92P261A TURB DE VIB Y
92P261ABTURB DE VIB X
92P261A TURB NDE VIB X

8 / Boiler Feed Water Pumps Performance Loss | March13


Unit 92-A261A –Failure

Thrust Bearing failure signs:

Scoring and smear on thrust pads Smeared Journal pads

9 / Boiler Feed Water Pumps Performance Loss | March13


Unit 92-A261A –Failure

Cavitation damage on 1st stage

Casing erosion

Cavitation damage

10 / Boiler Feed Water Pumps Performance Loss | March13


Unit 92-A261A –Failure
RCFA initiated August 2011 and completed October 2011

Casing erosion

11 / Boiler Feed Water Pumps Performance Loss | March13


Performance Deterioration

5
e r
s
th p
O um
p

Pump A

Optimum performance Deteriorated performance Other pumps performance

12 / Boiler Feed Water Pumps Performance Loss | March13


RCFA-Unit 92-P261A

13 / Boiler Feed Water Pumps Performance Loss | March13


RCFA-Unit 92-P261A

RCFA – Findings
• Root Cause (Human) - Incorrect material specification of the
pump casing for boiler feed water service led to major damage
of casing inner walls and rotor parts
• Contributing Factor 1 (Latent) – Insufficient online monitoring
of pump performance due to inadequate instrumentation
prevented effective pump health monitoring
• Contributing Factor 2 (Latent) – Inadequate surveillance
program for boiler feed water conditions led to a possible
corrosive environment within pump flow path

14 / Boiler Feed Water Pumps Performance Loss | March13


RCFA-Unit 92-P261A

RCFA – Recommendations
• Immediate action: Purchase x6 new BFWPs with 12%Cr Stainless
Steel casings and replace the existing pumps with carbon steel
casing
• Medium action: Revise the Equipment Strategy to perform a
bi-monthly online performance monitoring task including steam
condensate dissolved oxygen and pH levels to ensure they
remain within specification
• Long term action: Improve online monitoring by installation of
the following:
-Digital discharge pressure transmitter
-Install flow measurement devices on the discharge and
recirculation line

15 / Boiler Feed Water Pumps Performance Loss | March13


Operational Risk Mitigation

Contracts Dep. Electrical and Instrumentation Eng.

Manufacturing Dep. Rotating Machinery Eng.

Recovery TEAM

Maintenance Process Eng.

Asset Management Supply Dep.

16 / Boiler Feed Water Pumps Performance Loss | March13


Operational Risk Mitigation

Integrated Repair plan


• x3 pumps repaired between October 2011 and March 2012
• x2 pumps were repaired used spare parts manufactured by
third party as fast track repair to save time

• System reviewed for equipment reliability


(Turbines, Automatic Recycle Valves, Instruments etc.) and
corrective actions taken as appropriate

• Close monitoring and measurement of discharge and recycle


flow using clamp flow meter to assess pump performance

• Long term - Installation of x6 new BFW pumps with stainless


steel casing (procurement and installation during 14 months)

17 / Boiler Feed Water Pumps Performance Loss | March13


Recommendations Results

• Performance for the repaired 3 units as interim solution was


similar to OEM design.
• Ultimate replacement of all pumps by new stainless steel
casing's units results in operating the BFW system with reliable
units as per OEM design.

Optimum performance

18 / Boiler Feed Water Pumps Performance Loss | March13


Lessons Learned

• Follow API610 guidelines during equipment procurement


(material specifications versus fluid service)
• Improve datasheet and specification review during project
FEED and procurement
• Improve online monitoring instruments required during plant
design

19 / Boiler Feed Water Pumps Performance Loss | March13


Questions?

Authors:
Amr Mohamed Gad – RasGas
Dr. Nicholas White - RasGas
Arbain Mahmood – RasGas
asmohamedgad@rasgas.com.qa

20 / Boiler Feed Water Pumps Performance Loss | March13


Backup

21 / Boiler Feed Water Pumps Performance Loss | March13


23 | RasGas classification/title heading | December 12
24 / Boiler Feed Water Pumps Performance Loss | March13
Operational Risk Mitigation

Integrated Repair plan

26 / Boiler Feed Water Pumps Performance Loss | March13

You might also like