Professional Documents
Culture Documents
Faculty of Engineering
Introduction to Engineering Design 2
(IE202)
Spring 2021/2022
Final Report
Section 13
Team 3
M Name ID
1 Mohammed Ahmed 2037235
2 Mustafa Hassanin 2036160
3 Hassan Mazen 2035489
4 Abdullrahman Alelyani 1937120
Table of content:
Introduction ....................................................................................................................................5
Literature Review ..........................................................................................................................6
Client Project Problem Statement ..................................................................................................7
Revised Project Problem Statement ...............................................................................................7
Design Objectives ..........................................................................................................................8
Objective Tree ...............................................................................................................................9
Pairwise Comparison Chart ...........................................................................................................9
Realistic Constraints ......................................................................................................................10
Metrics to Measure the Achievement of Objectives .....................................................................10
Initial Design Attributes ................................................................................................................12
Project Charter ...............................................................................................................................13
Work breakdown Structure (WBS) ...............................................................................................15
Linear Responsibility Chart (LRC) .................................................................................…….….17
Gantt Chart ................................................................................................................................... 18
Percent Complete Matrix............................................................................................................... 20
Function to be Realized (Glass Box) ............................................................................................ 23
Function-Means Tree .................................................................................................................... 24
Morph chart................................................................................................................................. 25
Pugh’s Method............................................................................................................................. 26
Mathematical Modeling. ..............................................................................................................27
Design Drawings............................................................................................................................30
Stimulation results........................................................................................................................31
Budget (Cost analysis) ................................ .................................................................................34
Conclusion ....................................................................................................................................35
References ...................................................................................................................................36
Appendices .................................................................................................................................37
2
Team #3
IE202
Fall 2021
List of Figures:
Figure 1: The ten-leading cause of death...............................................................................6
Figure 2: Lack of Parental Supervision...................................................................................7
Figure 3: pool fence alarm…..................................................................................................7
Figure 4: Objective’s tree………………......................................................................................9
Figure 5: Gantt chart ............................................................................................................19
Figure 6: Glass box. .............................................................................................................23
Figure 7: Function-Means Tree. ...........................................................................................24
Figure 8: Wight of the person in the pool………………………………………………….32
Figure 9: Electrical Power modeling………………………………………………………32
Figure 10: Assembly plan of the circuit……………………………………………………33
3
Team #3
IE202
Fall 2021
List of Tables:
Table (1): Pairwise Comparison Chart............................................................................................9
Table (2): Initial Design Attributes...............................................................................................12
Table (3) Key milestones.............................................................................................................. 14
Table (4): Linear Responsibility Chart..........................................................................................17
Table (5): Percent Complete Matrix..............................................................................................20
Table (6): The Morph Chart……………………………………………………………………..25
Table (7): Pugh’s Method………………………………………………………………………………………………………..27
Table (8): The Mathematical Model…………………………………………………………….29
Table (9): All the component of the artifact………………………………………………….…30
Table (10): The Cost Analysis…………………………………………………………………..34
Table (11): peer assessment member 1.........................................................................................37
Table (12): peer assessment member 2.........................................................................................37
Table (13): peer assessment member 3.........................................................................................38
Table (14): peer assessment member 4.........................................................................................38
4
Team #3
IE202
Fall 2021
Introduction:
Swimming pools is a major source of entertainment and enjoyment. Swimming pools serve as a
gathering place for friends and family in the backyard, but when left unattended, they can become
a deadly attraction for an unsupervised child or even your pet. Pools and swimming areas can be
divided into two categories, residential pools used by one dwelling only, and public pools
associated with multiple dwellings provided by the local municipality.
There is not much difference when we look at the safety and risk perspective. Both public pools
and private swimming areas require lifeguard supervision while people are in the pools. Swimming
pool goers often have lifeguards on duty and are often left unsupervised when not in use, resulting
in children or even pets drowning in pools without people knowing about them. In all swimming
pools, parents are the main source of supervision and rescue in the event of a drowning accident,
and sometimes they are the only source of supervision for children in swimming pools, especially
in private home swimming pools with the increase in the number of swimming pools in residential
homes, the risks and drowning accidents also increase. Many pool owners are unaware that a lack
of proper pool safety puts their children and the lives of many others at risk.
In spite of the efforts of government and private companies to produce and market a simple and
effective range of safety techniques, but still children drown in pools and unsupervised swimming
areas is resulting in the loss of loved ones and turning joy into sadness.
