Professional Documents
Culture Documents
EPC Contractor:
1
METHODOLOGY FOR SOIL STABILISATION OF UPPER 150mm EARTHEN
SHOULDER
1. Objective: The present procedure is aiming to define the necessary operations
and procedures, including preparations to be done, personnel and equipment to be
deployed in order to execute the cement stabilized of upper 150mm earthen
shoulder and to ensure that the materials and workmanship are complying with the
requirements as stipulated in the technical specifications. Cement treated earthen
shoulder can reduce the erosion during heavy rain, should have sufficient strength
to carry occasional traffic load, be impervious to surface water.
2. Scope: This method statement covers the requirement for the cement stabilized
works of upper 150mm earthen shoulder instead of 150mm thick compacted layer
of granular material .
This method statement is to be adopted for laying and compacting an improved
upper 150mm thick earthen shoulder treated with cement on prepared surface of
earthen shoulder during construction activities after construction of paved shoulder
of proposed road and also describes the controlling elements during the execution.
4. From Kenyan pavement design manual ,PART III, for shoulder construction: it is
mentioned that for heavy traffic, where no suitable natural material can be found, it
will be necessary to improve the shoulder material with cement or lime mix, The
treated material shall be at least of subbase quality and shall comply with the
requirements shown in chart SB2.
5. Materials
5.1 Soil: The Soil used for stabilization shall be the local clayey soil having
plasticity index - 8<PI<20.
From chart SB2 for Cement or lime improved materials for subbase in
Kenyan pavement design manual part-III, material requirement before treatment for
improvement For Sand, clayey sands and silty sands soil is: maximum size 0.5 to
10mm, passing through 0.075 mm sieve is max 50%, plasticity index is max 30 and
organic matter max 2%.
5.2 Cement: Cement for stabilization shall be ordinary Portland cement, Portland
Slag cement or Portland Puzzolana cement and shall comply with the requirement of
IS:269,455 or 1489 respectively.
2
5.3 Water: The water to be used for cement stabilization shall be clean and free
from injurious substances. Potable water shall be used.
6. Equipment’s use:
The equipment below ist he minimum numbers used for the described works.
EQUIPMENT LIST
120G、
1 Grader 1
Wide=4.23m
2 Drum Roller Min 1 22T
Pneumatic tired
3 1
rollers
4 Water tanker 1
Transporting
5 Low-bed trailer 1
Cement
Survey and testing
6
eqipment
7.Personnel
Supervising Engineer
Supervisor/Foremen
Operator
Driver
Skilled Workers
Topographic Team
External lab team
Unskilled workers
3
8. Quantity of Cement mix for stabilization
9. Methodology:
9.2 Preparation
Before the commencement of the hard shoulder, the previous layer named earthen
layer in this project should meet the specification requirement and get the reception
from engineer. The surface of the selected layer should be cleaned properly.
9.3 Execution general
Mix-in-place procedure is relative simplicity and hence it is particularly suitable for
this work. The equipment used for mix in place construction shall be rotavator or
similar approved equipment capable of pulverizing and mixing the soil with cement
and water to specified degree to the full thickness of the layer (150mm) being
processed and of achieving the desired degree of mixing and uniformity of the
stabilized material
The thickness of layer 150mm will be stabilized at one go while compaction.In this
process the material is stabilized in-situ which requires the stabilizing agent to be
spread before or during the pulverisation and mixing of the soil and stabilizer. In-situ
stabilization generally involves the following operations:
4
9.5 Spreading the Stabilizer (cement)
Spreading the stabilizing agent (cement) at the required dosage rate can be carried
out manually or by machine. Bags of cement are spotted at a set spacing at manual
methods, they are then broken open and the stabilizer raked across the surface as
uniformly as possible. Mechanical spreaders automatically monitor the required
amount of stabilizer to be spread on the surface of the soil.
9.8 Compaction
Compaction is carried out in two stages:
a) An initial rolling and trimming which may be carried out followed by a
final mixing pass of the rotovator.
b) Drum roller will be used for secondary compaction until get the correct
density (98% ASSHTO Density). Grader can be used for cut to the design
level if necessary. Pneumatic roller will be used for finishing off to reach
the final density and level for acceptance.
c) Final compaction and levelling in the case of cement stabilized material,
must be completed within two hours of mixing.
9.9 Curing
Proper curing is very important for following reason.
a) It ensures that sufficient water is retained in the layer so that the hydration
reaction between the stabilizer, water and the soil can continue
b) It reduces shrinkage
5
c) It reduces the risk of carbonation from the top layer.
Curing is done by spraying water on a 30mm to 40mm thick layer of sand spread on
top of finished layer.
Watering Compaction
6
12. Safety Precautions: