Professional Documents
Culture Documents
Analysis
Introduction
The term “offset wells” refers to wells that are geographically the
closest to the proposed well location.
Offset well analysis is one of the most important step in well design.
It is a unique opportunity to review other wells at the start of the
planning process, prior to making critical design decisions.
When performed accurately and presented properly, it provides the
basis for all design work and risk analysis.
Session Objectives
At the end of this training session, you will be able to:
►List the main objectives of offset well analysis
►Perform detailed offset well analysis and present the data in a meaningful format
►Validate the pore and fracture pressures from offset wells data
►Estimate the Bottom Hole Static Temperature (BHST) from log data
►Validate assumptions
How can offset data analysis influence
the drilling schedule ?
209 90
52 60 68
67 91
55
72
C-4, Proposed
81 80 86 173
95 149
180
145
127 175
130
107 136 159
131
181
135
165
182
163
Recommendation:
Select the four closest
original wells and the
three closest infill wells
0 2 4 6
Selecting Offset Wells – Infill Drilling Case 2
Recommendation:
Select the four closest
original wells and all the
infill wells
0 2 4 6
Selecting Offset Wells – Deep Exploration
Recommendation:
Select all the Deep Wells
and the two closest
shallow wells to have
coverage in all areas
Legend
Shallow Wells (less than 2000 m) or
Wells with no Available Data
Deep Wells (more than 4000 m)
Proposed Deep Wells
Scale (km)
0 10 20 30
Selecting Offset Wells – Rank Wildcat
Selecting Offset Wells – Rank Wildcat
Recommendation:
Central-1 Select all wells within 400
Km !
Onshore
Wells
George
Danielle
Navarin
Nancy Basin Wells
Scale (km)
►Old wells contain valuable information (original pressures, drilling hazards, etc)
►Recent wells are better for time analysis, bit selection, existing pore pressure,
etc.
►Wells in close proximity to the new well but in different structures or separated
by faults can still yield valuable information
►Ideally, we are looking for geological similarity combined with geometrical
similarity
Offset Well Selection Exercise
You are the well engineer for an offshore platform and you
have been asked to plan a sidetrack for well C2 (see platform
diagram on the next slide). Assume that all wells are
targeting the same reservoir.
B3 (1988)
B1 (1988) B2 (1988) B4 (1988) B5 (1987)
B6 (1988)
Proposed C2-ST
C6-ST (2002)
C1 (1989)
C6 (1988)
C5 (1989)
C2 (1989)
C3 (1989) C4 (1989)
C5-ST (2003)
D1 (1989)
D5 (1989) D6 (1989)
B3 (1988)
B1 (1988) B2 (1988) B4 (1988) B5 (1987)
B6 (1988)
Proposed C2-ST
C6-ST (2001)
C1 (1989)
C6 (1988)
C5 (1989)
C2 (1989)
C3 (1989) C4 (1989)
C5-ST (2001)
D1 (1989)
D5 (1989) D6 (1989)
(Depth (feet)
8000
10000
18000
0 25 50 75 100 125
Tim e (days)
Case History - Seismic Cross Section
2000
4000
What do you think were
6000
the problems delaying
8000 performance ?
Depth (ft)
10000
12000
Wellbore deviation due
14000 to formation dip !
16000
18000
0 2 4 6 8 10
Inclination (deg)
The Importance of Data Presentation
Challenger Case History
How a simple O-ring lead to a Catastrophe
Source: Visual Explanations, Edward R. Tufte, PhD, Graphics Press, Cheshire, Connecticut, 1997 (revised 2002)
Sequence of Events
Source: Visual Explanations, Edward R. Tufte, PhD, Graphics Press, Cheshire, Connecticut, 1997 (revised 2002)
Example of Poor Data Presentation
(the answer is hidden)
Source: Visual Explanations, Edward R. Tufte, PhD, Graphics Press, Cheshire, Connecticut, 1997 (revised 2002)
Same Information Re-arranged
Source: Visual Explanations, Edward R. Tufte, PhD, Graphics Press, Cheshire, Connecticut, 1997 (revised 2002)
A Case History
C-32 Case History
C-35
C-39 P&A Wells
C-6 C-30
C-21
C-35
C-39 P&A Wells
C-6 C-30
C-21
C-35
C-39 P&A Wells
C-6 C-30
C-21
C-33 was drilled just before
C-17 C-27 C-33
C-32 with the same rig and
C-28
C-3 crew working directly for the
C-46 Operator
C-38
C-37
C-36 C-42
C-8 C-4
C-43
C-44
Why were two nearby wells ignored ?
C-11 Legend:
C-29
C-35
C-39 P&A Wells
C-6 C-30
C-21
C-33
Fault at
C-17 C-27
C-28 Reservoir
C-3
Level
C-46 C-42
C-38
C-37
C-36
C-8 C-4
C-43
C-44
How the Data was
Presented
C-21
-5 0 5 10 15 20 25 30 35 40 45 50
SUMMARY
5
B ent o nit e M ud 12 1/4" Hole Section:
( 1.12 - 1.2 2 ) g r / cc Drill to 450 m.
