M3 - PROC - NO-LOAD Compiled 14/12/2021 by Paglialunga

Description Ok Note
1 - REVIEW ALL POSSIBLE SOURCES
FOR SUPPLY OF PROCESS GAS TO
COMPRESSOR SKID AND ENSURE THAT
ARE ALL ISOLATED FROM THE
COMPRESSOR DURING THE PERIOD OF
INITIAL START-UP AND RUN IN
2 - CHECK LUBE OIL SYSTEM - LUBE OIL
LEVEL AND RUN MANUAL OIL PUMP IF
ANY
3 - RUNNING(IF PRESENT) THE
ELECTRICAL OIL PIUMP
LUBRIFICATION, IN ORDER TO
LUBRICATE THE INTERNAL
COMPONENTS(CROSSHEAD
LINER)CHECK THE CORRECT WORK OF
THE RELIEF VALVE POSITIONED ON
THE DELIVERY OIL CIRCUIT PUMP, SET
TO 7-8 bar.RUNNING THE ELECTRICAL
PUMP FOR 15-20min AT PRESSURE TO
5-6 bar
4 - DISASSEMBLE THE FRONT
DISTANCE PIECE WINDOWS.
5 - LUBRICATE THE OIL SCRAPER
GROUP IN THE LOWER PART OF THE
DISTANCE PIECE.
6 - CHECK THAT THE WATER PUMP IS
RUNNING AND THAT THE WATER IS
CIRCULATING CORRECTLY
7 - CHECK THAT SUCTION GAS VALVE
IS CLOSED
8 - CHECK THAT COMPRESSOR VALVE
DELIVERY VALVE TO THE CLIENT IS
CLOSED
9 - CHECK RECYCLE VALVE IS FULLY
OPEN AND IN MANUAL OR THAT THE
UNLOADERS ARE IN UNLOAD POSITION
10 - CHECK THAT THE VENT VALVE IS
CLOSED AND IN AUTOMATIC
11 - BY-PASS LOW SUCTION PRESSURE
SWITCH IF NECESSARY
12 - CHECK PERSONNEL ARE NOT
WORKING ON OR AROUND THE
COMPRESSOR
13 - OPEN THE NITROGEN TEST
SUPPLY AND PRESSURIZE THE
COMPRESSOR.
14 - CHECK FOR LEAKAGE ON THE
PIPING AND COMPRESSOR FLANGES.
TIGHT IF NECESSARY.
15 - START THE COMPRESSOR AND
CHECK THAT OIL PRESSURE REACH
THE CORRECT VALUE. IF NOT ADJUST
1/2
SIAD Macchine Impianti S.p.A.
Società unipersonale soggetta all’attività di
direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - siadmi@siad.eu
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107

IT.
16 - VERIFY THE CORRETLY WORK OF
THE RELEIF VALVE (PCV)IN THE OIL
CIRCUIT,POSITIONED ON THE
GRANKCASE(DOOR)SET THE RELIEF
VALVE TO 7-8 bar
17 - ENSURE THE ABSENCE OF
UNUSUAL NOISES AT COMPRESOR -
GEARBOX
18 - CHECK OIL LEAKAGE AT THE OIL
LUBE CIRCUIT
19 - RUN THE COMPRESSOR FOR 10
MINUTES
20 - CHECK TEMPERATURES,
PRESSURES AND FILL THE A9 SHEET
WITH ALL AVAILABLE INFORMATIONS
21 - TURN OFF COMPRESSOR