Professional Documents
Culture Documents
DITINJAU OLEH
Nama Jabatan Tanda Tangan
DISETUJUI OLEH
Nama Jabatan Tanda Tangan
Amount (IDR)
No Description Remark
Option #1 Option #2
1 Indirect Cost 15.421.839.385,6 14.260.549.975,3
2 Direct Cost
- Ninian Bridge 30.741.674.392,7 36.050.782.969,6
- Underpass Multi Plate Super Span 13.320.723.851,9 -
- Underpass Box Culvert - 4.693.645.531,2
Total 59.484.237.630,2 55.004.978.476,1
Contigency 30% 17.845.271.289,1 16.501.493.542,8
Grand Total 77.329.508.919,2 71.506.472.018,9
COST ESTIMATION
NINIAN BRIDGE 10 M X 25M - DOUBLE BRIDGE & UNDERPASS
OPTION 1
No Description of Works Unit Quantity Unit Price (USD) Amount (USD) Remark
A INDIRECT COST
Preliminaries
Mobilization/Demoblization, the contractor's general obligations for all charges in respect of
1 Ls 1,0 35% x Direct Cost 1.063.575,13
the establishment of the contractor's organization, camps, equipment ,personnel.
TOTAL INDIRECT 1.063.575,1
B DIRECT COST
B1 BRIDGES
Earthworks
Clear & Grubbing ; Clear trees, bushes, undergrowth and grub stumps with diameter
1 >300mm within the area to be stripped. Windrow/stockpile debris at perimeter of cleared Ha 1,1 6.522,31 7.256,09
areas
Topsoil stripping & spreading ; Strip nominal 0-300mm thick and spread to
2 M2 11.125,0 - - included
windrow/stockpile adjacent to embankments and bare areas
3 Cut & Fill; Excavate & haulage of earthworks up to 1Km (fill area or disposal area) M3 967,4 2,31 2.236,84
Backfilling and compacting as described; backfill selected material and shall complied with
4 M3 3.812,4 19,94 76.020,91
technical spesification
Supply and install embankment stabilization using non woven geotextile 1 layer (asume at
5 M2 1.100,0 4,71 5.175,59
swampy area or soft soil which to be treated as soil improvement)
Foundation
6 Precast Concrete Spun Piles Dia 500 included pitch handling & pile driving M 1.680,0 122,40 205.628,87
7 Pile Test Ls 1,0 3.448,28 3.448,28
Structure
8 Steel structure SM 490 for composite girder and steel truss module Kg 107.994,4 3,79 409.500,69
9 Reinforced concrete fc'30 (include formwork expose) M3 456,6 558,81 255.123,12
10 Gabion (Bronjong) M3 360,0 140,24 50.485,94
Accessories
11 Guard railing post dia 3" M 50,00 47,98 2.399,06
12 Elastomeric bearing pad Ea 12,00 467,46 5.609,56
13 Asphalticplug M 22,00 142,00 3.124,09
14 Marka thermoplastic M 50,00 15,98 799,00
15 Kerb - concrete fc'30 M3 50,00 558,81 27.940,33
16 Lighting PJU 65 watt Ea 2,00 279,81 559,62
Pavement Asphalt
17 Tack Coat - Aspal Emulsi Liter 137,50 1,77 243,55
18 Asphalt AC - WC Ton 25,52 176,58 4.506,20
Sub Total 1.060.057,7
Sub Total - 2 Ninian Bridges 2.120.115,5
B1 UNDERPASS - 100 meters length
1 Subgrade preparation M2 800,00 0,39 310,57
2 Aggregete Base C M3 400,00 71,81 28.724,64
3 Multiplat Superspan L=11m H: 5m M 100,00 7.762,98 776.297,85
4 Concrete fc 30 - Wing Wall M3 137,28 595,30 81.722,41
5 U-Ditch M 200,00 158,08 31.615,14
Sub Total 918.670,6
TOTAL DIRECT 3.038.786,1
TOTAL INDIRECT + DIRECT 4.102.361,2
CONTINGENCIES (30%) 1.230.708,4
GRAND TOTAL 5.333.069,6
Note : 1$ : Rp14.500
COST ESTIMATION
NINIAN BRIDGE 10 M X 25M - DOUBLE BRIDGE & UNDERPASS
OPTION 2
No Description of Works Unit Quantity Unit Price (USD) Amount (USD) Remark
A INDIRECT COST
Preliminaries
Mobilization/Demoblization, the contractor's general obligations for all charges in respect
1 Ls 1,0 35% x Direct Cost 983.486,21
of the establishment of the contractor's organization, camps, equipment ,personnel.