12 1/4'' Hole
9 5/8" , 36 lbs/ft, J-55, BTC
15m @450 m
@ 447
8 1/2" Hole Section:
796 m - suspended operations because the cuttings pit w as full
25 1213 m - koomey pump failure
Invert OB M 1450m - 448 m - logs
( 1.19 - 1.50 ) g r/ cc
35 8 1/2" Hole
7" , 23 lbs/ft, N-80,BTC @1455 m M D 6 1/8" Hole Section:
@ 1440m M D
2350 m - trip to 1440 m, Noted that the w ell w as flow ing (possibly from
45 sw abbing). Flared gas at surface.
Inver t OB M - conditioned mud from 1.74 to 1.77 gr/cc
( 1.59 - 1.9 6 ) g r / cc - increased mud density to 1.93 during w ell control
55 8rd
3 1/2" , N80, 9.3 lbs/ft,
@2,460.6 m M D 6 1/8" Hole
@2,476m M D
65
C-27
-5 0 5 10 15 20 25 30 35 40 45 50
Summary
B ent o nit e M ud
( 1.0 6 - 1.2 1) g r/ cc
5 12 1/4" Hole Section: Drill to 300 m. Ran and cemented 9 5/8".
9 5/8" Casing , 36 lbs/ft, J-55, BTC 12 1/4'' Hole At 300 m recorded high drag.
@ 299.69 m @ 300 m
15 8 1/2" Hole Section: Drill to 1450 m. At 1081m, recorded densities: In = 1.36 gr/cc,
Out = 1.29 gr/cc. Wireline logs w ere run from 1450m to 800m.
Invert OB M
25
( 1.2 0 - 1.3 9 ) g r/ cc
6 1/8" Hole Section: Drill to 1760. At 1605 m, encountered total losses. Tried to
7" Casing , 23 lbs/ft, N-80, BTC
cure w ith LCM. At the end, spotted tw o cement plugs from 1562-1606m. At 1671m
35
@ 1449 m encountered partial losses. At 1685 m took a gas influx. A 1760 m, ran 5" liner.
8 1/2" Hole
@1450 m
45 4 1/8" Hole Section: Drilled to 2046 m. Encountered losses w hile drilling at 2046
Invert OB M mts. While running tubing, it w as ejected from the w ell. Bullheaded the kick. Had
( 1.51 - 1.6 8 ) g r/ cc
difficulties to circulate. Had to perforate the tubing to be able to cement.
55 6 1/8" Hole @
5" Casing , N 80, 5 lbs/ft, HD SLX
1760 m
65
C-30
-5 0 5 10 15 20 25 30 35 40 45 50
Summary
B ent o nit e M ud
( 1.10 - 1.255) g r/ cc 12 1/4" Hole Section: Drilled to 450 m. Ran and cemented 9 5/8".
9 5/8" Casing, 36 lbs/ft, J-55, BTC 12 1/4'' Hole Section
@ 447.11 m @ 450 M 8 1/2" Hole Section: Drilled to 1505 m. Observed gas cut mud at 1219m. Density In
15
= 1.32, Out = 1.21 gr/cc. SCR at 70 SPM, 211 GPM. Increased MW to 1.33 gr/cc. At
1286 m, observed gas cut mud. In = 1.35, Out = 1.24 gr/cc. Increased MW to 1.35
Invert OB M
25 gr/cc. At 1300m, In = 1.35, Out = 1.24 gr/cc. Increased MW to = 1.36 gr/cc. At
( 1.2 5 - 1.4 1) g r/ cc
1333m, In = 1.36, Out = 1.24 gr/cc. Increased MW to = 1.37gr/cc. At 1380, In = 1.37,
Out = 1.28 gr/cc. Increased MW to = 1.38.
35
7" Casing , 23 lbs/ft, N-80, BTC
8 1/2" Hole Section
@ 1503.23 m M V @1505 m M D 6 1/8" Hole Section: Encountered losses at 1760m and 1769m. At 1769 m,
45 observed gas cut mud. MW Out = 1.46 g/cc. Increased MW to: In = 1.65g/cc w ith Out
Invert OB M
= 1.63 g/cc. Spotted cement plug. Drilled plug from 1645 to 1771 m. Observed gas
( 1.51 - 1.6 8 ) g r/ cc
cut mud at 1971m. In = 1.63, Out = 1.53 gr/cc. Increased MW to = 1.64gr/cc.
