DAYWORK RATES

Daywork rates will only be used as a basis for payment when normal rates for supply and fix (as
given above) are not applicable. No work shall be carried out on Daywork basis except when ordered in
writing by the Superintending Officer.

When work is so ordered the Contractor shall be paid Daywork prices plus 15% which shall
include for the use of all ordinary plant, tools and scaffolding, supervision, establishment charges and
profit. Daywork prices shall be taken to mean the actual prime cost to the Contractor of his materials,
transport and labour for the work concerned.

The Contractor shall produce for verification to the S.O. vouchers specifying the time and
materials employed on the work. If required the Contractor shall also produce his receipted bills and
wages books in support of his accounts.

When special mechanical plant is required for use on Daywork, the S.O.’s approval must be
obtained and the cost to be paid to the Contractor must be agreed before commencement of work. Only
such plant that the S.O. has accepted as special mechanical plant before commencement of work will be
considered for payment as special plant on Daywork basis.

The cost of any materials supplied by the Government for the use on Daywork shall not be taken
into account when calculating the amount on which the 15% addition is based.

Only time on work actually done will be allowed. A “Day” is considered to bbe normal working
day of 8 hours. Fractions of a day will be paid for “pro-rata”.

Rates for power driven tools are not included in the labour rates but charges for hand tools shall
be deemed to be included.

NO. DESCRIPTION UNIT RATE

A1/1
DAYWORK LABOUR RATES

A Labourer (Male – unskilled)

B Ditto (Female – ditto)

C Concrete Leveller and Screeder

D Mason

E Bricklayer

F Carpenter and Joiner

G Steel Bar Bender and Fixer Day

H Pneumatic Tool Operator

J Fitter

K Welder

L Plumber

M Painter

N Roofer

P Glazier

SCHEDULE OF BASIC PLANT CHARGES FOR USE


IN CONNECTION WITH DAYWORKS

A1/2

2
The Contract Rates for plant in the Schedule of Dayworks shall apply to all plant whether belonging to
the Contractor or hired by him and shall cover all the contractors obligations whatsoever in providing and
maintaining such plant at the place of work including operators, all fuel and lubricants, all ancillary
equipment necessary for efficient operation and use of the plant grid overheads and profits.

The Contract Rates for plant shall apply both to plant which is already available at site and to plant
brought to site especially for dayworks but in the latter case the Contractor shall be paid his additional
cost in transporting such plant to and from the site.

The daily rates in the Schedule are not intended to establish minimum charges. The rates should be
applied to the time during which the plant is actually engaged in daywork. The inclusion of an item of
plant in the Schedule does not necessarily deem nor indicate that the item is chargeable.

Rates for other plant not included in the Schedule shall be settled at prices reasonably related to the rates
so included.

NO DESCRIPTION UNIT RATE


Note: Against each item of the following
of palnt shall where applicable be entered
the type, class, capacity or rating of the
plant which the Contractor proposes to
use.

A Tipping Vehicle:
(i) 5 Tons and over Day
(ii) 3 Tons and under
B Dumper 1 cu. yd.
C Backhoe
D Air Compressor
E Pneumatic concrete breaker including
tools and hoses

NO. DESCRIPTION UNIT RATE


A1/3

3
F. Electric steam petrol diesel or other pump of any
type:
(i) 2-inch delivery (2000 gallons per hour)

G. Concrete mixer
(i) Type 10/7
(ii) Type 14/10

H. Electric welding machine

Day
J. Self-propelled road roller
(i) 6 tons and over
(ii) Under 6 tons

K. Excavator with face shovel________________m3

L. Generator (_____________kW)

M. Hydraulic rock breaker

N. Track excavator

SECTION A2 – PRELIMINARIES

4
LIST OF MATERIAL TOGETHER WITH QUANTITIES AND BASIC UNIR COST FOR
THE PURPOSE OF TENDER EVALUATION

TOTAL
ITEM CONTRACTOR
MATERIALS UNIT ESTIMATED
NO. UNIT COST
QUANTITY
1. Cement Bag 1
2. Steel Ton 1
3. Aggregate MC 1
4. Sand MC 1
5. Brick Per 1000 1000
6. Timber Ton 1
7. Roofing materials MS 1
8. Ceiling materials MS 1
9. Steel and metal sections Ton 1
10. Plumbing materials
a) MR 1
b) MR 1
c) NO. 1
d) NO. 1
11. Floor and wall tiles MS 1
12. Sanitary fittings
a) NO. 1
b) NO. 1
c) NO. 1
13. Ironmongery
a) NO. 1
b) NO. 1
14. Glass MS 1
15. Paint MS 1

I/We certify that this Schedule reflects the unit costing used in the submission of the tender and it
is based on current prevailing market price available.
Tenderer

A1/5

5
SPECIFICATION FOR THE PROVISION AND MAINTENANCE OF EQUIPMENTS
AND FACILITIES
Equipment and Facilities

The Contractor shall provide the following facilities listed hereunder for the use of the
Superintending Officer (S.O.) and/or his/her staff. All equipment(s) provided for the facilities
shall be new, delivered, tested and installed within a month of the issuance of the Letter of
Acceptance.

The facilities provided shall be maintained by the Contractor of his appointed agent throughout
the contract period until the issuance of the Certificate of Practical Completion. Maintenance
shall include all necessary, monthly servicing according to manufacturer’s specification and
supply of accessories and consumables.

The equipment(s) and facilities shall be in the custody of the Contractor at all times. Upon the
issuance of the Certificates of Making Good Defects, the Contractor shall remove all equipment
and facilities from the location.

If the Contractor fails to provide or maintain any equipment(s) for the facilities as listed
hereunder the Government shall have the right to procure the equipment(s) from other sources or
maintain it and all expenses arising shall be borne by the Contractor and an appropriate
adjustment shall be made to the Contract Sum.