Possession
METROPOLITAN LINE
43
22 January 2021 to 25 January 2021
7.0 INTRODUCTION 4
8.0 COMMUNICATION 5
10 WORKSITE INFORMATION 9
12 ENGINEERING TRAINS 30
13 CONTINGENCY ARRANGEMENTS 31
14 EMERGENCY ARRANGEMENTS 32
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 | Introduction 2
15 CHANGE CONTROL 33
16 SIGNATORIES 34
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 | Introduction 3
7.0 Introduction
7.1 Document Purpose
This document describes the detailed worksite locations, Possession logistics and planned work for the
following Possession: Between Preston Road Substation Gaps to Baker Street Substation Gaps
including Neasden Depot All excluding the Sheds on the Metropolitan Line and from Stanmore to the Buffer
stops at Charing Cross Sidings and Step-Plate south of Green Park on the Jubilee Line (including
Stanmore Sidings).
When traction current is switched off and there are no train or rail mounted mechanised vehicle movements
within the possession, track certification is not required. All staff/contractors must however hold the relevant
LU access induction requirement. LU Staff will be required to produce their staff pass, accompanied by the
worksite safety induction completed on e-zone (paper certificate). Contractors will be required to produce a
Sentinel card endorsed with the Industry Common Induction - LU module.
Anyone who is working within a possession published with Train/Rail mounted mechanised vehicle
movements must have Basic Track Awareness certification as a minimum. (LU-RB14-Section 6.4)
All staff/contractors working within the Possession must ensure when booking on with the Possession
Worksite Access Controller (PWAC) that they have on their person the required certification, failure to do so
will see access to the Possession denied in line with LU Rules/Quensh.
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 | Introduction 4
8.0 Communication
8.0 Pre-Possession Briefings
The EIC Briefing for this possession will be held at Conference Call: Dial 322 from an O2 mobile, 9322 for
mobile extension or 03333 009 800 from non-o2 mobiles or landlines, Conference Pin: 07711196938, at
10:30 on Wednesday 20 January 2021 to confirm the safety and operational arrangements. The SPC and/or
worksite manager for each of the worksites must be in attendance for this briefing.
The POM Briefing for this possession will be held at Stratford Market Depot from telephone recorded line, at
13:30 on Wednesday 20 January 2021 to confirm the safety and operational arrangements. The Protection
Masters responsible for Possession and Worksite implementation must be in attendance for this briefing.
Failure to comply with this procedure will lead to future worksite requests being refused.
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 | Communication 5
• Lessons learned, remedial measures and further actions have been identified, recorded and
communicated to all who need to know.
Conference Call 2 (Possession Handback Status) 21:00hrs Sunday 24th January 2021
Agenda
Discussions associated with the remaining number of active worksites within the Possession to review and
measure:
• The works progress against the planned programme;
• Remaining critical activities (i.e. train movements/ departures and signal testing);
• Any accidents / incidents that might have occurred and the recovery status;
• Remaining Possession milestones and stages;
• Discuss any contingency arrangements in the event of a possible over-run.
Agenda:
Discussion associated with the Switching ON of Traction Current within the Possession area (Stanmore
Sidings and Neasden Depot) and to ensure all critical resources are in position and understand duties to be
undertaken.
Participants Required.
• Engineering Works Manager (EWM)
• Engineer in Charge (EIC)
• Service Managers (Jubilee and Metropolitan Lines)
• Cable Lineman
• Possession Master (POM)
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 | Communication 6
9.0 Contact Details
H&C, Circle and Metropolitan Line Service Managers BT: 0207 027 5714 Auto: 55714
ServiceManagersH&CCircleMet@tube.tfl.gov.uk
Bakerloo Line Service Manager BT: 0207 918 1290 Auto: 41290
SvcMgrsBakerloo@tfl.gov.uk
This role is responsible for the overall management of the operational service.
11
Other Limits:
Buffer Stops on all Roads in Stanmore Sidings (No markers required)
Northern Limits:
Buffer Stops at Stanmore Platforms 1, 2 & 3 (No markers required)
WORKSITE LIMITS (B) Southern Limits:
20:00HRS SAT TO 00:01HRS SUN Kingsbury South End TOR, Both Roads
TRACTION CURRENT WILL BE ON
IN STANMORE SIDINGS
Other Limits:
At the Traction Current Gap at 32A Points (Stanmore Sidings)
At the Traction Current Gap at 17B Points (Stanmore Sidings)
Northern Limits:
Buffer Stops at Stanmore Platforms 1, 2 & 3 (No markers required)
WORKSITE LIMITS (C)
Southern Limits:
00:01HRS SUN TO 20:00HRS SUN
Kingsbury South End TOR, Both Roads
Other Limits:
Buffer Stops on all Roads in Stanmore Sidings (No markers required)
TRAIN WORKING AREA N/A
SCOPE OF WORK Renew 17B Crossing and various works within Stanmore Sidings
TOOLS & EQUIPMENT P-way tools, trolley and hand tools
Site 1
WORK LOCATION Stanmore to Queensbury including Stanmore Sidings
WORKSITE ACCESS CONTROL Stanmore.