55 6.4 lbs/ft, M -VAM
2 7/8" Tubing , N80, 6 1/8" Hole Section At 2017m, degasser failed. A 2025 m, encountered losses: 6 m3. At 2255 m,
shoe @ 2384.60 m M D @ 2,402 m
observed gas cut mud, In = 1.66, Out = 1.58 gr/cc. Increased MW to = 1.67gr/cc w ith
65 LCM.
Same Information on a
Stick Chart
Stick Chart of Original Wells
C-21 C-27 C-30
(Dec 2000) (Feb 2001) (Feb 2001)
0m
9-5/8” C-21
9-5/8” 300 m 9-5/8” C-27
447 m 447 m C-30
500 m
7” 7” 7”
1000 m
1219 Raised
MW fm 1.32
to 1.37)
1440 m 1450 m
1500 m 1503 m
JM-1 1605 (Total)
JM-5 5” 1760-1769
1685
1760 m Raised MW to 1.65
JM-11 2-7/8”
2-7/8” & set cement plug
2000 m 3-1/2” 1971
JI-3 2046 m 2046
2025 (6 m3)
JI-7 2350 Tubing was 2225 Raised
ejected from well 2384 m
2461 m Raised MW fm MW to 1.67
2500 m while cementing
1.74 to 1.77)
1 1.2 1.4 1.6 1.8 2 2.2
Legend
Influx Notes: 2940 m (Partial)
Lost Circulation - C-1 was drilled entirely with water base mud
- All other wells were drilled with oil base mud from the start of
Gas Cut Mud the 8-1/2” hole section to TD
Mud Weights Presented Separately
C-21
C-27
C-30
C-01
C-29
C-33
1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2 2.1
1000 m
2000 m
3000 m
4000 m
? Top of Salt
?
5000 m Base of Salt
Legend
Influx
6000 m Lost Circulation
Stuck Pipe
Reaming
Stick Charts - Comments
Note the
presence of mud
cake on the
borehole wall
Example 6 arm Caliper in 12-1/4” Hole
Axis 1 Axis 2 Axis 3
Sand
Shale
Gamma Ray 3”
Wellbore ovality is a good example of stress induced instability.
Note that it is also obvious in the sand.
6 arm Caliper Borehole Presentation
Pendulum
Spiralling stopped by introduction of a
BHA
Near bit stabilizer
Near bit
stab.
Stick Chart Exercise
Prepare a stick chart for the well you have been assigned (through a
random draw)
As a minimum, your stick chart should show:
- well name and date drilled
- hole and casing depths
- hole and casing sizes
- mud system used including density range
- all drilling hazards including wellbore stability concerns
Those who have time can plot the mud density vs depth.
Offset Wells Time
Analysis
Offset Wells Time Analysis
Rig Repair
Note: NPT on a well is defined as the 7%
45.0
40.0 Logging
35.0
Well Completion
Time (Days)
30.0
Cementing
25.0
20.0 Other
15.0 Unplanned BHA & Bit Trips
10.0 Rig Dow ntime
5.0 Location Subsidence
0.0
Productive Time
RS32 RS33 RS34 RS35 RS 36 S779 S780
This data can be normalized for the depth of each hole section to provide
performance data to estimate the next well. The drilling data can easily be
converted to “feet per day” while the flat times will be broken down in a fixed
component (rigging up to run casing and BOP testing is takes the same time
regardless of the hole depth) and a ft/day component.
Example 3 Data - Time Versus Depth Curves
0
2000 Well A
Well B
This is the data from
4000 Well C
the previous slide
Well D presented in a
Depth (ft)
6000
graphical method.
8000
10000
12000
14000
0 5 10 15 20 25 30 35
Time (days)
Time Analysis Presentation Example
Productive Well Times
500
1000
1500
Removing NPT
highlights was is Kiwa 1
Measured Depth (m)
4000
4500
0.00 10.00 20.00 30.00 40.00 50.00 60.00
Days
T vs D Presentation - Case History
0
1000
2000
Initial Presentation in
the End of Well Report
3000
4000
5000
400
6000
0 100 200 300 400 500
T i m e ( d a y s)
T vs D Presentation - Case History
0
Revised Presentation
1000
2000
Highlights Areas on
(Depth (m)
4000
5000
6000
0 50 100 150 200 250 300 350 400 450
Time (days)
Detailed Time Analysis Example
Section
30" Hole / 24" Conductor
Well A-10 A-9 A-11 A-6 A-3 A-5 A-2 A-7 A-8
Depth (casing) 201.00 200.00 193.00 192.00 191.00 192.00 191.00 191.00 199.00
Operation (hrs)
Conductor Running
R/U to run 18-5/8" 2.00 2.00 1.50 1.00 1.50 1.00 1.50 0.50 1.00
