This document provides maintenance instructions for the air brake system of a 75 tonne high capacity breakdown crane. It lists specifications for air brake pipe pressure, reservoir pressures, brake cylinder pressures and filling/release times. It also provides allowable clearances and wear limits for brake linings and discs. Technicians are directed to additional manuals for further information.
This document provides maintenance instructions for the air brake system of a 75 tonne high capacity breakdown crane. It lists specifications for air brake pipe pressure, reservoir pressures, brake cylinder pressures and filling/release times. It also provides allowable clearances and wear limits for brake linings and discs. Technicians are directed to additional manuals for further information.
This document provides maintenance instructions for the air brake system of a 75 tonne high capacity breakdown crane. It lists specifications for air brake pipe pressure, reservoir pressures, brake cylinder pressures and filling/release times. It also provides allowable clearances and wear limits for brake linings and discs. Technicians are directed to additional manuals for further information.
Section: 13 75 TONNE HIGH CAPACITY BREAKDOWN Date: Aug 2016 CRANE Page: 544 of 574
19.4 Air Brake System
Brake System Equipment Davies & Metcalfe Air Brake Pipe Pressure 5.0 bar Main Reservoir Pipe 6.9 bar Pressure Auxiliary Reservoir Pressure 6.9 bar (two pipe) Auxiliary Reservoir Pressure 5.0 bar (single pipe) Brake Cylinder 3.5 bar (Auto) Pressure(max) 4.82 bar (Direct) Brake Cylinder Filling Times Goods 9-15 seconds - two pipe Passenger 2-3 seconds - two pipe Brake Cylinder Release Times Goods 30-40 seconds Passenger 15-20 seconds Normal Brake Lining 1 mm Clearance Maximum Brake Lining 2 mm Clearance Maximum Brake 19 mm Lining Wear Maximum Brake 5 mm Disc Wear Each Side
For information refer to Davies & Metcalfe Installation and Maintenance Manual Ref M1214. & SAB WABCO M07042158