Schedule

Days

HRSG/WS -220
Complete/ECCs available

Pressure Pressure CW/CCW


Tests HRSG Tests WS Condenser for WS
Done Done available available

-200
HRSG/WS
Preparation for Chem
Clean

Condensate System B.
Temporary Cleaning Commissioning
Drainage Equipment installed E.
and operational (to support chemical
System Cleaning)
ready

Aux Boiler
operational
Ready (or alternative Aux
Potable for Chem
Water ready Clean
steam supply) -161

Blow Out of Aux


Steam Lines

Execution of
Chemical cleaning
Demi Water
Treatment
Plant
operational Commissioning E/I&C/
of Aux Steam System M

Pipe Preparation/
Post inspection

HRSG Inst' Flue Gas Path E/I&C/


Demi Water/ Commissioning
Chemicals in M
Sufficient Q'ty
available
Condensate
System B.
Commissioning E.

HRSG
ready to accept Main/HRH/CRH E/I&C/
Flue gas Aux Steam System M
Commissioning

Feedwater
System E/I&C/
Commissioning M
IA/SA
DCS Pneumatic Medium/
Cabinets System Low Voltage
ready available ready

Boiler
(Eco & Steam)
Commissioning

I&Field Electrical Field


Commissioning Commissioning

Temporary Blow Out System


Equipment installed related activities
and operational substantially
completed

Main CW
operational E/I&C/
M

HVAC HRSG
ready Ready for steam
Blow

CW
Electro-chlor
Chemical Biocide dosing LEGEND :
Dosing/Sampling operational
operational
MAJOR
MILESTONES Aux Systems

HRSG ready for Hot GT System


Commissioning -142
B. Back
E. Energising