P/U and check shoe joint 1.00 1.00 2.00 1.00 2.00 3.00
Run conductor 5.00 6.00 7.50 7.00 5.50 7.00 8.50 10.50 14.50
Total Conductor Running 8.00 9.00 11.00 9.00 9.00 8.00 13.00 11.00 15.50
Conductor Cementing
R/U to run cementing string 2.00 2.50 2.50 1.00 0.50 1.00 1.00 1.00 1.00
Run Cementing string & stab into float shoe 1.00 2.00 1.50 1.00 1.50 0.50 2.00
Cement conductor 7.50 2.00 1.50 1.00 1.50 2.50 1.50 1.00 1.50
POOH cementing string 1.00 2.00 1.00 1.00 0.50 1.00 0.50 1.00
R/D cementing equipment 6.00 6.00 8.50 2.00 1.00 0.50 4.00 0.50
Total Conductor Cementing 11.50 14.50 12.50 12.50 6.00 6.00 3.50 9.00 3.00
Install Diverter
Cut Conductor 2.00 2.00
Install 18-5/8" VG Loc 2.00
N/U Diverter 2.00 11.00 13.00 11.50 14.00 10.50 9.50 11.00 6.00
Pressure test Diverter & Conductor 2.50 0.50 0.50 1.00 1.50 0.50 2.50 2.00
Total Install diverter 8.50 11.00 13.50 12.00 15.00 14.00 10.00 13.50 8.00
Woodside Drilling Performance 1968-1992
170
30
3500
Ref: SPE 35077 – Step Change Improvement and High Rate Learning are Delivered by Targeting
Technical Limits on Sub-Sea Wells, DF Bond, PW Scott, PE Page and TM Windham
Technical Limit Definition
(20-40%) (10-15%)
Actual
Technical Limit + Waste + NPT
Time =
Ref: SPE 35077 – Step Change Improvement and High Rate Learning are Delivered by Targeting
Technical Limits on Sub-Sea Wells, DF Bond, PW Scott, PE Page and TM Windham
Technical Limit Methodology
1. List drilling data by activity and duration
2. Pull out NPT and waste (bit trips, wiper trips, rig maintenance, etc.)
3. Group reported activities by normal well construction sequence I.e. Set
Casing, wellhead/BOP, drill shoe track/LOT, etc (use of consistent
definitions essential)
4. Tabulate instantaneous ROP from mud log
5. Determine TL average ROP for section
90’/ Inst ROP (min/ft) + 10 min/stand = Pseudo ROP inc. connections
6. Tabulate each well by sequence
7. Take best times for each to determine best time composite well
8. Create TL well with best flat from above but use TL section ROP for generic
hole sections
Example Technical Limit Spreadsheet
Section
30" Hole / 24" Conductor
Well A-10 A-9 A-11 A-6 A-3 A-5 A-2 A-7 A-8 AVG MIN MAX
Depth (casing) 201.00 200.00 193.00 192.00 191.00 192.00 191.00 191.00 199.00 194.44 191.00 201.00
Operation (hrs)
Conductor Running
R/U to run 18-5/8" 2.00 2.00 1.50 1.00 1.50 1.00 1.50 0.50 1.00 1.33 0.50 2.00
P/U and check shoe joint 1.00 1.00 2.00 1.00 2.00 3.00 1.67 1.00 3.00
Run conductor 5.00 6.00 7.50 7.00 5.50 7.00 8.50 10.50 14.50 7.94 5.00 14.50
Total Conductor Running 8.00 9.00 11.00 9.00 9.00 8.00 13.00 11.00 15.50 10.94 6.50 19.50
Conductor Cementing
R/U to run cementing string 2.00 2.50 2.50 1.00 0.50 1.00 1.00 1.00 1.00 1.39 0.50 2.50
Run Cementing string & stab into float shoe 1.00 2.00 1.50 1.00 1.50 0.50 2.00 1.36 0.50 2.00
Cement conductor 7.50 2.00 1.50 1.00 1.50 2.50 1.50 1.00 1.50 2.22 1.00 7.50
POOH cementing string 1.00 2.00 1.00 1.00 0.50 1.00 0.50 1.00 1.00 0.50 2.00
R/D cementing equipment 6.00 6.00 8.50 2.00 1.00 0.50 4.00 0.50 3.56 0.50 8.50
Total Conductor Cementing 11.50 14.50 12.50 12.50 6.00 6.00 3.50 9.00 3.00 9.53 3.00 22.50
Install Diverter
Cut Conductor 2.00 2.00 2.00 2.00 2.00
Install 18-5/8" VG Loc 2.00 2.00 2.00 2.00
N/U Diverter 2.00 11.00 13.00 11.50 14.00 10.50 9.50 11.00 6.00 9.83 2.00 14.00
Pressure test Diverter & Conductor 2.50 0.50 0.50 1.00 1.50 0.50 2.50 2.00 1.38 0.50 2.50
Total Install diverter 8.50 11.00 13.50 12.00 15.00 14.00 10.00 13.50 8.00 15.21 6.50 20.50
Breaking down the well in small increments is essential to estimate the technical limit.
For example, the best time for Total Conductor Running was on well A-10 and A-5 (8.0
hrs) while the composite best time for this activity is 6.5 hours.
