POTABLE WATER COMMISSIONING PROC
DOSAGE SYSTEM OF POTABLE WATER COMISSIO
Before Commissioning (For Solution Preparation)

Ca(OH)2 solution must be prepared in Bulk Tank with addition of HCl Acid 200 ml in 1000 liter water to adjust
add Ca(OH)2 powder as per 5% solution preparation. Day tank must be filled by opening transfer valve from B
maintained in SWRO system as 15 liters/hour, whereas in BWRO, flowrate to be adjust as per the requirement
Caustic and Antiscalant must be filled in bulk tank directly from can and Day tank must be filled by opening tra
recommendation from supplier. whereas, caustic dosage to be set as per set point of pH value to be kept at 8.
Post Chlorination system must be run independently first and preparation of liquid chlorine to be started thro
Adjust the dosing rates of post chlorination dosing pumps to maintain the free chlorine level at the potable wa
PreCommissioning & Commissioning Steps & Checks
PreCommissioning Steps & Checks
Be sure for opening common inlet suction valve and each suction valve for each dosage Pump
Discharge valve and discharge valve before dosing point must be checked its opening
If you have mixer for dosing systems, check their auto or manual mode on its panel
Dosage rate must be set in setting page before running
Before Running dosage system, day tank must be checked as level from SCADA
Especially for Ca(OH)2 dosage system, Fresh Water line goes to suction of Ca(OH)2 dosage pumps must be che
Some Dosage Pumps could be set from SCADA, some of them could be set from directly dosage Pump (Caustic
done from related Scada setting page). Settings must be done before BWRO and dosing system start

Check fresh water pump discharge manual valves for Ca(OH)2 dosage system goes through Ca(OH)2 dosage pu
could be choked in short time. Pneumatic valves works automatically if one SWRO Train stops. In that case val
to prevent chocking. There is no need for adjustment for pneumatic valve.
Commissioning Steps & Checks
After starting of BWRO, Dosing systems will be started automatically but some dosage pumps controlled from
stop from pump side) must be checked on dosage pump its running or stop mode. If it is stop mode, it must be
After running of dosage systems, there could be air at suction line. There are release valve backside of Grundfo
open that valve and release air until all air is gone
If you still face any problem for discharging of solution, you have to check suction line, suction valve, suction c
If everything is well in 3th step discharge point of dosing pump must be removed and must be checked for disc
If still solution does not come, discharge line could be chocked and this could be happened on Ca(OH)2 dosage
Fresh water already comes with line on Ca(OH)2 dosage suction line. Pneumatic valve exists on fresh water pu
through dosage point. Discharge point must be open and must be checked coming of water to discharge line e
After Cleaning your system will run. Potable System is running
BWRO SYSTEM OF POTABLE WATER COMISSIONING
Commissioning Steps & Checks
Make all BWRO Feed Pump Auto from PJB.
Open Discharge Valve as set dischage bar as … bar
Make sure that BWRO Common is Auto on Scada and Start BWRO from Scada
Do not change BWRO Bypass Valve from 5th teeth if you do not change BWRO BYPASS Mode off.
If you change BWRO BYPASS Mode off and bypass line is open, system will give inlet low flow alarm in short ti
If you change BWRO BYPASS Mode off, you have to close Bypass valve goes directly to BWRO Product Tank
Potable water is running