Although pool safety technology has advanced over the years from fences and pool covers, this
has led to a decrease in deaths from unintentional drowning.
Alarms are still one of the best ways to keep unattended children out of harm's way by alerting
those around them to a drowning problem, especially pool alarms to warn the homeowner when
anything enters the pool. The alarm system can determine if a child or pet is entering the pool. The
alarm is activated after something enters the pond water. The owner of the house will be a device.
Warning when the child is playing near the pool or the private swimming area. Alarms help reduce
the time for rescuers to arrive from remote areas and also help reduce children drowning by alerting
people and parents in particular that children have drowned.
5
Team #3
IE202
Fall 2021
Literature review:
Enjoying swimming in swimming pools can turn into a nightmare for families, as drowning is the
fiift cause of death from unintentional injuries worldwide as showing in figure (1), as it stands
behind 7% of all accident-related deaths (1). Drowning causes many complications which range
from death or permanent disability to various degrees, and in some cases, the victim may
survive without any complications, according to what was mentioned in the newspaper.
Young people are the most vulnerable to drowning. The highest rates of drowning in the world
are among children aged between 1- 4 years, followed by children aged 5-9 years. For children
between 5-14 years of age, drowning is the most common cause of death than other causes
that claim their lives (1). The reason for the increase in child drowning cases is the lack of
supervision over children by parents, not supervising the infants, and leaving them alone with
other children in pools.
6
Team #3
IE202
Fall 2021
One of the best solutions to use is the pool alarm, young children
and their friends sometimes need a little more supervision to get
out of harm's way. That is why it is a smart move to enhance
protection with a pool alarm. These devices can warn you
immediately when unexpected movement occurs in and around
the pool or spa to avoid drowning accidents (3). These pool alarms
are designed to work around the perimeter of a pool's surrounding
wall or fence. It uses infrared beams to detect motion or magnetic
connections that set off an alarm when they are broken, and the
alarm systems are normally put on the fence to determine if there
Figure (3): Pool fence alarm.
is someone surrounding your pool (4).
7
Team #3
IE202
Fall 2021
the pool. the device gives us an easy way to informs us that a child or pets are drowning in the
pool using alarm.
Objectives:
1- Environmentally friendly
1.1) Recyclable
2- Safe
2.1) Nonhazardous
2.3) No sharp edges.
3- Comfortable
3.1) Small in size.
3.2) light weight.
4- Inexpensive cost.
5- Durability
5.1) Waterproof
5.2) Sustainable
6- Easy to use
6.1) Easy to repair
6.2) Easy to assemble
6.3) portability
8
Team #3
IE202
Fall 2021
Objectives tree:
Environmentally #### 0 1 0 1 1 3
Friendly
Safe 1 ### 1 1 1 1 5
Comfortable 0 0 ### 0 1 0 1
Durability 0 0 0 0 ### 0 0
After doing the Pairwise Comparison Chart in table, it was found out safe is the most important
objective while Durability is the least important.
9
Team #3
IE202
Fall 2021
Realistic Constraints:
Every artifact has his own constraints and constraints force us to think smarter and be more
innovative. Project constraints are the general limitations terms of a project. We did identify
the restrictions of our artifact in terms of economic, health and safety, manufacturability.
•Economic:
-Must not exceed 500 SR for the manufacturing.
•Health and safety:
-Should not have toxic chemical material.
•Manufacturability:
- Must contains an isolated circuit
-It must not be affected by the wind.
-Should weight not more than 5 Kg
-Must be Iron rust resistance.
Objective metrics:
• Metrics to measure the achievement of objectives:
It is critical to ensure that the design meets the project's objectives because if the
objectives are not met, the project will be poorly done, making it a failure and ineffective.
To avoid these issues, setting metrics to measure the project's objectives will aid its success
and influence. To perform metrics, we must first create a scale. For example, in our project,
we created a scale ranging from 0 (worst) to 100 (best), as shown below.
1-Environmentally friendly:
100 points Completely reusable.
75 points Material is recyclable.
50 points Material is easily disposable.
25 points Material is disposable with difficulty.
0 points Material is a hazardous waste.