Technical Limit - Estimate Success to be…
Technology Fortune
15% 5%
People
80%
Ref: Technical Limit Workshop, Brunei Shell Petroleum, Nov 4 and 5, 1998
Technical Limit Reference Page
The Learning Curve
The Learning Curve
The concept of the learning curve was first developed by the airline
manufacturing industry. Although no particular incentives were in
place, it was observed that the time required to build aircrafts was
getting smaller as a time progressed (and the number of aircrafts
built increased).
t c1 * e n c 2
c3(1 )*
Where:
Ref: SPE 15362 - The Drilling Performance Curve: A Yardstick for Judging Drilling Performance, JF
Brett and KK Millheim
Learning Curve
t c1 * e n c 2(1 )*
c3
30
25
T im e ( d a y s )
20 c1
15
10 ?
5 c3
0
1 2 3 4 5 6 7 8 9 10
Wells in Chronological Order
Value of C2 Industry Average: C2 = 0.34 (“C” Performers)
Good Projects: 0.5<C2<1.0 (“B” Performers)
Excellent Projects: C2>1.0 (“A” Performers)
Ref: SPE 15362 - The Drilling Performance Curve: A Yardstick for Judging Drilling Performance
C2 = 0.34 C2 = 0.50
30 30
25 25
160 days 148 days
Time (days)
Time (days)
20 20
15 15
10 10
5 5
0 0
1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10
Wells in Chronological Order Wells in Chronological Order
C2 = 1.00 C2 = 1.50
30 30
25 25
134 days 129 days
Time (days)
Time (days)
20 20
15 15 You can drill 3 more wells !
10 10
5 5
0 0
1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10
Wells in Chronological Order Wells in Chronological Order
Calculation of C1, C2 & C 3 Using Excel Solver®
The method proposed by Brett and Millheim to calculate the various coefficients is
a non linear minimization technique. It calculates the value of the three C’s for the
best possible fit with the existing data
It can easily be
performed by building a
simple Excel spreadsheet
and using the Solver
option.
If Excel Solver® is not
located in the “Tools”
menu of your Excel
version, you can add it by
using “Add-Ins” from the
“Tools” menu
Calculation of C2 Using Excel Solver®
Ref: Benton – Vinccler Project: A Drilling Performance Approach, Julio Guzman GFE Project
Exercise to Calculate the Learning Curve
Actual Time
1. Calculate the Learning Curve
Well Order (days)
1 33.1
Coefficients for the group of well
2 20.9 shown on the left.
3 19.0
4 19.0
5 15.5 2. How well is this project
6 17.6 performing from a learning curve
7 16.4 standpoint ?
8 14.0
9 15.6
10 16.1
11 11.9
12 12.6
Learning Curve Exercise
C1 20.9
C2 0.45
C3 12.3
C1 17.5
C2 0.74 Given a C2 of 0.74, this is
C3 14.9
considered a “Good” project
Actual Time Estimated Square of (Actual-
from a learning curve
Well Order (days) Time (days) Estimated Time) Standpoint
1 33.1 32.34 0.5827
2 20.9 23.20 5.2990
3 19.0 18.84 0.0256 35.0
4 19.0 16.76 5.0302 30.0 Actual
5 15.5 15.76 0.0690 25.0
Time (days)
6 17.6 15.29 5.3468 Calculated
20.0
7 16.4 15.06 1.7932
8 14.0 14.95 0.9075
15.0
9 15.6 14.90 0.4887 10.0
10 16.1 14.88 1.4977 5.0
11 11.9 14.86 8.7878 0.0
12 12.6 14.86 5.1021 1 2 3 4 5 6 7 8 9 10 11 12
Sum 34.9302
Wells in Chronological Order
Least Square Error 1.7061217
Estimation of Bottom Hole
Static Temperature
Bottom Hole Static Temperature (BHST)
The BHST for each hole section is used to estimate the geothermal
gradient of the formation (temperature increase as a function of
depth)
This information is critical to design the thickening time of cement
slurries and to test it in accordance with the test schedules of the API
RP 10B
In high temperature application, the data is also used to check the
stability of drilling/completion fluids and to determine the
temperature requirements of downhole equipment.
The best source to get the BHST is the production records
BHST in Exploration Drilling
The idea of using a Horner plot for the estimation of BHST was first
introduced by Timko & Fertl in 1972.
This was based on the analogy with conventional pressure build-up
method.
The Horner plot method is not fully accurate but given its simplicity,
it has received wide acceptance by well engineers.
Ref: SPE 5036 Static Formation Temperature From Well Logs – Am Empirical Method. WL Dowdle & WM
Cobb. JPT November 1975
Typical Log Header
circulation (hrs)
1 t t 10
t
(Logarithmic Scale)
Horner Plot Example
Tool 1 Tool 2
Assume the well was circulated for three hours from the time TD was
reached to the start of the trip out to log
Horner Plot Example
Circulation Time t (hrs) 3
Circulation Stopped 12/21/2002 21:00
Logging Run Number Log On Bottom delta t (hours) (t+ delta t )/delta t Temp
1 12/23/2002 1:30 28.5 1.1053 126
2 12/24/2002 4:00 55 1.0545 128
Temperature (deg F)
Temperature (deg F)
y = -42.577Ln(x) + 130.26
127.5 129
Applying a logarithmic 128.5
127 trend line to the graph and 128
forecasting backward to x = 127.5
126.5 1 (using Excel).
