Completion Operations
1
Brine Filtration : Bag type filter and a DE filtration unit.
Completion Examples
4.5”-5.5” tubing (L-
80,12.6#/17#, VAM Top)
Carbon Steel (will need
monitoring program!)
SCSSV ( ~150m)
SSD for circulation
purposes
Hydraulic, retrievable
packers
XN-landing nipple
WEG
SSD
2
Preparing the required Sub-Assemblies
3
Tubing Tongs
4
Measurement and Pipe Tally
5
Hand Slips and Elevators
Slips
Elevator
Tubing Elevators
Side Door
Centre Latch
Slip-Type
6
Flush mounted slips
7
Stabbing Guides
Tong Features
8
Typical 'Tapered Connection' Profile
Max
Opt
Torque applied to
Shoulder
MSP
Shoulder Engagement
Ref
Turns
9
Non-Marking Jaws
CRA precautions
10
Correctly bundled CRA tubulars
Packers
11
Operating Envelope
12
Control Lines & Clamps
13
Space Out Exercise
Permanent packer has been run and set on e-line # 236 (9.4m)
2.4m
Completion string including anchor latch, nipple 9.75m
and ELTSR has been run into the hole (ELTSR # 235 (9.1m)
Top of THS
pinned in the fully closed position)
0.3m
Hang-off Point
Anchor latch stabbed into the top of the packer # 234 (9.6m)
Tbg Hanger Sub-Assbly
14
Tubing Hanger Valves
15
16