Sub Total 983.486,2
B DIRECT COST
B1 BRIDGES
Earthworks
Clear & Grubbing ; Clear trees, bushes, undergrowth and grub stumps with diameter
1 >300mm within the area to be stripped. Windrow/stockpile debris at perimeter of cleared Ha 1,7 6.522,31 11.319,48
areas
Topsoil stripping & spreading ; Strip nominal 0-300mm thick and spread to
2 M2 17.355,0 - included
windrow/stockpile adjacent to embankments and bare areas
3 Cut & Fill; Excavate & haulage of earthworks up to 1Km (fill area or disposal area) M3 1.297,1 2,31 2.999,40
Backfilling and compacting as described; backfill selected material and shall complied with
4 M3 12.303,1 19,94 245.326,77
technical spesification
Supply and install embankment stabilization using non woven geotextile 1 layer (asume at
5 M2 1.100,0 4,71 5.175,59
swampy area or soft soil which to be treated as soil improvement)
Foundation
6 Precast Concrete Spun Piles Dia 500 included pitch handling & pile driving M 1.680,0 122,40 205.628,87
7 Pile Test Ls 1,0 3.448,28 3.448,28
Structure
8 Steel structure SM 490 for composite girder and steel truss module Kg 107.994,4 3,79 409.500,69
9 Reinforced concrete fc'30 (include formwork expose) M3 456,6 558,81 255.123,12
10 Gabion (Bronjong) M3 360,0 140,24 50.485,94
Accessories
11 Guard railing post dia 3" M 50,00 47,98 2.399,06
12 Elastomeric bearing pad Ea 12,00 467,46 5.609,56
13 Asphalticplug M 22,00 142,00 3.124,09
14 Marka thermoplastic M 50,00 15,98 799,00
15 Kerb - concrete fc'30 M 66,00 558,81 36.881,23
16 Lighting PJU 65 watt Ea 2,00 279,81 559,62
Pavement Asphalt
17 Tack Coat - Aspal Emulsi Liter 137,50 1,77 243,55
18 Asphalt AC - WC Ton 25,52 176,58 4.506,20
Sub Total 1.243.130,4
Sub Total - 2 Ninian Bridges 2.486.260,9
B1 UNDERPASS
1 Subgrade preparation M2 256,00 0,39 99,38
2 Aggragete Base C M3 128,00 29,54 3.781,00
3 Concrete fc 30 - Concrete box culvert M3 296,10 490,73 145.306,32
4 Concrete fc 30 - Rigid pavemennt M3 89,60 456,70 40.920,11
5 Concrete fc 30 - Wall abutment M3 137,28 558,81 76.712,96
6 Concrete fc 30 - Plat M3 105,60 490,73 51.821,50
7 U-Ditch M 32,00 158,08 5.058,42
Sub Total 323.699,7
TOTAL DIRECT 2.809.960,6
TOTAL INDIRECT + DIRECT 3.793.446,8
CONTINGENCIES (30%) 1.138.034,0
GRAND TOTAL 4.931.480,8
Note : 1$ : Rp14.500
SUMMARY
COST ESTIMATION
SUPERVISION CONSULTANT - NINIAN BRIDGE PROJECT
Amount (IDR)
No Description Remark
Option 1 Option 2
I DIRECT COST 2.812.200.000,00 1.945.200.000,00
Personnel 2.812.200.000,00 1.945.200.000,00
II.1 Accommodation
No Description Unit Vol Duration Unit Price (IDR) Amount (IDR) Remark
A Site Transport
1 Operational car/LV (included fuel 15lt/day) unit.month 2 12 25.000.000,00 600.000.000,00 AJI estimation - mining standard
