Professional Documents
Culture Documents
FOR
REVISION & EXPANSION
OF
GROUP HOUSING PROJECT
LOCATED AT
PLOT NO. 08/ GH-01, SECTOR – 08,
SIDDHARTH VIHAR, DISTRICT: GHAZIABAD,
STATE: UTTAR PRADESH
PROJECT PROPONENT
M/s T&T Realtech Pvt. Limited
Revision & Expansion of Group Housing Project
Plot No.: 08/GH-01, Sector-08, Siddharth Vihar,
District: Ghaziabad, State: Uttar Pradesh CONCEPTUAL PLAN
INTRODUCTION
Now, the project proponent proposed to revise and expand its group housing project located
at Plot No.: 8/GH-01, Sector-08, Siddharth Vihar, District: Ghaziabad, State: Uttar Pradesh.
As per revision and expansion the plot area same i.e 29,625m2, ground coverage increases to
7810.48 m2 and built-up area increases to 2,09,804.250 m2.
As per the EIA Notification S.O. 1533(E) dated: 14 th September, 2006 and its subsequent
amendments thereof, the built-up area of the proposed project is more than 1, 50,000 m 2 and
is Categorized as B “8(b)”. The cost of the revision and expansion of the project is 94.50
Crore.
The project will have following facilities:
1. Residential Apartments
2. Community and Social Centre
3. Commercial Building
4. Landscape Area
CONNECTIVITY
AREA STATEMENT
Table 2: Detailed & Comparative Area Statement
S.No. Particulars EC Accorded Area After Revision &
(m2) Expansion (m2)
1. Total Plot Area 29625 29,625
2. Permissible Ground Coverage 10,368.75 10,368.75
3. Proposed Ground Coverage 7304.57 7810.48
4. Total Permissible F.A.R 83,576.37 1,27,872.73
5. Total Proposed F.A.R 86164.41 1,27,771.46
6. Total Non F.A.R Area 63076.49 82,032.79
7. Total Built Up Area 1,49,240.90 2,09,804.250
POPULATION DENSITY
The population breakup after post revision and expansion of the project are provided below:
Table 2: Comparative Population
S.No. Particulars EC Accorded Area After Revision &
Expansion
1. Dwelling Unit 495 746
2. Residential Population 2,475 3730
3. Total Population 4172 4985
a. Staff @20% 35
WATER REQUIRMENT
The water during operation phase will be provided through the Awas Vikas Parishad. The
total water requirement is approx. 389 KLD, out of which total domestic water requirement is
340 KLD. The total fresh water requirement is approx. 248 KLD. The water requirement for
the construction phase will be 2.93ML and the demand for the same will be provided by the
nearby CSTP. The water requirement calculation is given below in Table 4 & 5:
4.
Waste water Generation 250 KLD 300 KLD
5.
STP Capacity 300 KLD 360 KLD
6.
Recycled water Generation 200 KLD 200 KLD
HORTICULTURE 39 KLD
(39 KLD)
10 KLD
Swimming pool Make-Up
(10 KLD)
Fresh Water
Waste Water
Treated Water
Fresh Water
Waste Water
Treated Water
It is expected that post revision and expansion of the project approx. 300 KLD of waste water
will be generated. The waste water will be treated in the STP of 360 KLD capacity. After the
treatment of waste water approximately 240 KLD treated water will be generated. Among
with 141KLD of treated water will be used for flushing and horticulture within the project
and surplus treated water will be discharged to the nearby sewer line or will be given for
nearby construction activities.
MBBR Technology
As per water balance diagram, 300KLD sewage will be generated in operation phase and
same will be treated by a 360 KLD capacity MBBR based STP resulting in generation of 240
KLD of treated water. Treated water will be used for horticulture and Flushing. It is proposed
to installed Moving Bed Biofilm Reactor (MBBR) type sewage treatment plant of 360 KLD
of capacity.
Process Description:
Design of STP
Approximately 300KL per day sewage/waste water will be generated from the proposed project. All
quantum of generated sewage will be treated in well-designed in-house sewage treatment plant. After
meeting stipulated standards, treated waste water will be utilized for flushing purpose and horticulture
purpose.
