You are on page 1of 3

Weston Solutions (India) Pvt. Ltd.

COST ESTIMATOR PROFILE

SRINIVASA RAO DARLA


Qualifications Summary

Registration Licensed Surveyor / Loss accessory Office of the Controller of Insurance, Government of India Licensed Surveyor Narasaraopet Municipality, AP, India. Fields of Competence End-to-end execution of Civil and Structural Engineering Projects; Designing, Planning, Monitoring and Coordination of Projects; Site Inspections. Education B.E., Civil Engineering Gulburga University (1990), Karnataka, India. Employment History 2007 Present WestonSolutionsPvtltd. 2004 2007 Arrow Constructions Ltd 1994 - 2004 SriSrinivasaArchitects 1992 - 1993 PriyadarshiniSpinningLtd. 1991 - 1992 Krishnadevaraya Charitable Trust Building Key Projects at Weston: Improve Military Family Housing, Phase 7 At Kadena AB, Japan:- Estimations of civil, Architectural, Structural, Landscaping and performing all work necessary for improvements to Family Housing, consisting of 511 Military Family Housing (MFH) units. The MFH includes portions of the Camp Courtney, Terrace Heights, Kadena Heights, Marek Park, and two of the Bazley Towers. Estimation for Renovations of Red flag Alaska, Bldg 1141 to Coal War fighter (CW)/Support Facility at Eielson AFB, AK (LEED Bldg): -- Estimations for Renovations in Bldg 1141 will involve converting the existing facility into vaulted briefing, administrative, storage, and supply and maintenance space and An auditorium, planning and briefing rooms, security office, classified equipment storage, and an area for range equipment maintenance operations will be added to the existing building.

Over 17 years of experience in civil engineering. Extensively involved in end-to-end execution of civil and structural engineering projects dealing with construction buildings, CC roads, along with utilities and infrastructure. Expertise in designing, planning, monitoring and coordinating projects. Proven abilities in designing the buildings, structures as per the laws, safety & security norms. Conducted inspections site

Experienced in coordinating with clients, consultants and Project Managers for the smooth functioning of overall operations. Worked on implementing quality standards and maintaining the relevant documents.

CORPLAN01|/opt/scribd/conversion/tmp/scratch6229/64739110.doc 4-digit date

Weston Solutions (India) Pvt. Ltd. SRINIVASA RAO DARLA

Mahaffey Middle School, Fort Campbell, Kentucky:-Estimations for renovate portions of the Headquarters Air Force Center for Engineering and the Environment (AFCEE), consists of load bearing exterior masonry walls setting on shallow spread footings with floating concrete floor slabs on grade, combination of concrete masonry load bearing walls with some steel columns and beams, the roof deck is supported by metal decking on steel joists, roof deck of 2 1/2 inch gypsum decking on steel joists, the roof consists of built-up roofing and ethylene propylene diene monomer (EPDM) roofing on rigid insulation. Renovations of Building 500, Malmstrom AFB, Montana (For installation control center):-Estimations for Renovate the interior of the Building 500, ICC. And will be phased into 3-4 areas to remain in operation and security of each area maintained, A portion of the northwest corner of the building will have the second floor level removed to create a large volume of space for the main command area, this space will incorporate raised access floor and a two story conference area.
Camp Ripley POL Road Repair & EFSO: -- Estimation of Pave POL Roads - Asphalt paving

between the existing concrete containment fuels trucks parking (airfield) and operating apron, which is in gravel. Asphalt paving between the existing Installation roads and the truck off-load area, which is in gravel road. Curbing and Concrete Sealing for Fuel Spill Containment- Re-seal joints, add a remote concrete basin(s), and improve overall drainage (including a lift station, drain pipe, etc). Access Apron, Grissom ARB, Indiana; Estimation for Existing surface of concrete (3-inch maximum depth) and asphalt repair patches on the access apron between Hangers 1, 2, 3, 4, 5 & 6. Replace additional concrete in areas of failure upon removal of top 3-inches of surface, Replace concrete surface with asphalt concrete in accordance with the latest Air Force guidance for aircraft taxiways and parking aprons, Replace asphalt concrete in areas surrounding the Hangers. Previous Key Projects Group Housing, Bhoopalapalli, AP, Singareni Collieries:- Billing Engineer. Project involved constructing quarters for the employees in Singareni Collieries. Design included construction of NB (16 with 16 servant quarters), NC (38), C2 (40) type quarters in 180,532 square foot (ft2) plinth area. The project was worth nine cores INR. Construction work included building individual compound walls, drain and sewer lines for the officers quarters in Singareni Collieries. Handled all activities related to construction and billing of various materials such as steel, concrete, brick wall, wood, sanitary and waterlines, internal concrete roads, etc Hospital, Singareni Collieries, Bhoopalapalli, AP, India: -- Billing Engineer, Project involved constructing a 50-bedded hospital in a 43,690 ft2 plinth area. The project was worth 4 cores INR. The plan included construction of 900 meter-compound wall, drain line and sewer lines, concrete roads for the employees at Singareni Collieries. Handled all activities related with construction and billing of various materials such as steel, concrete, brick wall, wood, sanitary and waterlines, internal concrete road, etc. Office and Cold Storage for Medicines, District Medical and Health Office (DM&HO), Warangal, AP, India: - Civil Engineer. The project involved designing and building an office and cold storage for DM&HO at Warangal town. The project was built in an area of 16,495 ft2 plinth area with raft foundations. The project was worth 1.5 Core INR including compound

CORPLAN01|/opt/scribd/conversion/tmp/scratch6229/64739110.doc 4-digit date

Weston Solutions (India) Pvt. Ltd. SRINIVASA RAO DARLA

wall, drain line and sewer lines. Handled all activities related with construction and billing of various materials such as steel, concrete, brick wall, wood, sanitary and waterlines, etc. Residential Complexes, Various Locations, Multiple Clients: -- Civil Engineer. Project involved constructing residential complexes for various clients. Responsible for preparation of project cost estimates, and drawings. Involved in developing design specifications, conducting field inspections, procuring material for work. Also responsible for execution of work. Commercial Complex, Various Locations, Multiple Clients: -- Consulting Engineer. Projects involved constructing commercial complexes for various clients. Responsibilities included preparation of project cost estimates, and drawings. Also responsible for design specifications, field inspections, procurement of material and execution of work. Land Survey, Various Locations, Multiple Clients:- Surveyor. Projects involved surveying of lands in residential, commercial and industrial areas using dumpy level, Theodolite, etc. ------------

CORPLAN01|/opt/scribd/conversion/tmp/scratch6229/64739110.doc 4-digit date