You are on page 1of 18

Control & Monitoring

Q Control systems vary from one

compressor manufacturer to another

Q John Crane use flow control

Q Some OEMs use pressure control

Q John Crane supply a monobloc system

11
Key System Functions

Filter Measure Control

Control Measure

Measure

Bearing

22
Monobloc Double Filter

With integrated:

Q Switch-over valve
Q By-pass / filling valve
Q Vent / purge valve for
each filter
Q 2 shut-off valves on
inlet and outlet for
differential pressure
measurement

Q Material: Stainless steel


Q NACE certification
Q 200 bar g

33
Double Filter Unit

Removal of sintered metal filter cartridge

44
2 x Tandem Seals - inner labyrinth
End User: Trenergy

OEM: KHI Japan

Application: Gas field

Buffer Gas: N2

Product: Methane

Pressure: 133 bar g

Temperature: 105°C

Materials: Stainless steel

55
Control Panel – Nuovo Pignone

66
Control Panel - Settings
Q Primary Vent
³ Set variable orifice to give DP of 0.5 bar
X Ensures bursting disc is not ruptured

X Provides positive pressure to O/B seal

X Enables condition monitoring of O/B seal

³ Alarms (Typical)

X 2 bar alarm (4 x normal flow)

X 4 bar shutdown (8 x normal flow)

Q Type 82 / Labyrinth (Typical)


³ Nitrogen / air 0.2 bar differential for labyrinth
³ Nitrogen / air 0.4 bar differential for Type 82
77
Control & Monitoring

Q On flooding compressor
³ dirty gas can get into seal area
³ use N2 purge before & during start-up

Q Liquid contamination
³ C7 and below, HC can condense out with
Joule-Thompson effect across needle
valves - congeals in spring areas etc.
³ keep gas temperature well above dew-point

³ lag pipework, add heating downstream of


needle valves

88
Typical Hydrocarbon Gases
Q CH4 Methane

Q C2H6 Ethane

Q C3H8 Propane

Q C4H10 Butane

Q C5H12 Pentane

Q C6H6 Benzene

99
Installation, Operation & Maint.

Q Icing can occur

³ if settle-out pressure is high (say 200 Bar)

³ pressure drop across static faces to


atmosphere can cause ice formation if free
water present in gas

³ pre-heat seals (e.g., inject warm N2) before


start-up

10
10
Installation, Operation & Maint.

Q Inboard Seal Pressure (Tandem Seals)

³ Inboard process pressure must always be


higher than primary vent (flare) pressure

³ Interspace pressure is not required for


normal operation, but prefer 0.5 bar g

³ Pressurised interspace requires control


system to avoid reverse pressurisation

11
11
Installation, Operation & Maint.

Q Barrier Gas Pressure (Double Seals)

³ Inert Barrier Gas supply pressure to seals

must be maintained at 1 to 2 bar above

sealing pressure at all times

12
12
Installation, Operation & Maint.

Q N2 buffer supply should always be on 30


minutes before bearing oil is switched on

Q N2 buffer supply should always be on 30


minutes after bearing oil is switched off

Q Filtration: usual size 3 micron. Some


prefer a finer filter.
13
13
Installation, Operation & Maint.

Q Mating Ring Corrosion

³ Free water in the seal area must be avoided

³ Majority of seals use Tungsten Carbide for

the rotating mating ring material

³ Tungsten Carbide suffers from acid and

chloride attack

14
14
Installation, Operation & Maint.
Q Reconditioning every 5 years (or so)
Q John Crane will, where economically viable:
³ Disassemble, inspect and clean
³ Replace o-rings and springs
³ Machine new thrust rings to suit new balance
diameter o-rings
³ Convex lap and polish primary rings
³ Replace primary rings if beyond re-lapping
³ Lap, polish and re-groove mating rings
³ Replace mating ring if beyond re-lapping
³ Re-machine locking sleeve to match new parts
³ Re-balance rotating assembly
³ Run full dynamic re-test, and re-calibrate

15
15
Reconditioning - Locking Sleeve
No gaps here

16
16
Reconditioning - Locking Sleeve
With no tolerance strips or o-rings installed.

Accurately machined gap here to allow for correct


o-ring compression and thermal expansion.

Incorrect gap will cause leakage behind mating rings


or broken mating rings.
17
17
Installation, Operation & Maint.
Q I.O.M.’s are supplied with every seal cartridge
Q Topics covered in the I.O.M. are :
³ Introduction to the John Crane Type 28 Gas Seal
³ Declaration of incorporation
³ Seal specification
³ Seal installation & removal
³ Commissioning procedure
³ Operation & maintenance with dry gas seals
³ Storage of seals
³ Notes on principles of operation

18
18

You might also like