Professional Documents
Culture Documents
1.0 Purpose/Scope
CTD liner cementing techniques continue to evolve. Recent equipment developments have
eliminated the inner string method for cementing. By displacing the entire hole to KCL water
prior to pumping any cement, the friction pressure drop in the system is reduced allowing higher
pump rates. This fluid change-out eliminated the mud/cement incompatibility concerns with
respect to fluid immobility. To increase low-side flow area, integral blade centralizers are now
used throughout the entire open hole section at each tool joint.
For 3-3/4” hole, BP CT Drilling has standardized on 2-7/8”, 6.16#, L-80, ST-L liner. For slim
(3.0”) hole, 2-3/8”, 4.7#, L-80 ST-L liner is used. While FL4S connections have been used in
the past, ST-L is preferred because of the longer thread and greater strength, particularly in the
bending stress conditions imposed in high dogleg areas. 3-3/16” TC II and 3-1/2” ST-L are
used in certain applications.
2.0 Definitions
CTLRT- Coiled Tubing Liner Running Tool
LBRT - Liner Backdoor Running Tool
TOL - Top of liner
ELM - Electric line measurement
5.0 Procedure/Process
Pre-Job Planning and Safety
1. Well Control:
Monitor well bore fluid level and keep hole full at all times.
Ensure TIW stabbing valve is tested, labeled, and ready in open position for
each liner size/thread being run.
If slotted liner is to be run, ensure a solid safety joint is available for
immediate deployment.
2. Confirm appropriate liner sized slip rams are in place in the BOP stack.
2. Use “YT” elevators (slip type).
3. The liner lifting nubbins should be tightened with a 24” pipe wrench and a back-up.
4. Use the proper size bowl, slips, and safety clamp for each liner size to be run.
5. Baker lock float equipment and joints if liner may be drilled out at a later date.
6. Strap and drift all pipe. Install centralizers as described in the procedure below. Be sure to
have an accurate total joint count for all liner on location, both inside and outside the pipe
shed. Note: Due to close liner wiper plug tolerances, it is important that 2-3/8” liner and
centralizers be drifted to 1.85” with a 16” or longer drift. 3-3/16” liner should be special
drifted (Non API) to 2.75” for possible future drill outs.
7. Provide cementers with a minimum of 24 hours advance notice. Fax the cement data sheet
from the well plan . Include an estimated BHT verified from MWD measurements.
Liner Running Procedure
1. Determine desired location of liner top based on condition of the production tubing and
location of jewelry. Be sure TOL is located by ELM and not drillers depth. Where possible,
plan to space out liner with at least one full joint above the tubing tail. Determine the size
and type of deployment sleeve based on tubing size and need for a liner top packer. The
standard deployment sleeve for 2-7/8” liners is 3.70” OD, 3.00” ID, 6’ long, and has a 4” GS
profile on top. The standard deployment sleeve for 2-3/8” liners is 2.7” OD, 2.25” ID, 6’
long, and has a 3” GS profile on top. Modifications to this may include a larger entry guide
on top for different sizes of tubing or increased length for seal movement in long straddle
applications.
2. Prior to POOH with the drilling assembly to run liner, short trip to the window at no more
than 30 fpm, tie in to RA marker and short trip back in to further condition the hole and to
confirm TD. Make a second wiper trip if hole conditions warrant. Inadequate hole cleaning
can prevent the liner from reaching TD.
3. In wells with poor hole conditions, lay in a pill of clean or new flo pro (corrosion inhibiter
not required) on the final up pass. This will require pulling slowly to avoid excessive pill
size. Flag the coil sufficiently far above the window so that a depth correction can be made
prior to the liner entering open hole. A flag +/- 50’ from bottom can help verify that the liner
reaches TD.
4. The coil volume and micro motion accuracy should be determined. This should be
performed during initial coil displacement at the start of each well. If coil volume has not
been verified prior to running the liner, circulate the CT with the wiper dart to be pumped
behind cement. Determine accuracy of micro motion meters in and out. Check against
known reel volume and against magnetic counter on triplex pump. Note any damage on dart
when retrieved. For slim hole applications, verify that dart will pass through weld on coil
connector id.
