100 MW
65.15€/MWh
80 MW
65.10€/MWh
60 MW
65.05€/MWh
40 MW
65.00€/MWh
20 MW
0 MW 64.95€/MWh
ERG EDPR IVPC Daunia Energia INERGIA EFFEGI
100 MW 65.20€/MWh
89 MW
90 MW
65.10€/MWh
80 MW
70 MW
58 MW 65.00€/MWh
60 MW
50 MW 64.90€/MWh
40 MW
64.80€/MWh
30 MW
20 MW 15 MW 12 MW 11 MW 10 MW 64.70€/MWh
10 MW
0 MW 64.60€/MWh
Enel ContourGlobal Engie Juwi Blusolar Energia Acea
Auction Results for Solar PV (MW) Auction Results for Onshore Wind (MW)
- -
29.2 -
-
-
17.8 50.4 - -
129.1 -
21.0 -
11.7
-
- - - -
13.2 -
67.7 3.7 - - -
2.9 18.0
187.1
- 12.6
211.3 4.1 29.4 15.3
8.4 -
5.9 136.4
▪ FER is granted by auctions of sealed bidding. ▪ Eligible technologies under the FER1 Decree are: Wind
▪ The product that is auctioned is the installed capacity of the (onshore only), PV Solar, Hydro (running water and
plant or facility. reservoir/basin), and Sewage gases.
▪ Reductions (%) to a base tariff (determined by the GSE at a ▪ Notably, plants located in other EU member states (or in a third
level of 66.5€/MWh) are offered in the auction.
neighbouring state having a free trade agreement with the EU)
▪ The bidder undertakes to deliver a certain amount of which physically export electricity to Italy can also apply for
energy, minimum auction energy, within a certain
incentives under the FER1 Decree
timeframe.
▪ The bidder will participate in the daily and intra-daily market ▪ New plants or extensions to existing facilities, such as the
and will receive a price for the energy that will be calculated hybridisation or repowering of existing renewable energy
based on the auction award price and the market price. plants, under a special procedure.
In order to apply for incentives, the following eligibility ▪ The FER1 decree established a total of 7 auctions, with the
requirements must be met: possibility to increase in case the entire capacity auctioned
a. the plant must be fully permitted; was not awarded, in which over 8GW were supposed to be
b. the connection proposal by the grid operator must auctioned.
have been accepted;
c. the constructions works must not have commenced ▪ However, due to well-known permitting issues in Italy, there
(except for plants for which applications were have been over 3.3GW that have not yet been awarded.
submitted but were not granted under the 2016 FER
▪ The GSE has already stated that all the unassigned capacity
Decree);
d. delivery of a bid bond equal to 1% of the capex (final will be auctioned off at a new auction that will close
performance bond equal to 2% of the capex to be applications on the 2nd of March 2022, and results are due on
delivered upon award of the incentive). the 31st of May. In case there will be left over capacity, there
will be a ninth auction in with starting date in May.
Source: Gestore dei Servizi Energetici
Previous auctions results
Previous auctions have seen little interest from developers, after years of unreliableness and complicated procedures
Auction Results
Installed Average Price Average
Auction Date Auction Results Published Installed Capacity Auctioned (MW) Capacity Delta (MW) Delta (%) per Auction reduction in
Requested (MW) (€/MWh) Tariff (%)
1 28-Jan-20 730 772 42 105.8% 55.10 (18.0%)
2 28-May-20 872 588 (285) 67.3% 65.09 (7.7%)
3 24-Sep-20 1,341 486 (854) 36.3% 64.59 (2.9%)
4 26-Jan-21 1,882 576 (1,305) 30.6% 65.07 (2.1%)
5 27-May-21 2,461 358 (2,103) 14.6% 65.15 (2.0%)
6 27-Sep-21 3,316 859 (2,457) 25.9% 65.17 (2.0%)
7 31-Jan-22 4,825 1,800 (3,025) 37.3% 65.10 (2.1%)
Total 15,427 5,440 (9,987) 35.3% 63.61 (5.3%)
▪ The Italian FER1 auctions have been largely undersubscribed. ▪ In view of the European Recovery Plan initiative, the Italian
The criterion that all projects must have completed the government has promised to revamp the regulatory process for
authorization process coupled with a difficult regulatory Renewable energies with an aim to accelerate the obtention of
scenario, with multiple regions incapable of clearly setting out the targets that it has set out in the National Energy and Climate
Plan.
where the authority lies has created a permitting backlog which
▪ Indeed, the Minister for the Ecologic Transition has promised
has hurt the participation to the auctions.
that a new revamped and improved version of the FER1 decree
▪ New regulations which are meant to come into force soon, will try will be published in 2022 with an aim at easing the current
to help absolve this backlog. The Regulation change will burden that developers must face.
implement a national commission composed of 40 members ▪ In the meantime, the GSE has already established one new
which will adjudicate nationally on the status of projects. This auction under the current FER1. The next auction is going to
measure is supposed to help ease the burden from regions, and have 3.3GW of capacity auctioned and results will be due the 31st
is supposed to expediate the nationally important projects. of May 2022.