POINT
UNIQUE REF NO 18351/4775
PLANNED START 03:00hrs Saturday
PLANNED WHEELS N/A
WORKSITE TIMES FREE
PLANNED HAND 03:00hrs Monday
BACK
ASSET ASSURANCE MEASURES PRIOR TO HAND BACK
P WAY T002/3
SIGNALS Technical Officer Signal Engineer
POWER Isolation Person (CLM)
Area Manager and FRC will be notified as required of any change to the planned station operational
STATIONS hours
TRAINS N/A
ENG TRAINS N/A
TRAINS IN USE N/A
ROAD & RAIL VEHICLES IN USE N/A
PPE & CERTIFICATION Minimum BTA and as per Asset Ops method statement
REQUIREMENTS
OTHER NOTES
TRACTION CURRENT IN STANMORE SIDINGS WILL BE ON/OFF TO THE REQUIREMENTS OF THE POM FOR THE
POWERING UP OF JUBILEE LINE TRAINS.
• THE SPC AND PWAC GET A CALL FROM JUBILEE FLEET TEAM THEY ARE READY TO POWER UP TRAINS IN
STANMORE SIDINGS.
•
MILESTONES AS PER PUBLISHED UNLESS REQUESTED OTHERWISE BY EIC. A 4 HOURLY PROGRESS
UPDATE IS TO BE COMMUNICATED TO EIC AND ALL INCIDENTS/SUB-STANDARD ACTS, ARE TO BE
REPORTED TO THE LU INCIDENT LINE (SEE CONTACT DETAILS) AND THE DUTY EIC TO BE ADVISED
ACCORDINGLY.
RECORDED DECLARATIONS
I have received a briefing from the Possession Master, and I have read and understood this Possession Works Guide and associated Possession
Plan / Possession Amendment Notice. I am aware of my responsibilities and am satisfied that the arrangements detailed within the documentation
will allow all staff within the Worksite suitable Protection.
DATE: TIME: COMPANY: NO OF STAFF:
PWAC NAME: TRACK CERTIFICATION NO:
SIGNATURE:
PWAC CONTACT: ALTERNATIVE CONTACT:
I have informed the Possession Master via a recorded telephone line that the track is safe for trains to run, and that a Site Clear or Site Safe
message can be passed to the relevant person(s).
DATE: TIME: COMPANY:
PWAC NAME: TRACK CERTIFICATION NO:
PWAC CONTACT:
NOTE: PHYSICAL BARRIER TO BE ERECTED WHEN WORKING NEXT TO LIVE TRACK TRACK AT ALL TIMES
Other Limits
At South of Sectionalisation Gap between 51A and 51B Points (Neasden Depot –
WORKSITE LIMITS (A)
Wembley Park end)
03:00HRS SATURDAY TO
At South of Sectionalisation Gaps between 52A and 52B Points (Neasden Depot -
04:00HRS SATURDAY
Wembley Park end)
Clear of the Fouling point of Points 49A and 48B (Wembley Park).
Clear of the fouling point of 34A points south of Wembley Park
Clear of the fouling point of 45A points south of Wembley Park
Clear of the fouling point of 20 points at Neasden
Clear of the fouling point of 25B points at Neasden
Buffer Stop Wembley Park Sidings (31 Road)
Buffer Stops of Wembley Park Sidings (32 to 36 Roads) (No markers required)
Other Limits
Buffer Stop Wembley Park Sidings (31 Road)
Buffer Stops of Wembley Park Sidings 32 to 36 Roads (No markers required)
TRACTION CURRENT WILL BE ALIVE ON MAUVE, RED, RED / WHITE, GREEN, BLUE, BLUE /
WHITE, BROWN, INDIGO, CHARCOAL, CHARCOAL / INDIGO AND PART ORANGE (52 TO 57
ROADS) TRACTION CURRENT SECTIONS INCLUDING ALL SHED ROADS IN NEASDEN DEPOT. A
SAFE SYSTEM OF WORKS MUST BE IMPLEMENTED TO PREVENT AND ENSURE STAFF WILL NOT
ENTER THE RECHARGED TRACTION CURRENT AREAS IN THE DEPOT.
