Professional Documents
Culture Documents
In 2021, a further 701 hectares of land was rehabilitated, taking the total amount of land under rehabilitation to 14,746 hectares, which equates
to just over 39 percent of all land disturbed by mining in the Upper Hunter. During the same period, 514 hectares of disturbance was recorded.
The annual rehabilitation to disturbance ratio means that for every hectare of land disturbed, 1.36 hectares of rehabilitation was undertaken.
This is the first time since this project was first undertaken in 2012 to deliver a positive rehabilitation to disturbance ratio. At the close of the
reporting period, a total of 23,058 hectares of disturbed land is awaiting rehabilitation, which is also an improvement on the opening figure.
As cumulative figures are presented for all operations in the Upper Hunter rather than at a site-specific level, the total figures in any given year
may be impacted by newly established operations, or the expansion of an existing site. Sites commencing or expanding operations generally
disturb land at a higher rate than sites which are later in their lifecycle, where rehabilitation is more likely to increase nearer to closure. However,
all mines are required to progressively rehabilitate disturbed land throughout the duration of operations and publicly report their progress.
During the active operation of a mine site, there is only a limited amount of land that is available to be rehabilitated. Much of the land reported
as disturbed and awaiting rehabilitation, may not actually be available for rehabilitation during the reporting period as it is likely this is being
actively used in some capacity by mining operations during the reporting period.
Rehabilitation 2012 2013 2014 2015 2016 2017 [8] 2018 2019 2020 [12] 2021
A: Disturbed land
awaiting rehabilitation 17,830 18,098 18,479 20,171 21,180 21,472 21,816 22,276 22,726 23,245
- Start amount (ha) [4]
B: Total land newly
disturbed within the 1,163 1,148 1,057 1,424 [6] 1,270 1,008 1,666 979 1,380 514
reporting period (ha)
C: Total land newly
rehabilitated within
the reporting period
895 962 801 856 907 763 1,071 869 848 701
(ha) [1]
D: Disturbed land
awaiting rehabilitation 22,518
- End amount (ha)
18,098 18,283 18,736 21,008 21,304 21,770 22,411 [10]
23,259 23,058
(D=A+B-C)
E: Total land under
rehabilitation at all 8,791 9,145 10,023 10,783 11,653 12,315 12,714 13,470 14,242 14,746
[11]
operations (ha) [2]
F: Annual ratio of
rehabilitation to 0.77 0.84 0.76 0.6 0.71 0.75 [7] 0.64 0.89 0.61 1.36
disturbance (C:B) [3]
G: Overall proportion
of disturbed land 32.7% 33.3% 34.9% 33.9% 35.4% 36.1% 36.2% 37.4% 37.9% 39.0%
rehabilitated
Other Managed
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Land [5]
Estimate of total
biodiversity offset 10,973 13,164 22,607 22,773 25,466 41,768 41,139 41,803 43,689 41,034
[13]
land (ha)
Estimate of total
managed agricultural 57,533 60,174 44,252 44,632 40,146 59,320 59,212 59,209 59,160 52,788
[14]
land (ha)
Estimate of total
buffer land (ha) [9]
N/A N/A N/A N/A N/A N/A 47,063 47,179 48,175 41,629
Note: Please see over the page for Contextual Notes that provide further information to the figures in the above table.
Upper Hunter Mining Dialogue Temporary and Final Rehabilitation Principles and Commitments
All Dialogue member companies have agreed to a set of common principles and commitments, developed by the Joint Environment Working Group, to encourage
improvements in the speed of rehabilitation and to provide aggregate data to the community about total land disturbed and rehabilitated. The Principles are as follows.
1. Include rehabilitation planning in mine planning - Planning for rehabilitation should be integrated into the mine planning process and should include allocating
adequate and dedicated resources to achieve the planned rehabilitation outcomes.
2. Undertake progressive rehabilitation - Companies should undertake rehabilitation progressively, with the objective of ensuring that rehabilitation is as close as
possible to active mining.
3. Minimise time that disturbed areas are left without vegetation - Companies should actively seek to minimise the time that land is left without cover during mining.
This should include:
• Taking steps to ensure that rehabilitation is commenced within 12 months of land becoming available for rehabilitation.
• Utilising methods of temporary rehabilitation*, such as aerial seeding of overburden and other disturbed areas where permanent rehabilitation has not commenced.
4. Prioritise areas of rehabilitation and temporary cover to reduce impacts - Companies should prioritise rehabilitation and temporary cover in those areas where
leaving land exposed will have the most impact. The following areas should be considered to have priority:
• Areas that have the greatest impact on visual amenity, such as areas that face townships, residences, or the highway
• Areas that have the potential to generate dust leaving the site.
• Areas that are important for biodiversity, such as rehabilitation adjoining or providing connectivity to remnant vegetation.
5. Meet target for rehabilitation progress identified in the Mining Operations Plan - Each company should meet the annual target for rehabilitation quantity (area) set
in the Mining Operations Plans for each of its mines.
6. Set quality targets for rehabilitation in the Mining Operations Plan and implement a monitoring program to measure performance - Each company should
include quality targets for the various types of rehabilitation in the Mining Operations Plan for each of its mines. A monitoring program to measure the performance of
rehabilitation areas against the quality targets should be implemented at each of its mines.
* Temporary rehabilitation describes reshaping, revegetation and other rehabilitation techniques that are used for purposes other than final rehabilitation. This includes
such initiatives as seeding overburden emplacement areas, which are only temporary, to reduce erosion.