MANAGEMENT MEETING AGENDA NO.

100

Reference No.: CGCMAKATI-03-008-1C1-100

PROJECT : PROPOSED 10 STOREY CHURCH BUILDING


LOCATION : LOT 6,7,8 BLOCK 34 JAVA STREET BARANGAY PALANAN MAKATI
CITY OWNER : CHRISTIAN GOSPEL CENTER INC.
DATE : JANUARY 30, 2023 TIME: 2:00 PM
VENUE : FACE-TO-FACE MEETING (JOBSITE)
ITEM MATTERS TO BE DISCUSSED RESPONSIBLE REMARKS
NO. PARTIES
1.0 CLARIFICATION OF PREVIOUS MINUTES ALL For Approval
2.0 PROJECT STATUS
Project Status as of (January 30, 2023) ELS
(Based on Revised Bar Chart dated February 18, 2022)
Projected Accom. = 75.785% Present Accom. (January 30,2023) = % For Update As per joint of PCDC &
Variance= (+/-) % For Update Equivalent No. of Days = % For Update ELS evaluation
Start of Construction = July 15, 2020 Project Duration= 660 Calendar Days
Elapsed Days = 929 Calendar Days
2.1 End of Construction = May 06, 2022 CARI Period = May 20, 2022 to February 28,2023
Bldg. Permit Released: July 01, 2020 Bldg. Permit No. BP-2020-02-0445
Time Extension:
Time Extension 1 - 21 days Revised Project Duration – 1080 Calendar Days
Time Extension 2 - 271 days Revised Remaining Days – 151 Calendar Days
Time Extension 2 - 128 days
Total - 420 days Revised End of Construction – June 30, 2023
2.2 Progress Reporting including Two Weeks Look Ahead Schedule and Safety Report PCDC FOR PRESENTATION
3.0 GENERAL REQUIREMENTS
3.1 DETAILED SITE ACTIVITIES ACCOMPLISHMENT MONITORING ELS FOR PRESENTATION
4.0 DESIGN CONCERNS
4.1 RFA/RFI/MATERIAL/SHOPDRAWING APPROVAL MONITORING
4.2 CIVIL/ STRUCTURAL/ ARCHITECTURAL
4.2.1 DECK FLOOR LOBBY DESIGN ANGLO FOR UPDATE
4.2.2 DECK FLOOR TO MACHINE ROOM DETAILS ANGLO FOR UPDATE
4.2.3 APPROVED PAINT COLOR DESIGNATION/ROOM ASSIGNMENT ANGLO FOR UPDATE
4.2.4 SITE DEVELOPMENT PLAN ANGLO FOR UPDATE
4.3 INTERIOR
4.3.1 INTERIOR DESIGN FOR, GRAND LOBBY, HUTENG, BANQUET, & WORSHIPHALL ANGLO FOR UPDATE
4.3.2 REVISED CEILING LAYOUT AT GROUND FLOOR, WORSHIP HALL, & PRAYER ROOM ANGLO FOR DISCUSSION

4.3.3 TILES FOR THE DECK AND POOL ALL FOR DISCUSSION
4.3.4 PLUMBING FIXTURES ALL FOR DISCUSSION
4.3.5 STAIR AT DECK GOING TO MACHINE ROOM ANGLO FOR UPDATE
4.3.6 ACOUSTIC DESIGN & STAGE LAYOUT ALL FOR DISCUSSION
4.3.7 STAIR DETAIL OF ACCESS FOR MIDPARKING ELS FOR PRESENTATION
4.3.8 COUNTERTOP DETAIL ANGLO FOR UPDATE
4.4 MECHANICAL/ELECTRICAL/PLUMBING/SANITARY/FIRE PRO
4.4.1 SMART PARKING SLAB AND TURNTABLE COMPLETION ALL FOR DISCUSSION
4.4.2 ELEVATOR SHAFT & PIT COMPLETION ALL FOR DISCUSSION
4.2.3 MOCKUP FOR FIRE HOST CABINET AND INTERCOM LOCATION ALL FOR DISCUSSION
5.0 OPERATION CONCERNS
5.1 CIVIL/ STRUCTURAL/ ARCHITECTURAL
5.1.1 OVERALL REVISED TARGET FINISHED SCHEDULE PCDC FOR PRESENTATION
5.1.2 SLAB ON GRADE COMPLETION PCDC FOR UPDATE
6.0 OSM/OFCI CONCERNS
6.1 OSM/OFCI MONITORING ALL FOR UPDATE
7.0 OTHER MATTERS
8.0 WALKTHRU
9.0 ADJOURNMENT
NOTE: ALL ISSUES MUST HAVE AN IMMEDIATE AND CONCRETE RESPONSE FROM THE RESPONSIBLE PARTY/IES AS IT AFFECTS THE OVERALL COMPLETION OF THE PROJECT.

CGCMAKATI Mgmt. Meeting No.100 Effectivity date: January 25, 2022


DC No.: ELS-FM-OP-003-08-1C1-02 Page 1 of 1

HEBREWS 13:5
“Keep your life free from love of money and be content with what you have, for he has said, “I will never leave you nor forsake you.””

You might also like