• PHYSICAL BARRIERS TO BE ERECTED AT THE FOLLOWING WORKSITE LIMITS TO
ENSURE THE PREVENTION OF STAFF STRAYING OUTSIDE THE WORKSITE AREAS:
o BETWEEN 501A AND 502B POINTS ON ROAD 3 AND ADJACENT ON ROADS 1,
2 AND 4
o 10M SOUTH OF SIGNAL 222 ON BOTH 21 AND 22 ROADS (YELLOW
SECTION)
o AT THE TIP OF 618 POINTS (CHARCOAL / ORANGE SECTION)
o AT THE TRACTION CURRENT GAP SOUTH OF SIGNAL 945 (45 ROAD)
o AT THE TRACTION CURRENT GAP SOUTH OF SIGNAL 946 (46 ROAD)
o AT THE SOUTH ENTRANCE SHED DOORS OF ROADS 40 TO 44
Other Limits
Buffer Stop Wembley Park Sidings (31 Road)
Buffer Stops of Wembley Park Sidings (32 to 36 Roads) (No markers required)
Other Limits
At South of Sectionalisation Gap between 51A and 51B Points (Neasden Depot –
WORKSITE LIMITS (F) Wembley Park end)
21:00HRS SUNDAY TO At South of Sectionalisation Gaps between 52A and 52B Points (Neasden Depot -
03:00HRS MONDAY Wembley Park end)
Clear of the Fouling point of Points 49A and 48B (Wembley Park).
Clear of the fouling point of 34A points south of Wembley Park
Clear of the fouling point of 45A points south of Wembley Park
Clear of the fouling point of 20 points at Neasden
Clear of the fouling point of 25B points at Neasden
Buffer Stop Wembley Park Sidings (31 Road)
Buffer Stops of Wembley Park Sidings 32 to 36 Roads (No markers required)
Buffer Stop at Willesden Green Siding (No markers required)
Cut-in Points including Signals assets maintenance and Signals assets works on
SCOPE OF WORK Roads 1 - 4 (Signals 701,702,703,704) and klondyke (Signals 721,722 and 723).
Site 2
Between 10 metres south of Preston Road Sub Gaps all roads (Met) and Wembley
WORK LOCATION Sub Gaps (Jub) to Dollis Hill / Willesden Green All Roads including Neasden
Depot.
WORKSITE ACCESS
Neasden Depot and Wembley Park Station
CONTROL POINT
UNIQUE REF NO 18351/4776
PLANNED START 03:00hrs Saturday (Mainline)
04:00hrs Saturday (Mainline including Neasden depot)
PLANNED
WORKSITE TIMES WHEELS FREE
N/A
PLANNED HAND 20:00hrs Sunday (Neasden depot excluding mainline)
BACK 03:00hrs Monday (Mainline)
ASSET ASSURANCE MEASURES PRIOR TO HAND BACK
P WAY T002/3
SIGNALS Technical Officer Signal Engineer
POWER Isolation Person (CLM)
Area Manager and FRC will be notified as required of any change to the planned station operational
STATIONS hours
TRAINS N/A
ENG TRAINS N/A
RECORDED DECLARATIONS
I have received a briefing from the Possession Master, and I have read and understood this Possession Works Guide and associated Possession
Plan / Possession Amendment Notice. I am aware of my responsibilities and am satisfied that the arrangements detailed within the documentation
will allow all staff within the Worksite suitable Protection.
DATE: TIME: COMPANY: NO OF STAFF:
PWAC NAME: TRACK CERTIFICATION NO:
SIGNATURE:
PWAC CONTACT: ALTERNATIVE CONTACT:
I have informed the Possession Master via a recorded telephone line that the track is safe for trains to run, and that a Site Clear or Site Safe
message can be passed to the relevant person(s).
DATE: TIME: COMPANY:
PWAC NAME: TRACK CERTIFICATION NO:
PWAC CONTACT:
NOTE: PHYSICAL BARRIER MUST BE ERECTED WHEN WORKING NEXT TO LIVE TRACK AT ALL TIMES
Other Limits
Buffer Stop at Willesden Green Siding
Worksite limits 3A Buffer Stop at West Hampstead Siding
03:00 SAT – 07:00 SUN Finchley Road north end TOR (both Met)
Clear of the fouling point at 11 points on the NB Jubilee Line at Baker Street
Clear of the fouling point of 3A points (Baker Street)
Clear of the fouling point at 11 points (Baker Street)
Clear of the fouling point at 4 points south of Green Park on the SB Jubilee Line at Step-
Plate Junction
Clear of the fouling point at 5 points south of Green Park on the NB Jubilee Line at Step-
Plate Junction
P&C tamp
Finchley Rd 20A&20B, West Hampstead 18B/19B FUT (+ 18A&19A if required) and
Willesden Green 6A&7A & 6B/7B in 2 x 12hr day shifts on Sat 23/01/21 & Sun
24/01/21.