127
126 126.5
126
125.5 125.5
1 10 1.0000 10.0000
(t+detla t)/delta t (t+delta t)/delta t
BHST Exercise
Logging Run Number Log On Bottom delta t (hours) (t+ delta t)/delta t Temp
1 10/17/2001 4:45 21.25 1.2353 401
2 10/17/2001 12:16 28.77 1.1738 406
3 10/17/2001 21:36 38.10 1.1312 409
Temperature (degF)
407 y = -91.341Ln(x) + 420.4
406 415
405
Estimated BHST = 420 degF
404 410
403
402 405
401
400 400
1.0000 10.0000 1.0000 10.0000
(t+detla t)/delta t (t+detla t)/delta t
* This provides an indication that the frac pressure is at least that high
Pore and Frac Pressure from Offset WellsHochstetter Offset Pore & Frac Pressures
Maui 5 - 7 Te Whatu 2
500
An example
Witiora 1
Kiwa 1
Te Whatu 2
1000
Witiora 1
offshore
2000
Maui 5
Maui 6
Maui 7
wells
2500
Well Test Data
Maui 1 - 3
Kiwa 1
3000
Te Whatu 2
Witiora 1
3500
4000
Formation Strength Data - Example
0
Kauhauroa-1
Kauhauroa-2
1000 Kauhauroa-3
FIT
Kauhauroa-4
2000 Kauhauroa-5
Kauhauroa-3 Lost
Depth (ft MD rkb)
Circulation MW
Kauhauroa-4 Lost
3000 Circulation MW
4000
FIT
Formation Integrity
5000 Tests (FIT) are clearly
Identified FIT
6000
10 11 12 13 14 15 16 17 18 19 20
EMW (ppg)
Drill Bit Performance
Analysis
Drill Bit Performance Analysis
0
Drill bit performance analysis
1000
is an important component of
2000
offset well analysis.
(Depth (m)
4000
performance depends largely
5000 on the performance of the
6000 drilling bits.
0 50 100 150 200 250 300 350 400 450
Time (days)
Drill Bit Performance
A close analysis of the offset well bit records can yield valuable
information for improving the performance on subsequent wells.
Typical Bit Record
Rig Name: OE Well Name: H-1 Operator: Conf. Report Date: 6-March-2000
Bit Run Bit Manuf. Bit IADC Serial Nozzles TFA Footage Depth Hours Avg. Avg. Avg. Circ. SPM Cutters Bea Gau Oth. Rsn.
No. No. Size Type Code Number (1/32 in) in2 (m) Out On Bit ROP WOB RPM Press. FLOW I O D L ring ge
(in.) (m) (hr.) ( m/hr ) (Klbs) (psi) gpm
1 1 26 Reed EMS 11 KCC 115 Y96189 2 x 20 ; 1 x 22 2.356 93 310 6.0 15.5 2 80 750 1000 0 0 NO A E I NO TD
1 2 26 Reed EMS 11 KCC 115 Y96189 2 x 20 ; 1 x 22 2.356 2 312 0.5 4.0 6 80 750 1000 0 0 NO A E I NO TD
2 1 17 1/2 Reed EMS 13 GLKC 135 X54592 1 x 16 ; 3 x 20 1.117 1088 1400 29.5 36.9 12 130 2400 900 1 1 NO A E I NO TD
3 1 12 1/4 Hycalog DS 69 HFGNV 22809 4 x 14 ; 2 x 16 0.994 1460 2860 56.5 25.8 12 160 2600 850 1 1 WT G X I PN TD
4 1 8 1/2 Hycalog DS 56 DGJ M432 18757 3 x 12 ; 1 x15 0.504 4 2864 4.5 0.9 20 110 1900 450 0 0 BU A X I NO PR
5 1 8 1/2 Reed EHP 51 ALKDH 517 KN2702 2 x 14 ; 1 x 16 0.497 326 3190 53.5 6.1 25 100 2050 450 3 3 WT A E I NO HR
4 2 8 1/2 Hycalog DS 56 DGJ M432 18757 1 x 14 ; 2 x 16 0.543 2 3192 3.5 0.6 20 130 2300 450 0 0 BU A X I NO PR
6 1 8 1/2 Hycalog EHP 51 ALKDH 517 KT2772 3 x 14 0.451 106 3298 9.0 11.8 20 100 2400 450 1 1 NO A E I NO TD
IADC Bit Dull Grading Code
0 1 2 3 4 5 6 7 8
Inner Cutting
Structure (All Inner Cone 1
Rows)
Outer Cutting
Structure (Gauge
Row Only)
Cone 2
Cone 3
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
IADC Bit Dull Grading Code
Cutting Structure B G Remarks
INNER OUTERR DULL LOCA- BRNG/ GAUGE OTHER REASON
ROWS OWS CHAR TION SEALS 1/16” CHAR PULLED
POST OR STUD
CUTTERS
CYLINDER
CUTTERS NO WEAR WORN BROKEN LOST BOND
(NO) CUTTER CUTTER CUTTER FAILURE
(WT) (BT) (LT) (BF)
Courtesy of
Dull Characteristics – Some Examples
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
Dull Characteristics – Some Examples
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
Dull Characteristics – Some Examples
