Professional Documents
Culture Documents
Segment segment
IPM D&C
Barriers Standard
Document Number:
IPM-D&C-WC-ST-006
Schlumberger Private. © Copyright 2014 Schlumberger, Unpublished Work. All rights reserved. This work contains
the confidential and proprietary trade secrets of Schlumberger and may not be copied or stored in an information
retrieval system, transferred, used, distributed, translated or retransmitted in any form or by any means, electronic
or mechanical, in whole or in part, without the express written permission of the copyright owner.
Barriers Standard IPM-D&C-WC-ST-006
Amendment Summary
Preface
Document Classification
This document is classified as Schlumberger Private. It is available to anyone in Schlumberger
and authorized third parties. A security incident involving unauthorized disclosures will have a
severity level of Serious or Major, depending on the financial or time-to-recover impact, but never
less than Serious.
Document Control
This document is uncontrolled when printed. A controlled version of this document is stored in the
IPM Document Management System (InTouch).
Contents
Schlumberger Private
1 Statement of Standard
On all IPM D&C Operations, barriers will be incorporated in the plan during the design phase and
this design implemented during the execution phase to prevent unplanned well flow.
2 Objective
To define the acceptable quality, quantity and application of barriers to be installed in a well during
its construction, operation, workover and abandonment in order to prevent the unplanned escape
of wellbore and formation fluids to the atmosphere or seabed.
3 Applicability
This standard applies to all wells where IPM D&C manages any combination of design,
construction, testing, operation, intervention, or abandonment.
Schlumberger Private
4 Definitions
Term Definition
ALARP - As Low As A risk is reduced to levels such that further risk reduction measures
Reasonably would be so disproportionate to the probability and consequences of
Practicable occurrence that it would be objectively unreasonable to implement them.
Term Definition
Secondary Well Barrier Second set of barrier elements that prevents flow from a source. Barrier
elements that make up the Secondary barrier are those, which are or
might be exposed to contact with well pressure should any of the
elements described as a primary barrier element fail. This is defined as
the ultimate defense should any of the primary barrier elements fail and,
as such, prevents outflow to surface and environment.
For example while drilling the secondary barrier is formed by the open
hole section, the cemented casing, wellhead, BOPs and drill string with a
closed safety valve or check valve (inside BOP) installed.
Surface Casing The surface casing is the first casing where the BOPs will be installed for
pressure containment.
Surface casings shall be set within competent formations thereby
allowing the installation of BOPs prior to drilling into potentially
hydrocarbon-bearing and/or pressured formations.
Tested Barrier Qualified barrier tested to withstand maximum anticipated pressure in the
direction of flow.
Schlumberger Private
Excluding BOPs, barriers will not be considered effective after they have
been disturbed.
Fluids acting as a barrier may be qualified as a tested barrier when
proven fit-for-purpose on the basis of specification, stability, condition,
position, and monitoring/observation.
Well Barrier Element An object or element (fluid) that alone or in combination with other
elements will create an envelope capable of containing well pressure and
preventing uncontrolled flow of fluids and gases from the formation, into
another formation, or to the surface or environment, if properly deployed.
For example: drilling fluid, properly cemented casing, wellhead and
associated components, BOP and its’ associated parts, drill string with
kelly valve or check valve, cement plugs, casing bridge plugs,
mechanical or hydraulic retrievable bridge plugs, packers, tubing.
Well Intervention Entry into a well to repair or maintain the existing well components.
5 Minimum Requirements
On all IPM D&C well operations after setting the surface casing string, wells shall have two or more
dissimilar and tested barriers at all times to ensure that the risk of an unplanned flow of wellbore
and formation fluids into another formation, to the atmosphere or seabed is as low as reasonably
practicable. The requirement for two barriers does not apply to Underbalance or near balance well
operations with a rotating head.
Note on drilling blind: Refer to section 5.1 of the IPM-D&C-WC-ST-008 Kick Prevention Standard.
Schlumberger Private
It is independent of other barriers in contact with the same fluid; in other words, there is no
common mode of failure
• It can operate competently in the planned environment throughout its potential service life.
Testing of Barriers
Positive pressure tests shall be conducted for periods of:
Negative pressure tests or inflow tests shall be conducted for 30 minutes where the volume being
monitored is large in comparison to any possible leakage rate.
Inflow test of a liner lap: in anticipation of situations such as, but not limited to a mud weight
reduction subsequently to setting a liner or well testing with underbalance fluid in the annulus, a
liner lap will be imperatively inflow tested simulating the future pressure reduction to which it will be
exposed.