SCOPE OF WORK
Rail Grinding
Site 3
Finchley Road to Green Park + Diesel Refuel at Willesden Green Sat EH Follow Up
Tamp of ITT works on the Jubilee line only.
SIGNATURE:
PWAC CONTACT: ALTERNATIVE CONTACT:
I have informed the Possession Master via a recorded telephone line that the track is safe for trains to run, and that a Site Clear or Site Safe
message can be passed to the relevant person(s).
DATE: TIME: COMPANY:
PWAC NAME: TRACK CERTIFICATION NO:
PWAC CONTACT:
Stock and Switch replacement on Points between Baker Street and Swiss Cottage
SCOPE OF WORK
TOOLS & EQUIPMENT Hand tools
Site 4
WORK LOCATION Between Baker Street and Swiss Cottage
WORKSITE ACCESS
Baker Street Pway cabin at the end of platform 4
CONTROL POINT
UNIQUE REF NO 18351/4778
PLANNED START 08:00hrs Saturday
PLANNED
Not Applicable
WORKSITE TIMES WHEELS FREE
PLANNED HAND
17:00hrs Sunday
BACK
ASSET ASSURANCE MEASURES PRIOR TO HAND BACK
P WAY T002/3
SIGNALS Technical Officer Signal Engineer
POWER Isolation Person (CLM)
Area Manager and FRC will be notified as required of any change to the planned station operational
STATIONS hours
TRAINS N/A
ENG TRAINS N/A
TRAINS IN USE Not Applicable
ROAD & RAIL VEHICLES IN USE Not Applicable
PPE & CERTIFICATION Minimum BTA and as per Asset Ops method statement
REQUIREMENTS
OTHER NOTES
MILESTONES AS PER PUBLISHED UNLESS REQUESTED OTHERWISE BY EIC. A 4 HOURLY PROGRESS UPDATE IS TO
BE COMMUNICATED TO EIC AND ALL INCIDENTS/SUB-STANDARD ACTS, ARE TO BE REPORTED TO THE LU
INCIDENT LINE (SEE CONTACT DETAILS) AND THE DUTY EIC TO BE ADVISED ACCORDINGLY.
RECORDED DECLARATIONS
I have received a briefing from the Possession Master and I have read and understood this Possession Works Guide and associated Possession
Plan / Possession Amendment Notice. I am aware of my responsibilities and am satisfied that the arrangements detailed within the documentation
will allow all staff within the Worksite suitable Protection.
DATE: TIME: COMPANY: NO OF STAFF:
PWAC NAME: TRACK CERTIFICATION NO:
SIGNATURE:
PWAC CONTACT: ALTERNATIVE CONTACT:
I have informed the Possession Master via a recorded telephone line that the track is safe for trains to run, and that a Site Clear or Site Safe
message can be passed to the relevant person(s).
DATE: TIME: COMPANY:
PWAC NAME: TRACK CERTIFICATION NO:
PWAC CONTACT:
13 Engineering Trains
13.1 The Possession is taken around the following trains
• Tamper 640 (Length 54m) Willesden Green Platform 3 SB Jub
• WT556 (Length 35m) – Schweerbau Rail Grinder -Charing Cross Platform 4
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 30
| Network Rail Interface Arrangements
14 Contingency Arrangements
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 31
| Contingency Arrangements
15 Emergency Arrangements
Where a significant Incident occurs involving Engineers Trains or Mechanised Vehicles the Renewals
and Enhancements Incident Management Process (Version 1A) will be instigated and led by the
Engineering Works Manager (EWM) and must be complied with by all staff concerned for all business
areas (R&E, MPD and Asset Operations). All work group leads will be required to discharge their duties
accordingly in line with the criteria set out within the Renewals and Enhancements Incident Management
Process (Version 1A).
15.2 Accident
In the event of an accident that requires emergency services please contact 999.
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 32
| Emergency Arrangements
16 Change Control
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 33
| Change Control
17 Signatories
PWG-WK43-MET.JUB-PRR.STAtoBAS.GPR.CHC-10333-22.01.21 34
| Signatories