Procedures
Step 1: Open the pneumatic developer.
Step 2: Click the “+” sign, then fill up the examples needed to perform the
operations.
Step 3: Choose all the materials needed. Click the “tools” in the upper left corner of
the screen, and then click the “clock” sign to portray the given instructions.
Step 4: Select the materials that corresponds to your laboratory, then drag them to
your window.
Step 5: Configure the 5/2 way DVC valve, double click and select“piloted” both
sides, then ON the “spring return”.
To set up the two 3/2 way DVC, double click and select “button” on the right side,
and ON the “spring return” on both sides.
Then, followed by the last one 3/2 way DVC, which is on the left side, double click
and select “roller” on the the left side and ON the “spring return”.
Step 6: Exhaust points, connect all the terminals, be sure it is connected and
configured. For the remaining terminals, double click and select “Exhaust not
Channeled” to configure the exhaust points.
Step 7: Flow simulation to simulate the process. Press the play button to operate the
simulation. It shows the Double Acting Cylinder push and pull. Lastly, save your
work.
LABORATORY 6
Pneumatic Circuit for Embossing Application
Name: ____________________ Date Submitted:_________________
Course & Section: ____________ Score:________________________
Components Used
Procedures
Step 1: Open the pneumatic developer.
Step 2: Click the “+” sign, then fill up the examples needed to perform the
operations.
Step 3: Choose all the materials needed. Click the “tools” in the upper left corner of
the screen, and then click the “clock” sign to portray the given instructions.
Step 4: Select the materials that corresponds to your laboratory, then drag them to
your window.
Step 5: Configure the 5/2 way DVC valve, double click and select“piloted” both
sides, then ON the “spring return”.
To set up the right area of the 3/2 way DVC, double click and select “button” on the
right side, and ON the “spring return” on the left side.
Then, followed by the left area of the 3/2 way DVC, double click and select “roller”
on the the right side and ON the “spring return” on the both side.
Lastly, for the remaining 3/2 way DVC, double click and select “button” on the right
side, and “button with
lock” on the left side, then ON
the “spring return” both
sides.
Step 6: Exhaust points, connect all the terminals, be sure it is connected and
configured. For the remaining terminals, double click and select “Exhaust not
Channeled” to configure the exhaust points.
Step 7: Flow simulation to simulate the process. Press the play button to operate the
simulation. It shows the Double Acting Cylinder push and pull. Lastly, save your
work.
LABORATORY 5
Pneumatic Circuit for Shuttle Valve Operation
Name: ____________________ Date Submitted:_________________
Course & Section: ____________ Score:________________________
Components Used
Procedures
Step 1: Open the pneumatic developer.
Step 2: Click the “+” sign, then fill up the examples needed to perform the
operations.
Step 3: Choose all the materials needed. Click the “tools” in the upper left corner of
the screen, and then click the “clock” sign to portray the given instructions.
Step 4: Select the materials that corresponds to your laboratory, then drag them to
your window.
Step 5: Configure the 5/2 way DVC valve, double click and select“piloted” both
sides, then ON the “spring return”.
To set up the right area of the 3/2 way DVC, double click and select “button” on the
right side, and ON the “spring return” on the left side.
Then, followed by the left area of the 3/2 way DVC, double click and select “roller”
on the the right side and ON the “spring return” on the both side.
Next, set up the center 3/2 way DVC, double click and select “pedal with lock” on the
right side, and ON the “spring return” on the left side.
Lastly, for the remaining 3/2 way DVC, double click and select “button” on the right
side, and “button with lock” on the left side, then ON the “spring return” both sides.
Step 6: Exhaust points, connect all the terminals, be sure it is connected and
configured. For the remaining terminals, double click and select “Exhaust not
Channeled” to configure the exhaust points.
Step 7: Flow
simulation
to simulate
the process.
Press the play
button to operate
the simulation.
It shows the
Double Acting
Cylinder
push and pull.
Lastly, save your
wor