10
Team #3
IE202
Fall 2021
2-Inexpensive cost:
100 points Lower than 200 SR
75 points 201-300 SR
50 points 301-400 SR
25 points 401-500 SR
0 points More than 500 SR
3-Comfortable:
100 points Lower than 5 Kg
75 points 6-10 Kg
50 points 11-15 Kg
25 points 16-20 Kg
0 points More than 20 Kg
4-Easy to Use:
100 points Everyone can use it
75 points Easy to learn its functions
50 points Needs sometimes to get used to
25 points Very young and elders face problems using it
0 points Set up needed by an expert
5-Durability (Sustainable)
100 points Work for a month
75 points Work for 3 weeks
50 points Work for 2 weeks
25 points Work for a week
0 points Work for 3 Days
11
Team #3
IE202
Fall 2021
12
Team #3
IE202
Fall 2021
Project Charter:
• Goals:
The objectives are for which the project was approved and for which
the project seeks to achieve. The objectives are the beating heart of the project,
and their failure to formulate them well may lead to the failure of the project.
So, these are the goals of our project.
13
Team #3
IE202
Fall 2021
• Deliverables:
The project is not complete without the presence of the deliverables, and the
deliverables are the results of the project that the team members seek to
achieve. So, these are the deliverables of our project.
1. A practical project with a positive impact on society.
2. A progress report contains the latest progress in the project.
3. A structured presentation of the team's work and the progress of that
work.
4. An organized and comprehensive final report.
• Key milestones:
Throughout this course, key milestones will show you the project's timeframe
and keep you updated on your progress.
14
Team #3
IE202
Fall 2021
• Resources:
The resources that we will use to enhance success in our project are:
o The Engineering design textbook.
o The internet.
o The consulting of our instructor.
We should break down the primary tasks into subtasks to make them easier.
Indeed, the more you split the task, the easier it becomes to do. This strategy,
however, is known as Work Breakdown Structure, and we used it to assist us to
organize our work and achieve better results by completing it. Our work is organized
as follows: detailing customer requirements and translate them into initial design,
implementing and evaluation of the design, and finally the documentation of the
15
Team #3
IE202
Fall 2021
16
Team #3
IE202
Fall 2021
Task M1 M2 M3 M4
1. Choose a project problem
Brainstorming meeting R R R R
Voting among team members to R R R R
choose the best three problems
Present the problems to the R R R R
instructor
Take approval from instructor S S S S
2. Manage design process
Construct a Work Breakdown R S
Structure (WBS)
Make a Linear Responsibility R S
Chart (LRC)
Make a Gantt chart. R S
Make a percent complete matrix R S
(PCM)
3. Identify the users’ requirements
Writing introduction. R S
Research for similar projects R S
Discuss the information gathered R R R R
among team members
Writing the literature review. S R
Writing conclusion. S R
Writing references. S R
Writing the client problem R S
statement
17
Team #3
IE202
Fall 2021
Gantt Chart:
18
Team #3
IE202
Fall 2021
19
Team #3
IE202
Fall 2021
20
Team #3
IE202
Fall 2021
Projects.
Discuss the Information 1 0.98 % 100 % 0.98 %
gathered among team
members.
Writing the literature review. 1 0.98 % 100 % 0.98 %
Writing conclusion. 1 0.98 % 100 % 0.98 %
21
Team #3
IE202
Fall 2021
22
Team #3
IE202
Fall 2021
Glass Box:
In terms of usability, the glass box is comparable to the black box, but
it focuses more on what happens between the inputs and outputs, which is the
artifact's system. It's also advantageous for an expert to know how the artifact
is supposed to work.
Sound
Alarm
Power speaker
Battery sound
Produces
c
electricity.
sensor Switch
Water
wave Water
vibration LED Alarm
light light
23
Team #3
IE202
Fall 2021
• Function-Means Tree:
Means Makes a sound that Reads the wave Makes light that alerts Working for a
alerts people vibrations people long time
24
Team #3
IE202
Fall 2021
Morph chart:
A conversion chart is a tool for creating design alternatives and developing a design space. In
the first column, the major functions or features are mentioned, followed by different ways to
achieve each function in the row for that function. By selecting one medium from each row, one
concept design is grouped. As a result, each vertical path has an own design approach. Also, while
there may be a large number of options, not all of them are feasible. The morph chart for our
project is shown in table (6).
Function or Means
features 1 2 3 4 5
Control
1. Makes a Attached
room Wireless
sound that speaker - -
speaker speaker
alerts people. system
system
2. Reads the Water
Water wave Wind
wave movement - -
Sensor. sensor
vibrations sensor
3. Makes LED
LED surface Indoor light
light that subsurface - -
light. system
alerts People. Light.
4. Working Solar
Big capacity Chargeable
for power - -
Battery battery
long time. battery.