The sewage shall be collected by gravity into the collection tank/equalization tank of Sewage
Treatment Plant (STP) via perforated screens to prevent the large particles into system. In
equalization tank, pH and temperature of incoming sewage will be equalized. The sewage from
equalization tank will be pumped to Moving Bed Biofilm Reactor (MBBR) reactor for
Project Proponent: Page 10 Environment Consultant:
M/s. T&T Realtech Pvt. Ltd. Ambiental Global Private Limited
Revision & Expansion of Group Housing Project
Plot No.: 08/GH-01, Sector-08, Siddharth Vihar,
District: Ghaziabad, State: Uttar Pradesh CONCEPTUAL PLAN
biological treatment, where required quantity of air will be supplied to meet the oxygen
requirements by means of blower and fine bubbles air diffusers. In MBBR reactor, thousands
of polyethylene biofilm carriers operate in mixed motion within an aerated wastewater
treatment basin. Each individual bio carrier increases productivity through providing protected
surface area to support the growth of heterotrophic and autotrophic bacteria within its cells. It
is this high-density population of bacteria that achieves high-rate biodegradation within the
system, while also offering process reliability and ease of operation. After MBBR reactor,
sewage will flow by gravity to settler (tube type or equivalent) where sludge will be settled at
the bottom due to gravity. There will be provision for sludge recirculation, if needed. This
settled sludge may be recycled through sludge pump to MBBR reactor to meet the mixed
liquor suspended solids (MLSS) requirement. Excess sludge will be discharged through a filter
press where solid and liquid will be separated. The sludge collected with has low moisture and
after drying can be used as manure. The collected liquid will be recirculating through the
system. Final discharge of treated waste water from settler will be collected in chlorine contact
tank, where some chlorine will be dosed for disinfections of treated waste water. Then, treated
sewage will be pumped for tertiary treatment through duel media filter or it will be passed
through Ultraviolet (UV) disinfection system. Treated sewage will meet the norms prescribed
by Environmental (Protection) Rules,1986, Schedule VI for Discharge to Inland Surface Water
but will be utilized for flushing and horticulture.
Design Parameters:
Screen Chamber:
Prior to the actual treatment of the wastewater, a screen chamber will be provided. In this
chamber removable type mechanical bar screens will be provided for removal of various large
size elements, such as paper, cloth, plastic etc., which may hamper the satisfactory functioning
of subsequent units of the STP, if not removed at early stages.
Equalization Tank
As the quantity of the flow is non-uniform in nature, an equalization tank will have to be
provided. By the provision of an equalization tank, wastewater characteristics will become
homogeneous in nature and, therefore, better treatment can be achieved in the subsequent units
of the STP. Diffused aeration will be provided in this tank to stir the contents of the tank
completely.
Rainwater harvesting (RWH) is the collection and storage of rain, rather than allowing it to
run off. Rainwater is collected from a roof-like surface and redirected to a tank, cistern, deep
pit (well, shaft, or borehole), aquifer or a reservoir with percolation. Rainwater harvesting
differs from storm water harvesting as the runoff is collected from roofs, rather than creeks,
drains, roads or any other land surfaces. Its uses include watering gardens, livestock,
irrigation, domestic use with proper treatment, and domestic heating. The harvested water can
also be committed to longer-term storage or groundwater recharge.
Rainwater harvesting is one of the simplest and oldest methods of self-supply of water for
households, and residential and household scale projects usually financed by the user.
However, larger systems for schools, hospitals and other facilities can run up costs only able
to be financed by companies, organization and governmental units.
The storm water collection system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary area
and the time required for such flow to reach the drains. The drains shall be located near the
carriage way along either side of the roads. Taking the advantage of road camber, the rainfall
run off from roads shall flow towards the drains. Storm water from various plots/shall be
connected to adjacent drain by a pipe through catch basins. Therefore, it is proposed to provide
8 RWH pits at selected locations, which will catch the entire run-off from roof top area.
1) Since the existing topography is congenial to surface disposal, a network of storm water
pipe drains is planned adjacent to roads. All building roof water will be brought down
through rain water pipes.
2) Proposed storm water system consists of pipe drain, catch basins and RWH pits at regular
intervals for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement storm
water storage tank. This water will be pumped out to the nearest external storm water drain.
4) Peak Hourly rainfall of 50 mm/hr shall be considered for designing the storm water drainage
system.
Rain water harvesting will be catered to and designed as per the guideline of CGWA. Peak
hourly rainfall has been considered as 50 mm/hr. The recharge pit of diameter 2.6 m and depth
of 2 m will be constructed for recharging the water. The bottom of the recharge structure will
be kept 5 m above confined aquifer level. At the bottom of the recharge well, a filter media is
provided to avoid choking of the recharge bore. Design specifications of the rain water
harvesting plan are as follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags
and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is flushed
off.