When planning for an inflow test, always be prepared for the barrier to fail the inflow test and a
subsequent well control event to occur: include contingency plan on how to handle potential influx
and return well to overbalanced condition in the case of a failed inflow test.
Test pressures shall be specified in the Operations Program.
Schlumberger Private
6 Responsibilities
The IPM Well Engineer shall design wells, which can be constructed, operated, maintained, and
abandoned fully in accordance with this standard.
The IPM Well Engineer is responsible for determining if more than two barriers are required.. This
should include expected: pressure, temperature, fluid chemistry, accessibility, and duration of
service. The integrity and reliability of a barrier and its intended duty will determine if more than two
barriers are to be employed.
The IPM Wellsite Supervisor shall undertake the construction, operation, intervention, and
abandonment of wells fully in accordance with this standard.
The IPM Wellsite Supervisor shall not allow the removal of a BOP, marine riser, christmas tree,
casing head, or tubing head from a well unless the formation fluids are contained behind two
independent tested barriers.
On failure of a barrier the Wellsite Supervisor shall initiate immediate measures to secure the
integrity of the well and restore or replace the failed barrier. Other activities should cease unless
doing so increases the risk of an incident.
Schlumberger Private
Internal /
Guidance How will this help users of this document? Link to Guidance
External
[1] “Casing, Liner and Tubing Pressure Internal Standard for casing and liners pressure test after InTouch ID 3286092
Testing Standard” IPM-D&C-CSG-ST-001 installation.
Revision 2.0.0 Release Date March 2014.
[2] “IPM-D&C-WC-ST-002 Well Control Internal Standard for Well Control Equipment InTouch ID 5379419
Equipment Requirements”. Revision 2.0.0
Release Date March 2014.
Schlumberger Private
[3] “Drilling Blind Recommended Practices” Internal Recommended practices if due to losses is required InTouch ID 4864890
IPM-D&C-LC-RP-001 Version 2.0.0 to drill blind.
Release Date March 2014
[4] “Kick Prevention Standard” IPM-D&C- Internal Standard for the kick prevention. InTouch ID 3286106
WC-ST-008 Revision 2.0.0 Release Date
March 2014
[5] Pressure Operations Manual for Wireline Internal Section 4: Well Integrity and WHE Equipment InTouch ID 3046294
Version 7.3. Revision 2012 Requirement and Selection.
[6] “Temporary and Permanent Internal Barrier standard specifying the barrier requirements InTouch ID 3286114
Abandonment Standard” IPM-D&C-WBA- for well suspension and well abandonment.
ST-001 Revision 2.0.0 Release Date
March 2014.
[7] “Schlumberger Well Control Manual” Internal Sections 1.21 and 3. InTouch ID 4731677
Revision 0 Release October 2006
[8] IPM Standing Orders – Well Site Internal Introduction: part 1 InTouch ID 4924177
Supervisors, Release Date 2009. Operations: part 1
[9] API RP 59 “Recommended Practice fro External Section 11.11 Rig practices for handling pressure http://www.api.org/
Well Control Operations” -. Second Section 12.6: Gas influx in cemented annulus
Edition Release Date May 2006
Internal /
Guidance How will this help users of this document? Link to Guidance
External
[10] API RP 90 “Annular Casing Pressure External Section 2.5: Diagnostic testing http://www.api.org/
Management for Offshore Wells”, First Section 3: Annular Casing Pressure Management
Edition, Release Date August 2006 Program
[11] API STD 65-Part 2 “Isolating Potential External Section 4: Barriers http://www.api.org/
Flow Zones during Well Construction”. Section 7.3: Cement Evaluation
Second Edition, December 2010.
Table A.1: Most frequent Primary and Secondary
Barriers that Failed in all Phases
[12] API RP 96 “Deep Well Design and External Section 5.2: Deepwater Well Architecture http://www.api.org/
Construction”, First Edition, Release Date Section 5.3: Barrier Philosophy
March 2013.
Annex A (informative) Examples of Barriers
Schlumberger Private
Employed During Operations
Annex B (informative) Example Barrier Definitions
[13] NORSOK D-010 Standard Revision 4 External NORSOK Standard for well integrity in drilling and http://www.standard.no/en/Sea
Release Date 4 June 2013 well operations. rch-and-
buy/Search/?search=d-010
[14] Information Security Classification Internal The Information Security Classification Standard http://www.hub.slb.com/display
Standard. Release Date Nov 2011 describes how the classification labelling is applied /index.do?id=id2518514&file=c
to information regardless if the media on which is lassify.html
stored.