Feature:
Wood Plastic Aluminum Metal -
Materials
25
Team #3
IE202
Fall 2021
Discussion:
The construction of the Morphological chart using artifact’s functions, features, and means,
helped us to determine the number of the design alternatives that is possible to build it to
achieve the objectives of this artifact. Therefore, the number of alternatives is equal to 324
designs. Furthermore, 3 design alternatives is specified and selected to continue with.
Alternative 1:
Attached speaker system _ Water wave Sensor _ LED surface light_ Chargeable battery_ Plastic.
Alternative 2:
Wireless speaker_ Water wave Sensor_ Indoor light system_Big capacity Battery_Aluminum.
Alternative 3:
Control room speaker system_ Water wave Sensor_ Indoor light system_ Solar power battery_
metal.
Pugh's method:
Pugh's method is intended to locate an available design on the market and compare it to many
original choices generated by the designers. The chosen design must be similar to the
generated designs or achieve similar goals. The Datum is the name of the chosen design, which
in our case is a Pool Fence alarm [3]. Furthermore, we compared our initial designs generated in
the morph chart with the Datum in the following table (7) and chose the option with the
greatest score, which is alternative 1.
26
Team #3
IE202
Fall 2021
Environmentally
1 8
friendly S S -
2 Recyclable 6 S S -
Safe
3 10
+ + +
4 Nonhazardous 8 + + -
5 No sharp edges 10 + - +
Comfortable
6
6 - + S
+
Datum (Pool Fence alarm)
7 Small in size 9 -
+
8 light weight. 10 + + +
9 Waterproof 8 + S +
10 Sustainable 8 + S S
Durability +
11 9 - S
Easy to use _
12 10 S -
Easy to repair _
13 5 + S
Easy to assemble
14 8
+ + _
portability
15 10 + S S
16 Inexpensive cost 8 S - _
TOTAL POSITIVES (+) 86 42 56
27
Team #3
IE202
Fall 2021
Mathematical Modeling:
Mathematical models are essential for device or system design and precise prediction. The goal
of mathematical modeling is to capture all of the system's significant attributes in order to
derive the mathematical (or analytical) equations that regulate the system's behavior.
Nonlinear, dependent on how system components behave. Linear models may provide quick
and simple solutions; however, non-linear models may reveal properties of the system that
linear models cannot predict, and once a mathematical model is available, equilibrium
equations must be derived to describe the physical phenomena of the system and are intended
for quantification.
Table (8) shows a set of parameters, that could be used to build a mathematical model for a
“Sitting-Posture Corrector project”. Also, it presents the relevant parameters for the next three
functions:
For each of the above function has related variables are shown below with their units:
28
Team #3
IE202
Fall 2021
29
Team #3
IE202
Fall 2021
Design Drawing:
Design drawings are used to develop and communicate ideas about a developing
design. We did the Design drawings to clarify any misunderstanding or mistakes and visual
representation help us to describe the shape and the size of all the components clearly.
2 Rain Senior
RainSen.SLDPRT
3 resistor 1k ohm
RESISTOR 1K
1X8W.SLDPRT
5 transistor 2n2222
2N22221A.SLDPRT
6 Buzzer Device
Buzzer- Mallory
PB-09N23P-03Q.STEP
30
Team #3
IE202
Fall 2021
8
Capacitor10000pf(103) 2200uF_16V.STEP
9 Battery 9v
Battery 9V.SLDPRT
11 Case
2. Electrical power
P=V*I
P= Electrical power (Watt)
V= Voltage (Volt)
I= Current (Ampere)
31
Team #3
IE202
Fall 2021
Simulation results
After that we consider logical equations, we can logically make a simulation based on the
preceding equations. We pick equation 1 & 2 to see the effect of the wight due to mass and gravity
acceleration as well as the effect of the power with the voltage and ampere. The Microsoft Excel
output will be illustrated in the next figure.
800
600
400
200
0
50 70 90 110 130 150 170
Mass
Electrical Power
50
45
40
Power (Watt)
35
30 y = 9x
25
20
15
10
5
0
0 1 2 3 4 5 6
Current (Ampere)
32
Team #3
IE202
Fall 2021
As we can see in figure (8), the relationship between the wight and mass is liner. So, as a result
increasing the mass will affecting the water level in the pool which will make the water touch the
water sensor. Therefore, the circuit will be close, and buzzer will turn on. Note that we the gravity
acceleration 9.8 m/s2. In the figure (9), the value of the electrical power will be higher if we are
increasing the current.
