COMMISSIONING

Description Ok Note

1 - REMOVE CRANKCASE DOOR AND


INSPECTION COVERS AND INSURE
INTERNALS ARE CLEAN, THERE ARE NOT
SHIPPING BLOCKS, AND PAINT IS IN GOOD
CONDITION. HAND CLEAN INTERNALS WITH
SOLVENT IF NECESSARY TO REMOVE ALL OK
TRACES OF DIRT OR SAND.ON THE OXYGEN
COMPRESSOR DISTANCEPIECES ARE
PREPARED FOR THE SAFETY DISCHARGE OF
ANY LEAKAGE FROM THE ROD PACKING,
THE O2 DISTANCE PIECES DOORS HAVE
THE FOLLOWING CHARACTERISTICS
PLEXIGLASS DISTANCE PIECE DOORS WITH
HOLE (REMOVE PLASTIC PLUG)
PLEXIGLASS DISTANCE PIECE DOORS WITH
HINGE (REMOVE THE SCREWS INSTALLED
ON THE MOVING SIDE) LATTICE
DOORS(REMOVE THE PROTECTION COVER)

2 - IN ORDER TO VERIFY THE CORRECT


INSTALLATION OF TRANSMISSION GROUP ,
TO CARRY OUT THE FOLLOWING OPERATION
REMOVE THE BELT GUARD OR THE COUPLING
GUARD BELT REMOVAL, BAR OVER
COMPRESSOR FLYWHEEL MANUALLY AND
VERIFY THAT THEY TURN FREELY,
SMOOTHLY AND NOISE FREE CHECK THE
EXTERNAL BEARING GREASING ALIGNMENT
OK
VERIFICATION AND CHECK DEFLECTION
CRANKSHAFT
(VERTICAL) , CHECK LUBRICATING MOTOR
BEARINGS , MOTOR RUNNING AND CHECK
FUNCTIONALITY (TEST) CHECK MOTOR
ROTATION SENSE , ALIGNMENT AND BELT
TENSION AS GT
1.008 RE-INSTALL BELTS COVER
3 - FILL OIL IN THE CRANCKASE WITH THE
APPROPRIATE OIL TYPE QUANTITY
NEEDED(see manual). POSSIBLE OIL
ADDITION IF THE CIRCUIT INCLUDES
EXTERNAL PIPING FILLING CONTROL OK
THROUGH THE VISUAL CHECK
(granckase)
4 - REMOVAL OF CRANKCASE COVER
(CPR H) FOR INTERNAL INSPECTION, OK
SHOULD BE CARRIED OUT WITHOUT THE
PRESENCE OF EXTERNAL FACTORS
POLLUTANTS
5 - FILL CRANKCASE GEARBOX WITH
CORRECT GRADE OF CLEAN OIL. CONFIRM OK
THE OIL HEATER (IF ANY) IS SUBMERGED.

1/3
SIAD Macchine Impianti S.p.A.
Società unipersonale soggetta all’attività di
direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - siadmi@siad.eu
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107
6 - FILL OIL IN THE LUBRICATE N/A

2/3
SIAD Macchine Impianti S.p.A.
Società unipersonale soggetta all’attività di
direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - siadmi@siad.eu
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107

CYLINDER RECIVER WITH THE OK


APPROPRIATE OIL TYPE (see manual).
7 - CARRY OUT THE PROCEDURE FOR THE
OIL PUMP CYLINDER LUBRICATION AS OK
GT.1.022
8 - SPOT CHECK THAT COMPRESSOR
BOLTS AND NUTS ARE TIGHT OK
9 - CHECK THAT ALL PRESSURE RELIEF AND
SAFETY VALVES ARE PROPERLY INSTALLED
AND THAT THEY HAVE THE PROPER SET
POINT AS SHOWN ON THE P&ID OR OK
INSTRUMENT LIST.
10 - SPOT CHECK THAT PROCESS
FLANGES ARE TIGHT OK
11 - CHECK THAT ALL MANUAL VALVES
OPERATE FREELY OK
12 - CHECK THAT DRAINS AND VENT
ARE IN PLACE AND CLOSED OK
13 - CHECK ALL INSTRUMENTS, GAUGES,
TRANSMITTERS, PRESSURE AND
TEMPERATURE SWITCHES ARE IN PLACE
AND CORRECTLY LABELLED COMPARING OK
WITH THE INSTRUMENT LIST

14 - VERIFY THAT ALL THE INSTRUMENTS


ARE SETTED AT THE CORRECT VALUE AS
PER INSTRUMENT LIST

15 - FUNCTIONALLY CHECK THE


VIBRATION SWITCH
16 - CARRY OUT THE NECESSARY
FUNCTION CHECKS TO ENSURE THAT THE
DCS, ALARM SHUT DOWN CIRCUITS, LIGHT,
PERMISSIVE STARTS, AND INDICATOR
MEETERS ARE OPERATING IN A CORRECT
MANNER
17 - CARRY OUT FUNCTIONAL CHECKS TO
CONFIRM THAT THE PERMISSIVE STARTING
CIRCUIT IS FUNCTIONING CORRECTLY AND
THAT VISUAL AUDIBLE ALARM IS INITIATED.

18 - STROKE THE RECICLE VALVE. VERIFY


CLOSED AND OPEN POSITIONS. RECORD
ACTION ON FAILURE
19 - STROKE INLET VALVE AND VERIFY
CLOSED AND OPEN POSITION, RECORD
ACTION FAILURE
20 - STROKE VENT VALVE AND VERIFY
CLOSED AND OPEN POSITION, RECORD
ACTION FAILURE
21 - STROKE DELIVERY VALVE AND VERIFIY
CLOSE AND OPEN POSITION, RECORD
ACTION FAILURE
22 - VERIFY THAT THE FOLLOWING TRIP
FUNCTIONS ACTUALLY TRIP THE
COMPRESSOR BREAKERS - STOP AND
EMERGENCY BUTTON - HIGH VIBRATION - OK
LOW LUBE OIL PRESSURE -

3/3
SIAD Macchine Impianti S.p.A.
Società unipersonale soggetta all’attività di
direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - siadmi@siad.eu
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107

HIGH DELIVERY PRESSURE - HIGH DELIVERY


TEMPERATURE - LOW WATER FLOW OK
23 - OPEN WATER INTERCEPTION VALVES
AND ENSURE THAT WATER IS CIRCULATING OK
REGULARLY
24 - VENT COOLING WATER CIRCUIT FROM
BLEEDS ON TOP OF THE CYLINDERS OK
25 - CHECK INTERCOOLER AND AFTER
COOLER GAS SIDE DRAINS FOR WATER OK
GLYCOL LEAKAGE
26 - CHECK PERSONNEL ARE NOT WORKING
ON OR AROUND THE COMPRESSOR OK
27 - START AND STOP THE COMPRESSOR
AND CHECK SENSE OF ROTATION. IF OK
REVERSE, REVERSE TWO POWER LINES.

28 - START AND STOP ANY OTHER


EQUIPMENT ON THE SKID AND CHECK
CORRECT SENSE OF ROTATION AS DONE
FOR THE MAIN MOTOR. OK

4/3