B Site Accomodation
1 Mess rental & operational unit.year 1 1 100.000.000,00 100.000.000,00 AJI estimation
2 Meal & drink & loundry man.month 9 12 3.000.000,00 324.000.000,00 AJI estimation
C Leave
1 Transportation to site - travel fare (return) trip 31,5 1 3.556.266,00 112.022.379,00 Flight GA Economy - (BJM-CGK)
2 Transportation - land travel (return) trip 31,5 1 500.000,00 15.750.000,00 Bandara - Site
D Inspection Test
1 Transportation to site - travel fare (return) trip 5 1 3.556.266,00 17.781.330,00 Flight GA Economy - (BJM-CGK)
2 Transportation - land travel (return) trip 5 1 500.000,00 2.500.000,00 Bandara - Site
3 Hotel day 10 1 500.000,00 5.000.000,00 estimation standard bintang 3
4 Meal allowance day 10 1 350.000,00 3.500.000,00 Inkindo 2021.
Total Sub Total 1.180.553.709,00
III.3 Reporting
No Description Unit Vol Duration Unit Price (IDR) Amount (IDR) Remark
1 Monthly report book 4 12 200.000,00 800.000,00 Inkindos 2021.
2 Final report book 4 1 800.000,00 3.200.000,00 Inkindos 2021.
3 Technical report - Witness Test book 4 3 750.000,00 9.000.000,00 Inkindos 2021.
Total Sub Total 13.000.000,00
Option 2
I.1 Personel
No Deskripsi Sat Vol Duration Unit Price Amount (Rp.) Remark
A Direct
1 Team Leader man.month 1 12 43.550.000,00 522.600.000,00 Inkindo 2021. Ahli Utama - 10 experience
2 Site Manager man.month 1 12 38.900.000,00 466.800.000,00 Inkindo 2021. Ahli Madya - 10 experience
3 Quality Control Engineer man.month 1 12 35.850.000,00 430.200.000,00 Inkindo 2021. Ahli Madya - 8 experience
4 Civil Inspector man.month 1 12 31.200.000,00 374.400.000,00 Inkindo 2021. Ahli Madya - 5 experience
5 Document Specialist & Admin man.month 1 12 7.400.000,00 88.800.000,00 Inkindo 2021. Supporting Staff
B Indirect
1 Driver/Pengemudi man.month 1 12 5.200.000,00 62.400.000,00 Inkindo 2021.
Sub Total 1.945.200.000,00
II.1 Accommodation
No Description Unit Vol Duration Unit Price (IDR) Amount (IDR) Remark
A Site Transport
1 Operational car/LV (included fuel 15lt/day) unit.month 1 12 25.000.000,00 300.000.000,00 AJI estimation - mining standard
B Site Accomodation
1 Mess rental & operational unit.year 1 1 75.000.000,00 75.000.000,00 AJI estimation
2 Meal & drink & loundry man.month 6 12 3.000.000,00 216.000.000,00 AJI estimation
C Leave
1 Transportation to site - travel fare (return) trip 21 1 3.556.266,00 74.681.586,00 Flight GA Economy - (BJM-CGK)
2 Transportation - land travel (return) trip 21 1 500.000,00 10.500.000,00 Bandara - Site
D Inspection Test
1 Transportation to site - travel fare (return) trip 3 1 3.556.266,00 10.668.798,00 Flight GA Economy - (BJM-CGK)
2 Transportation - land travel (return) trip 3 1 500.000,00 1.500.000,00 Bandara - Site
3 Hotel day 6 1 500.000,00 3.000.000,00 estimation standard bintang 3
4 Meal allowance day 6 1 350.000,00 2.100.000,00 Inkindo 2021.
Total Sub Total 693.450.384,00
III.3 Reporting
No Description Unit Vol Duration Unit Price (IDR) Amount (IDR) Remark
1 Monthly report book 4 12 100.000,00 400.000,00 Inkindos 2021.
2 Final report book 4 1 400.000,00 1.600.000,00 Inkindos 2021.
3 Technical report - Witness Test book 4 3 750.000,00 9.000.000,00 Inkindos 2021.
Total Sub Total 11.000.000,00