• Main Engine : Gas Engine
• Installed Capacity : 16 MW AF 95%
• Contract Developer : EPC + O&M
• Project Schedule : 8-10 Months COD
• Area required : 5000 m2
• Gas Supply : 2.5 MMSCFD
• Net Power Output : 12.5 MW
• Voltage/Frequency : 20 kV/70 kV/50 Hz
6
Why Gas Engine :
1. No need for high pressure gas ~5 bar
adequate
2. No external Power from the grid during
start up
3. Normal start up time ~ 10 minute from
the cold start up to Full Load
4. Due to multi unit concept, alternative
back up capacity may not required
5. Multi unit benefit (step wise investment
and high plant availability)
6. Maintenance Schedule not depending on
number start up, stop and trip
7. Efficient and power output is very stable
until 35 deg C ambient temperature
(suitable in tropical country)
8. Delivery time is shorter compare to Gas
Turbine
7
8
PPA
12.5 40 PJBG
MW MW
14 TM2500 GAS TURBINE AERO 30,000 9,730 0.009222 37.00 1,186.82 3000 50
15 SGT A45 mobile GAS TURBINE AERO 39,300 9,375 0.008885 38.40 1,143.55 3000 50
2,680,069.93 B&D comp USD pa
Component A (Investment) 5,897,404.84 C comp USD pa
Development Cost 16,800,000.00 A comp USD
13,440,000.00 principal loan
EPC Cost
3,360,000.00 equity
Cost of Fund USD/KWH
672,000.00 interest
Component B ( O & M Fixed) 134,400.00 repayment p.a
Manpower & Tools
INVESTMENT 12,071,874.77 total cost USD pa
Component C (Fuel) PERIOD 2,477,076.28 USD gross revenue
Gas (USD/MMBTU)
Component D ( Variable O & M) 109,500,000.00 kWh
AVAILABILITY 1,900.00 IDR/kWh
Spare Part
FACTOR 208,050,000,000.00 IDR revenue
Consumables 14,548,951.05 revenue USD
Component E ( Transmission)
0.1102 cent USD est egc
1,576.51 IDR estimated egc
Project Preparation
Project Operation
Feasibility Study
Operation
Technical Maintenance
Commercial Tools & Spare Part
AMDAL (UPL/UKL) Gas Supplier
All Permit
Land Status
13
MULAI
PROSES Feasibility Grade Design
Spesifikasi teknis
Desain layout
Data survei Data kebutuhan PID
geologi dan kelistrikan
hidrologi TIDAK
Sesuai dengan
Penentuan lokasi pembangkit kebutuhan ?
Ketersediaan bahan bakar
Ketersediaan sumber air
Analisis geoteknik Survei vendor YA
Simulasi balans energi Survei lapangan
Data sekunder
Perkiraan konsumsi BB Analisis Kelayakan
keekonomian
Investasi
Rekomendasi
TIDAK Hasil
cocok ? 14
YA AKHIR
PROSES
Peraturan Pemerintah Nomor 14 Tahun 2012
tentang
Kegiatan Usaha Penyediaan Tenaga Listrik (1)
9. Izin Operasi dapat diberikan untuk jangka waktu paling lama 10 (sepuluh)
tahun dan dapat diperpanjang.
17
Peraturan Pemerintah Nomor 14 Tahun 2012
tentang
Kegiatan Usaha Penyediaan Tenaga Listrik (4)
10. Instalasi Tenaga Listrik yang beroperasi wajib memiliki Sertifikat Laik
Operasi.
18