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
Dull Characteristics – Some Examples
TR - Tracking
Dull Characteristics – Some Examples
N - Nose Row
M - Middle Row
Cone 1, 2 or 3
G - Gauge Row
A - All Rows
C - Cone
N - Nose
T - Taper
S - Shoulder
G - Gauge
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
IADC Bit Dull Grading Code
Cutting Structure B G Remarks
INNER OUTERR DULL LOCA- BRNG/ GAUGE OTHER REASON
ROWS OWS CHAR TION SEALS 1/16” CHAR PULLED
Sealed Bearings
E - Seals Effective
F - Seals Failed
N - Not Able to Grade
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
IADC Bit Dull Grading Code
Cutting Structure B G Remarks
INNER OUTERR DULL LOCA- BRNG/ GAUGE OTHER REASON
ROWS OWS CHAR TION SEALS 1/16” CHAR PULLED
If the bit is under gauge, the amount is recorded to the nearest 1/16” of an
inch. For example, if the bit is 1/8” under gauge, this is reported as 2/16
or often only as 2.
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
IADC Bit Dull Grading Code
Cutting Structure B G Remarks
INNER OUTERR DULL LOCA- BRNG/ GAUGE OTHER REASON
ROWS OWS CHAR TION SEALS 1/16” CHAR PULLED
This is for the Secondary dull char. and it uses the same codes as for the Primary dull char.
Fixed Cutter Bits Roller Cone Bits
BF - Bond Failure *BC - Broken Cone LN - Lost Nozzle
BT - Broken Cutters BF - Bond Failure LT - Lost Teeth/Cutters
BU - Balled Up BT - Broken Teeth/Cutters OC - Off-Center Wear
CT - Chipped Cutters BU - Balled Up Bit PB - Pinched Bit
ER - Erosion *CC - Cracked Cone PN - Plugged Nozzle/Flow Passage
HC - Heat Checking *CD - Cone Dragged RG - Rounded Gauge
JD - Junk Damage CI - Cone Interference RO - Ring Out
LN - Lost Nozzle CR - Cored SD - Shirttail Damage
LT - Lost Cutter CT - Chipped Teeth/Cutters SS - Self Sharpening Wear
NR - Not Rerunable ER - Erosion TR - Tracking
PN - Plugged Nozzle FC - Flat Crested Wear WO - Washed Out Bit
RG - Rounded Gauge HC - Heat Checking WT - Worn Teeth/Cutters
RO - Ring Out JD - Junk Damage NO - No Dull Characteristic
RR - Rerunable *LC - Lost Cone
SS - Self Sharpening Wear * Show Cone under Location 4
TR - Tracking
WO - Washed Out Bit
WT - Worn Cutters
NO - No Dull Characteristics
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
IADC Bit Dull Grading Code
Cutting Structure B G Remarks
INNER OUTERR DULL LOCA- BRNG/ GAUGE OTHER REASON
ROWS OWS CHAR TION SEALS 1/16” CHAR PULLED
Ref : Reed Hycalog PDC & Roller Cone Product Technology Reference Information
Key to Dull Bit Grading: Grade a Lot of Dulls !
Photo courtesy of
11” Bits Bit Performance Analysis Example
7-7/8” Bits
0 ft
A May 2002 B Jun 2002 C Aug 2002 D Sep 2002
GT-C1 (117)
6x13, 20, 120-150 195.8 201.0
1000 ft 1-1-WT-G-X-I-NO-TD 213.3
1173 1156
GT-C1 (117) 1175 GT-C1 (117)
GT-C1 (117) 6x13, 20, 120-150
2000 ft 3x16, 1x13, 45, 160-175
3x16, 1x13, 40, 60-120
1-1-WT-G-X-I-NO-TD 1-1-WT-G-X-I-NO-TD
1-1-WT-A-1-I-NO-TD
3000 ft
Ft Union
3565 66.7 ft/hr
4000 ft
HC 606 (PDC)
6x14, 10-28, 40-60
HC 606 (PDC) 1-2-CT-S-O-I-WT-BHA
5000 ft 6x13, 5-25, 45-115
1-1-CT-T-X-I-RO-PR
Cb Cr (tb tc tt )
Cf
Where: D
Cf Cost per foot ($/ft)
Cb Cost of the bit ($)
Cr Operation spread rate ($/day)
tb Time rotating (hrs)
tc Time for connections(hrs)
tt Round trip time (hrs)
D Footage drilled
A Case History
Offset Well Bit Record
Dull
Inner Outer Dull Loca- Bear Gage Other Reason
Hole Dia. BIT IADC Depth In Depth Out Interval Hrs ROP Rows Rows Char tion Seals 1/16" Char Pulled
Take a close look at the IADC code, ROP and dull code. What can you
assume ?