5. Hold an on-site safety meeting to review liner running related issues. Review well shut-in
procedures and responsibilities.
6. Determine fluid volume requirements for displacement (KCl) and cementing (fresh water).
Plan to save mud system for processing at mud plant for re-use. Schedule fluids and trucking
as required.
7. MU up the liner assembly as detailed in the well plan. Typically as follows:
CEMENTING PROCEDURE
Run thickening time and fluid loss tests based on BHCT = 150 F or BHCT
observed on MWD while drilling if higher than 150 F. Adjust to achieve a
thickening time of 3 to 4 hrs plus 1 hr on surface.
Retain a slurry sample for UCA testing by cementers.
Do not rig cementers down until cement is in place and running tool is free from
liner. Cementers pump may be needed for unplanned contingencies.
noted. Slow pumps to 0.5 BPM no more than 1 bbl before planned plug bump. If plug
does not bump, do not over displace more than liner volume below landing collar.
8. Liner wiper plug will latch into the Baker landing collar and provide two way check.
Bleed off pressure to check floats. Re-pressure to +/-500 psi and sting out of tie back
sleeve. Begin circulating while stinging out to prevent any excess cement from falling
past running tool.
9. Circulate at liner top to clear any excess cement. POOH chasing contaminated cement.
Notify pit watcher for estimated bottoms up. Check for cement in bottoms up returns
and estimate volume if possible. LD running tool BHA
10. MU swirl sub on coil. Stab on well and flush BOP stack to remove any trapped cement.
1. If slim hole, plan to PU a 1-11/16 motor and 1.85” mill assembly. Experience has
shown that even trace amounts of cement can result in slim hole logging and /or
perforating problems. In big hole, if job parameters were normal (dart latch, plug bump,
floats held), then proceed with logging and/or perforating.
2. While logging big hole, utilize the pump through tool carrier. Circulate both in and out
of hole in the event that green cement is encountered inside the liner. Do not exceed 1.5
bpm while logging due to possible vibration induced logging tool problems. Circulate in
150k LSRV new flopro for perforating. Pull out of hole.
3. Consult Schlumberger UCA cement test. When cement is at least 2500 psi compressive
strength, pressure test liner and lap to 2000 psi (or as per well plan) prior to
perforating. If the lap bleeds off more than 15% of test pressure in 30 minutes, a liner
top packer may be required. Monitor the inner annulus and surface pressures to verify
leak is at lap. Consult with town. If required, the liner top packer will normally be set
before perforating.
4. Prepare to perforate liner.
Field make-up torques for 2 7/8” and 3 ½” ST-L connections are typically higher than the “book
value” given by the manufacturer. Field torque values may vary with block alignment, ambient
temperature and tong calibrations. A simple procedure to achieve good ST-L connection make up is
as follows:
a. Make up ST-L connection with hand wrenches to shoulder “contact”.
b. Scribe a vertical line across the connection with a medium tip magic marker
(1/8”)
c. Use hydraulic tongs to make up connection such that the scribed line is offset
one marker width (1/8”). Note torque required. ( 1/8” scribe movement
equates to 5 degrees rotation on 2 7/8” pipe and about 6 degrees on 2 3/8” pipe)
d. Inspect box to confirm no swelling.
e. Repeat three to four times to confirm repeatable torque numbers.
f. Use field determined torque value for remainder of liner job.
The collared TC II connection on 3 3/16” pipe shoulders internally rather than externally.
However, the make up procedure given above for ST-L can be used for TC II also. Detection of
“contact” may be a bit more difficult with TC II as there is more thread interference than with
ST-L. The same principle applies in that rotation of approx. 5 degrees or 1/8” after pin
“contact” will result in good make up.
Revision Log
Revision Date Approving Custodian/ Revision Details
Authority Author
December 1997 Original Issue
March 31, 1999 Drilling Manager John McMullen
April 2, 2002 CTD Manager Gary Goodrich Revised entire procedure to reflect
current practices. Deleted liner top
packer section.
<< Revision date >> << Approving << Author’s << Brief Description of Revision
Authority’s Name >> Name >> >>