Premium Percentage Calulations For Arriving Costs of COS Works (either +ve or -ve) in HAM Projects

Variable Factor Premium over


NHAI Estimated Fixed Factor (multiplying) =
Bid Project Cost Applicable SOR SOR Applicable (in force ) as on the Bid
Bid Due Date Project Cost as (multiplying) as per BPC/Estimated Project
SN. Project Name (Rs. Cr.) Rates for COS Items Due Date, as per Article 16.6.1 (i)
per RFP (Rs. Cr.) Article 16.6.1 (ii) Cost, as per Article (multiplying factor)
16.6.1(iii)
A B C D= A/B E = C*D to be ascertained by concerned site

1 Dausa-Lalsot 15-Jun-16 881.0 688.71 1.08 1.28 1.38 SOR Applicable (in force) as on 15-Jun-16

2 Chitradurga-Davengere 27-Jan-17 1434.0 993.16 1.08 1.44 1.56 SOR Applicable (in force) as on 27-Jan-17

3 Jhansi-Khajuraho (Pkg-I) 28-Feb-17 1410.0 1053.41 1.08 1.34 1.44 SOR Applicable (in force) as on 28-Feb-17

4 Jhansi-Khajuraho (Pkg-II) 28-Feb-17 1310.0 1001.62 1.08 1.31 1.41 SOR Applicable (in force) as on 28-Feb-17

5 Chakeri-Allahabad 01-Aug-17 2159.0 1430.16 1.08 1.51 1.63 SOR Applicable (in force) as on 01-Aug-17

6 Aligarh-Kanpur (Pkg-II) 06-Mar-18 1197.0 923.56 1.07 1.30 1.39 SOR Applicable (in force) as on 06-Mar-18

7 Challakere-Hariyur 20-Apr-18 1157.0 910.85 1.06 1.27 1.35 SOR Applicable (in force) as on 20-Apr-18

8 Aligarh-Kanpur Pkg-V 21-Jan-20 2052.0 1621.85 1.06 1.27 1.34 SOR Applicable (in force) as on 21-Jan-20

9 Unnao-Lalganj 23-Jan-20 1602.0 1437.33 1.06 1.11 1.18 SOR Applicable (in force) as on 23-Jan-20

10 Meerut-Nazibabad 23-Jan-20 1412.0 1071.31 1.05 1.32 1.38 SOR Applicable (in force) as on 23-Jan-20

11 Jagdishpur-Faizabad 24-Jan-20 1530.0 1051.50 1.06 1.46 1.54 SOR Applicable (in force) as on 24-Jan-20