This is PDC country !
Bit Program of the Well Drilled by IPM
12-1/4” Interval
Bit Dia. Interval (m) Bit Type IADC Nozzle Flowrate Mud Weight Predicted HIS
(inches) Code (1/32") (gpm) (sg) SPP (psi) (HHP/in2)
12-1/4" 1636 to 2266 DS66H M432 6 x 11 700 1.10 - 1.20 2500/2750 4.8
Note that a DS66H was programmed to drill the complete 12-1/4” interval. The
alternate bit differed depending on section depth (it is essential to have an alternate
plan when trying PDC’s for the first time in an area).
Bit Record of the Well Drilled by IPM
When the DS66H was pulled, it was still drilling at 50 ft per hour !
What can be said about the dull grading ? 3-4-WT-S-X-1-CT-TQ
3-4-WT-S-X-1-CT-TQ
Answer:
This bit was actually pulled to surface after a wiper trip. Torque is indeed
a very unlikely reason for pulling a PDC bit which shows uniform wear.
Given that this bit was still drilling at 50 ft/hr and that only approx. 450 ft
were left to drill, the right decision should have been to rerun it.
Bit Record of the Well Drilled by IPM
Given that there was only about 450 ft left to drill, an inexperienced WSS
decided to run the cheapest bit on the rig (a milled tooth bit IADC code
113). The bit drilled to TD of 9842 ft at an average ROP of 11.8 ft/hr.
What can be said about the dull grading ? 7-7-WT-A-F-2-CD-PR
7-7-WT-A-F-2-CD-PR
Answer:
We were lucky to make it to TD ! The cutting structure was gone,
the bearings had failed, the bit was 1/8” under gauge and it
showed indication of cone drag. Pulling on rate of penetration is
wrong given that the well had reached TD.
Bit Economics – Compare Alternatives
Operation Spreadrate 63,500 $/day
Interval to drill 450 ft
Trip time 11 hours
HP13G EHP51H DS66H
Bit Price ($) 5,280 12,900 free*
Expected Average ROP (ft/hr) 20 15 10 40 30 20 45 40 35
Time to Drill (hours) 22.5 30.0 45.0 11.3 15.0 22.5 10.0 11.3 12.9
Cost per Foot 209 253 341 159 182 226 123 131 140
* In this type of incremental interval economics, we can assume that the bit cost has been absorbed by the
previous run. Note that the original cost of the DS66H was $46,000.
All prices are in 1995 dollars.
Notes:
The sensitivity analysis shows that that DS66H ROP could decrease significantly and still be
more economical that the roller cone bits
Assuming the DS66H would have continued drilling at an average of 45 ft/hr, this poor bit
selection resulted in losses of:
$5,280 + 63,500$/day/24hrs/day x (37.0-9.7)hrs = $77,511
Rock Strength Analysis (RSA)
2800
2850
2900
Using the spreadsheet of the daily drilling report activities for Well
SB-1, prepare the following:
- a list of all Non Productive Time (Day, Description, Duration)
- a pie chart showing the NPT distribution
- indicate what is the proportion of NPT as a percentage of total
well time
If you finish early, you may also wish to plot the time versus depth
curves (total time and clean time).
SB-1 List of NPT Events
Day Description Time (hrs)
1 Repair Bell Nipple 1
1 Replace Damaged Saver Sub 2
1 Change Anadrill Sensor on Drawworks 0.5
2 Repair Mud Mixing Pump 1
3 Clean Excessive Cement Returns 7.5
4 Repair Leaking Coflexip Hose 2
5 Correct Rig Subsidence Problem 164.5
15 Problem Breaking Out Drill Pipe 0.5
16 Monitor Mud Losses 0.5
16 Change Leaking Pop Valve 0.5
17 Repai Drawworks 20.5
18 Stuck Pipe 3
19 Repair Dead Line Anchor Weight Sensor 1
19 Stuck Pipe 1.5
20 Stuck Pipe 8.5
21 Stuck Casing 5
23 Repair Air Compressor 3.75
25 Re-do Control Line Hnager Connection 3
Total 226.25
SB-1 NPT Breakdown
2% 1%
3% 0%
6%
Rig Subsidence
14% Rig Equipment
Stuck Pipe
Excessive Cement Returns
Stuck Casing
Hanger Control Line Connection
Other
74%
0
Measured Depth (m)
1500
2000
2500
16.1 25.
0 10 20 5 30
Time (days)
Drill Bit Exercise
►Validate the pore and fracture pressures from offset wells data
►Estimate the Bottom Hole Static Temperature (BHST) from log
data
►Analyze drill bit performance