33
Team #3
IE202
Fall 2021
In order to calculate the cost of producing the device, we decided to do our best to find all
the parts needed in our local markets We found the necessary parts from several suppliers, but
we found it difficult to find three parts, so we went to buy them through the Amazon
website(www.amazon.com) where the three parts were found, but the shipping fees were added
by Amazon, which increased the total cost of the device. Moreover, we only found ten pieces in
local retail stores. The following table shows all the parts used in the artifact and their detailed
cost.
Table (10): The Cost Analysis:
34
Team #3
IE202
Fall 2021
Conclusion:
To summarize, this report clarified three key aspects of the project, which are defining the
problem, setting the project plan and requirements establishment. The project is about using
engineering approach to solve a problem proposed by a client, which is the swimming pool is not
always safe for kids and beginners on swimming. In the time it takes to order a rocky-road cone,
a person can drown. No matter how much we know about drowning prevention, it remains the
top cause of unintentional injury death in children in most countries in the world. The problem
was defined and analyzed through several methods in order to come up with well-defined
statement of the problem. As a result, effective functions with the corresponding means can be
established. Many methods and tools are used in this report. First, the project planning is set by
breakdown structure, linear responsibility chart and Gantt chart. Second, the functions,
objectives and constraints are also set with objectives tree, glass box, and function-means tree.
Until this point, working on the project should be continued to select the best solution that will
resolve the problem by a real artifact. solutions could possibly succeed therefore in order to
narrow our design alternatives we used Morphological chart Table (5) to create some feasible
design alternatives. Methods like Pugh’s Table (6) helped us choose the best alternative. Also, we
preferred it over other alternatives for many main reasons. Moreover, after we picked the best
alternative, we continued to Calculate the artifact performance and identify the terms of our
model thus we accomplished that by applying mathematical modelling Table (7). Moreover, since
the deanship has decided that we will design a prototype of the artifact we simulated it and did
the drawings by program called Solid works Figure (15). The way the simulation will work is by
giving signals if a person is drawing in the pool, alerting the people around to save his life. After
that we did used (cost analysis) to calculate total cost of the artifact which would cost (298.40
SAR) including the Laboure works which was assumed to be 40 SAR. Table (10). And we tested
the artifact to improve it also to reduce the problems that could hinder its work and also to make
sure that its works well without any problem.
35
Team #3
IE202
Fall 2021
References:
2. السباحة إرشادات لحماية األطفال والمراهقين من حوادث الغرق.2022 .البيان. [online] Available at:
https://www.albayan.ae/health/health-happiness/2018-12-23-1.3441159
[Accessed 27 March 2022].
3. Spas, B., 2022. Swimming Pool Safety: How Pool Alarms Boost Protection. [online]
Articles.bluehaven.com. Available at:
https://articles.bluehaven.com/swimming-pool-safety-how-pool-alarms-boost-protection
[Accessed 27 March 2022].
Appendices:
36
Team #3
IE202
Fall 2021
37
Team #3
IE202
Fall 2021
38
Team #3
IE202
Fall 2021
Team Meetings
----------------------------------------------------------------------------------------------------
tasks
What Happened?
- The meeting started on time.
- Tell the team members what will achieve in this meeting by the team leader and recorder
39
Team #3
IE202
Fall 2021
The results
We are aal aware of the responsibilities that have been
allocated to each of us.
Member No.
1 Leader
Mohammed Ahmed
2 Recorder
Mustafa Hassanin
3 Summarizer
Hassan Mazen
4 Supporter
Abdullrahman Alelyani
40
Team #3
IE202
Fall 2021
resources
What Happened?
The results
- The team obtained sources about the project
41
Team #3
IE202
Fall 2021
Member No.
1 Leader
Mohammed Ahmed
2 Recorder
Mustafa Hassanin
3 Summarizer
Hassan Mazen
4 Supporter
Abdullrahman Alelyani
tasks
What Happened?
- The meeting started on time.
- Tell the team members what will achieve in this meeting by the team leader and recorder
The results
We are aal aware of the responsibilities that have been
allocated to each of us.
42
Team #3
IE202
Fall 2021
Member No.
1 Leader
Mohammed Ahmed
2 Recorder
Mustafa Hassanin
3 Summarizer
Hassan Mazen
4 Supporter
Abdullrahman Alelyani
43
Team #3
IE202
Fall 2021
resources
What Happened?
The results
- The team obtained sources about the project
----------------------------------------------------------------------------------------------------
44