No sewage or wastewater would be admitted into the system.
No wastewater from areas likely to have oil, grease, or other pollutants has been connected
to the system.
Recharge pits of suitable numbers will be provided for recharge of ground water potential. A
total of 7 rain water harvesting pits will be constructed. The quantity of storm water load for
the proposed construction project is given below:
Calculation for Run-off :
Plot Area = 29,625 m2
Roof top area = Ground Coverage = 7,810.48 m2
Runoff Load-
Roof-top area = Ground coverage * Runoff coefficient * Average Annual Rainfall
Adequate provision will be made for car/vehicle parking at the project site. There will also be
adequate parking provisions for visitors so as not to disturb the traffic and allow smooth
movement at the site.
PARKING REQUIRED AS PER MoEF&CC
PARKING PROPOSED: -
S.No. Parking Type Area Area per ECS Total parking
Provided (ECS)
1 Stilt Parking 895.44 23 32
2 Basement-1 22,997.44 30 719
3 Basement-2 23,301.76 30 728
POWER REQUIREMENT
Power will be supplied by Uttar Pradesh Power Corporation Limited (UPPCL). The total
connected load for the entire group housing project will be approx. 2,150 kVA which will be
supplied by 2 transformers of capacity (2,000 + 800 kVA) at 85% load.
Details of D.G Sets
Two Nos. of DG sets of total capacity 1,350 kVA (600 kVA + 750 kVA) will be provided for
entire group housing project at the project site for power back up. DG sets are open to air &
will be provided with acoustic enclosure. Power back-up is 85%.
Solid waste would be generated both during the construction as well as during the operation phase.
SOLID WASTE GENERATION
The following steps were proposed to be followed for the management solid waste:
Construction yards are proposed for storage of construction materials.
The excavated material such as topsoil and stones was stacked and reused for other
stages of construction.
Excavated top soil was stored in temporary constructed soil bank and reused for
landscaping of Residential Complex.
Remaining soil shall be utilized for refilling / road work / rising of site level at
locations/ selling to outside agency for construction of roads etc.
Same steps as above are to be followed for the Solid waste management of the
remaining part of the construction
Solid Waste
Construction
Waste
Construction Empty
waste, Excavated
Cement Soil
Broken Bricks,
Waste Plaster
Used in re-filling, Top soil conserved for landscaping, balance used in re- filling
Raising site level
During the operation phase, waste will comprise domestic as well as agricultural waste. The solid
waste generated from the project will be mainly domestic waste and estimated quantity of the waste
shall be approx. 1,582 kg/day (@ 0.50 kg per capita per day for the dweller, @0.15 kg per capita per
day for the visitor, @ 0.25 kg per capita per day for all kind of staffs, landscape wastes @ 0.2
kg/acre/day). Following arrangements will be made at the site in accordance to Solid Wastes
Management Rules, 2016 and its subsequent amendments till today.
Table No. :- Comparative Soildwaste Generation
S.No. Particulars As per EC Accorded After Revision & Expansion
E-waste will be managed as per E-waste (Management & Handling Rules, 2011) and its
subsequent amendments. It will be handed over to SPCB approved vendors.
Treatment of waste
Bio-Degradable waste:
1. Bio-degradable waste will be subjected to composting through Organic Waste Converter
and the compost will be used as manure.
Disposal
Recyclable and non-recyclable waste will be disposed through a local approved vendor. Solid
waste management Scheme is depicted in the following figure:
Waste Generation:-
Biodegradable waste generated = 60% of the total solid waste 2086 kg/day
= 1251.6 kg/day
Area Requirement:
= 14.63say 14.63m2
= 17.43m2
GREEN AREA
Landscape area for the project of the group housing will be developed as per the MoEF&CC
and Ghaziabad bye-laws. Total green area measures 6,446.24 m 2 i.e. 21.76% of the total plot
area. Indigenous trees will be prepared for the plantation and samplings will be purchased
from government nursery or government approved nursery.
As per MoEF&CC norms, no. of trees required:
= 1Tree/80 m2
= 6446.24 /80 = 81 Trees
Number of trees proposed: 100 trees
2. Delonixregia Gulmohar
5. Polyalthialongifolia Ashok
6. Azadirachtaindica Neem
7. Ficusretusa Ficus
8. Saracaindica Ashoka
(ix) Hoist
(x) Labor Lifts
(xi) Pile Boring Machines
(xii) Concrete pressure pumps
(xiii) Mobile transit mixer
(xiv) Dumper